Public Water Access Advisory Board
Archive for 2007 meeting minutes
For minutes of specific meetings, click on the date below (pdf format):
- December
4, 2006
-
November 6, 2006
-
October 2, 2006
-
September 11, 2006
- August 2006 --
meeting cancelled
-
July 10, 2006
- June
19, 2006
- May
1, 2006
- April
3, 2006
-
March 6, 2006
- February
6, 2006
-
January 9, 2006
_____________________________
PUBLIC WATER ACCESS ADVISORY BOARD
MINUTES
Meeting of December 4, 2006
9:00 a.m. - NH Fish and Game Headquarters
Members Present: Thomas Quarles, Esq., Chairman;
Daniel R. Lynch, F&G; Carol Barleon, OEP; B. David Bryan; Representative
Duncan Chaplin; Brian Giles; Maynard Goldman, NHLA; Patricia Goodridge;
Cheryl Killam, GCD; Johanna Lyons, DRED; Allen K. MacNeil; Michael
Pillsbury, DOT; Dick Smith
Members Absent: Paul Blizzard; Jacquie Colburn,
DES; David Barrett, DOS; Senator John T. Gallus; Senator Joseph
D. Kenney; Representative John Klose; and Roger J. Bellerose, Sr.
Audience Members: Derek Durbin, NH Lakes Association
*****************************************************************************
MEETING CONVENED
Chairman Tom Quarles called the meeting to order
at 9:03 a.m.
AGENDA ITEMS
1. Approval of the November 6, 2006, Meeting
Minutes - Tom Quarles, Chairman
No changes were requested. Maynard Goldman moved
to approve the minutes of November 6, 2006 as presented, seconded
by Dunc Chaplin. The Board unanimously approved.
2. 2007 Meeting Schedule & Chair, Vice Chair
Appointments - Tom Quarles
Tom reported that on November 15, Governor &
Council designated Tom as Chairman of this board. Tom's term on
the board will expire in October 2007, however, it is his intention
to seek reappointment at that time.
Tom requested that members of the board consider
appointing a Vice Chairman. Allen MacNeil has offered to fill the
position and Tom felt it would be beneficial to have a prior Chairman
in this position. Any members wishing to speak with Tom regarding
this appointment may do so at any time prior to the January meeting
when a vote will take place.
Tom mentioned that it was time to set the schedule
for 2007. He stated a preference for keeping the meetings on the
first Monday of each month but is willing to entertain other ideas.
Members were asked to think about the schedule with a vote to take
place at the January meeting regarding meeting dates for 2007. It
was noted that the Next meeting would take place on January 8th.
3. NH Wildlife Journal - Tom Quarles
Tom questioned whether members wished to receive
the Wildlife Journal, which had at one time been sent complimentary
to members. It was the general consensus that members felt that
receiving the magazine was worthwhile in providing information about
and a connection to the Department other than through the board.
Dan reminded the board that these subscriptions are paid for through
access funds and are not actually complimentary. Back issues can
be obtained through Public Affairs with new subscriptions to be
sent to members beginning in January.
4. State Agency Reports for 2006 PWAAB Annual
Report - Tom Quarles
Tom requested that state agencies provide their
Annual Report to PWAAB by February 1, 2007. Time will be scheduled
at upcoming meetings to discuss these reports. Johanna Lyons of
DRED will provide a presentation to the board at the January meeting
regarding their annual report. Johanna's report will be sent to
members prior to the meeting to give them a chance to review and
ask questions.
5. Update on Winnisquam Access Site - Daniel
Lynch & Jacquie Colburn
Jacquie was not in attendance due to illness
so Dan Lynch provided the update.
It was noted that the next working group meeting
will be held on December 8th at 9:00 a.m. onsite. Dan reported that
the Wetlands permit had been submitted, and because it is a major
impact project, once tentatively approved by DES, there will be
a public hearing or public comment session scheduled. Once that
is complete DES will seek Governor and Council approval of the permit.
Once this is obtained, the Bureau of Public Works will initiate
the bid process. The Department hopes to have a contract in place
by March for work to begin in April 2007. At this time the federal
aid grant application is in process and should be submitted by mid-December,
with confirmation expected by February.
Tom questioned whether federal funding will be
used for the project. Dan noted that without federal funding it
would be difficult, but not impossible, to keep this project moving
forward. The total cost of the project was questioned, and Dan reported
that total costs should be approximately $1.9 million when complete.
Tom further questioned the designation of other 2006 federal funding
and Dan responded that the project at Merrymeeting Lake could be
eligible for funding but it is uncertain at this time. Dan stated
that federal funds are also used for maintenance and refurbishment
of existing sites.
Pat Goodridge questioned how much land was purchased
for the Water Street access. Dan answered that the parcel purchased
from the City of Laconia was 1.4 acres. Pat also questioned the
cost of the land and Dan stated that the Department had paid $180,000.00,
which constitutes fair market value, as determined by a certified
appraiser.
6. DRED Access Matters - Plymouth/Common Man
Surplus Land - Johanna Lyons
Johanna noted that this item did not go through
the CORD process because the property was originally purchased with
federal highway funds, and so notification was not sent to DRED
by NHDOT when NHDOT decided to surplus this property. Discussion
needs to take place on how to better communicate within and between
agencies in cases such as this. The NHDRED Trails Bureau has had
conversations about this property regarding maintaining snowmobile
access. The Common Man is definitely willing to cooperate with allowing
snowmobile access to this property and in fact promotes it as such.
7. Baxter Lake, Rochester - Daniel R. Lynch, F&G
Dan briefly presented the completed project by
showing the project plans and pictures of the work in progress and
once complete. The only thing remaining to be done is paving of
the top of the ramp, which will be done in the spring. Brian Giles
commended the Department's limited use of impervious surfaces on
this project. Cheryl Killam questioned wheelchair accessibility
and stated she felt it would be important to formally designate
at least one wheelchair accessible parking space. Dan stated he
would follow up on this issue. Pat Goodridge questioned storm water
runoff issues. Dan noted that the site is designed so that any water
runoff would drain into the riprap beside the ramp or would run
back towards the parking area according to grade. Tom questioned
whether federal funding was used for this project. Dan reported
that the Memorandum of Agreement with NHDES was for approximately
$185,000 and that federal aid was used. It was also noted that this
site would need to be added to the list of access sites on the NHFG
website and new map. Carol Barleon will also update the OEP list
with this site information.
8. F&G Project Update - Daniel R. Lynch,
F&G
Dan Lynch provided an updated Boat Access Site
Status Matrix to the board and discussed the updates noted as follows:
1) Hilton Park (Dover) - Repairs have been completed.
2) Pleasant Lake (Deerfield) - Wetlands permit
received from NHDES, and approved by Governor & Council. Will
move forward with bids and contracting for work to begin Spring
2007.
3) Baker River (Plymouth) - Work by the NHFG
crew has begun, with the contractor scheduled to begin work later
this week.
4) Lambert Park (Hooksett) - Wetlands permit
application in process. NHDES has requested additional information,
to which NHFG is responding.
5) Winnipesaukee River (Northfield) - Tom questioned
what is planned for this site. Dan reported that an MOA is needed
with NHDOT to move forward. Will be discussed further at January
PWAAB meeting.
6) Connecticut River (Orford) - Dan will be more
aggressive in following up on this item. Will pursue discussion
with Town Selectmen rather than the lawyer to try to move this forward.
Will be discussed further at January PWAAB meeting.
7) Merrimack River (Nashua) - Tom questioned
a recent article in Hawkeye on this site, Greeley Park. Dan reported
that the City has been provided with a lease agreement that has
not yet been signed. At this time there is no vehicular RR crossing
in place. The city needs to be the one to push this issue forward.
Tom asked Mike Pillsbury to follow up with NHDOT's Rail & Transit
Bureau for discussion in January whether they have authority or
there is a process to force a private railroad to allow a crossing
for public use.
8) Stinson Lake (Rumney) - Allen MacNeil questioned
why the rocks in the water blocking existing ramp cannot be moved.
Dan responded that a wetlands permit is needed in order to do that,
and in order to get a permit a plan is required. 100% plans for
this site are expected to be complete in 2007.
9) Wild Goose (Sunapee) - NHDOT is once again
looking at traffic studies and roadway access issues. Dick Smith
questioned what could be done to help move this project forward,
and how to answer the questions of sportsmen who want to see this
project competed. Dan recommended first being patient. Secondly,
Dan recommended that these interested sportsmen be vocal and contact
their state representatives to voice their concerns and get things
moving again. Mike Pillsbury noted that since the site access driveway
will be from a town road versus a state road it is not NHDOT's call
where to put the access road. Dick stated he would try to get an
action group together to address this issue.
9. Access Opportunities: Sea Bees Bridge, Chesterfield
and Route 202 Peterborough - Tom Quarles and Mike Pillsbury
Sea Bees Bridge, Chesterfield - This site was
reviewed with NHFG as a possible access site, however, was found
to be too steep a grade to be acceptable. However, there is a path
fisherman frequently use there. Limited parking is available on
adjacent land owned by PSNH. Tom and Mike will discuss issues at
this site further.
Route 202 Peterborough - Logs are in the water
blocking access to the river. The road was put in for this access
as part of a NHDOT mitigation project, based on a local request.
It is unclear at this time who can handle debris removal from the
water. Johanna noted that it would be difficult to get a permit
for removal of the trees. Tom indicated that Marine Patrol's position
is that trees can be removed if they create a hazard to navigation.
Tom will speak with Mike further regarding access via the canal
in the area, which would avoid the debris issue. Tom will also discuss
this site with the Peterborough Conservation Commission.
10. Proposed Legislation - Pat Goodridge and Derek Durbin
Dan distributed a list of LSRs that NHDES will
be monitoring published as of November 30, 2006. More LSRs could
be added up until December 8, 2006. NHFG will also be putting forth
an additional LSR regarding a conservation decal requirement for
non-motorized boats, once a legislative sponsor is found. Jacquie
and/or Dan will provide an updated list for January.
Pat Goodridge stated she was not in favor of
a user fee for canoes/kayaks until powerboats pay their fair share.
She suggested that instead of the conservation decal for non-motorized
boats, a fee should be charged for motor boats according to the
horsepower of their motors, i.e. the bigger the motor, the larger
the fee (progressive tax). Pat will follow up with Jacquie Colburn
to determine if this type of fee has been successful in other states.
Dick Smith stated that he is in favor of the
conservation decal idea and said he would be happy to pay a small
fee for his canoes to help preserve the resources he enjoys. Pat
stated that her idea would raise more revenue for safety services
related to boating. Dick stated that NH waters are very safe when
compared to other states and he did not see funding for safety as
a need.
Pat Goodridge reported that the Big Island Pond
Corporation had not yet met, but will be meeting later in the week.
Big Island Pond Corporation will monitor the status of this proposed
legislation to put a state owned access site on this lake; although
it is possible the legislation could be withdrawn.
Derek Durbin reported that the Lakes Association
would be submitting legislation this week relative to the study
of leasing of state land. Other proposals mentioned included out
of state boat registrations and licensing of motorized watercraft
rental agents. Derek also noted that he would include PWAAB members
on the mailing list of the Association's publication, Lakeside.
Tom Quarles mentioned that he would ensure the NH Rivers Council
Newsletter will also be sent to PWAAB members.
11. Bass Tournaments - Dick Smith
Dick provided a brief presentation on the importance
of fishing and boating access to the NH economy. He stated that
in NH alone, boating, fishing and swimming adds $1.2 billion dollars
each year. Dick stated that bass fishing is the most popular type
of fishing in the United States, and that approximately 240,000
people fish in New Hampshire's freshwaters every year. Bass tournaments
are popular because Americans love a little friendly competition
as it is fun and also motivates us to further develop our skills.
The average bass club in NH has only about fourteen members and
so a tournament only includes about seven boats in most cases. Bass
tournaments have no negative biological impacts on the fisheries
as all tournaments are catch and release. Dick further discussed
what he felt were adequate access sites in terms of number of sites,
size of sites and designs that are friendly towards tournament participants,
and stated that on many lakes, especially Squam Lake, the access
is grossly inadequate.
Tom Quarles questioned how much NHFG regulates
the number of participants in bass tournaments. Dick stated there
are rules in place and the NHFG Conservation Officers have been
really tough on tournament directors regarding these rules. These
rules limit the number of participants to one half of the available
public access parking spaces. Dick stated that the limit is set
because there are many other users of these public waters and access
sites and the bass tournaments should not be allowed to dominate
all the spaces available. Carol Barleon stated lakes across the
country are dealing with these very issues and that there is a large
spectrum of lake use and carrying capacities and not all lakes are
equal. Diversity is necessary. Discussion of these issues will continue
at the January PWAAB meeting.
12. Signage Subcommittee - Tom Quarles
Due to the lateness of the hour, Tom deferred
this item for discussion in January.
13. Update on Harilla's Landing, Lake Winnipesaukee
- Tom Quarles
Tom noted that the sub-committee would be meeting
following this meeting.
Old Business - None at this time
New Business - Mike Pillsbury told members that
previous NHDOT representative Michael Burlage had returned safely
from active military duty in Iraq.
Representative Dunc Chaplin notified the board
that this would be his last meeting. He has very much enjoyed serving
the board and hopes his replacement will be immediate. Tom thanked
Dunc for his stellar attendance record and his participation on
the board.
Public Comment - None at this time
Adjournment
Carol Barleon moved to adjourn the meeting. Seconded
by Cheryl Killam. The Board unanimously approved. Meeting adjourned
at 11:50 a.m.
The next meeting will take place on January 8,
2007 at 9:00 a.m. in the East/West Conference Room at Fish and Game
Headquarters in Concord, N.H.
PWAAB Minutes
<Return
to top>
_____________________________
PUBLIC WATER ACCESS ADVISORY BOARD MEETING
MINUTES
November 6, 2006
9:00 a.m. - N.H. Fish and Game Headquarters
Members Present: Thomas
Quarles, Esq., Acting Chairman; Dave Mikolaities, NHFG; Carol Barleon,
OEP; B. David Bryan; Representative Duncan Chaplin; Jacquie Colburn,
DES; Maynard Goldman, NHLA; Patricia Goodridge; Cheryl Killam, GCD;
Johanna Lyons, DRED; Allen K. MacNeil; Michael Pillsbury, DOT; Dick
Smith
Members Absent: Paul
Blizzard; Brian Giles; David Barrett, DOS; Senator John T. Gallus;
Senator Joseph D. Kenney; Representative John Klose; and Roger J.
Bellerose, Sr.
Audience Members: Daniel R. Lynch, F&G; Derek Durbin, NH Lakes
Association
*****************************************************************************
MEETING CONVENED
Acting Chairman Tom Quarles
called the meeting to order at 9:04 a.m.
Chairman's Comments
Tom noted that currently
minutes and agendas are both emailed and sent hard copy via USPS.
He questioned members regarding the need to continue with sending
hard copies. General consensus was that email works fine, with Dunc
Chaplin requesting that hard copies continue to be sent to him.
Any other members wishing to continue to receive items via USPS
should contact Ellen Harrington to be included on the hard copy
mailing list. Otherwise only email will be sent. You can also contact
Ellen at 603/271-2225 should you at any time you feel you have missed
a mailing.
AGENDA ITEMS
1. Approval of the October
2, 2006, Meeting Minutes - Tom Quarles, Acting Chairman
No changes were requested.
Allen MacNeil moved to approve the minutes of October 2, 2006 as
presented, seconded by Mike Pillsbury. The Board unanimously approved.
2. Update on Winnisquam
Access Site - Daniel Lynch & Jacquie Colburn
Jacquie stated that the
working group met in October, with the two abutters in attendance
as well. Both abutters signed off on permission for the dredging
work that will need to take place once construction begins. Jacquie
further noted that Councilor Burton visited the site on October
19th along with several city officials, and that all went well.
The next working group meeting will be held on December 8th at 9:00
a.m. onsite.
As Dan Lynch was unable
to attend this meeting, Dave Mikolaities filled in for him as NH
Fish and Game's representative on the board. Dave reported that
design plans are 100% complete. He also stated that Hong Environmental
had completed the demolition of the Butler Buildings, and that the
next hurdle will be the wetlands permit application which will be
sent next week. The next step once that is approved will be the
Federal Aid grant application.
Cheryl Killam noted that
she had reviewed the plans and they appear to be in compliance with
accessibility regulations for parking and boat access, as well as
an accessible fishing pier.
Dave stated that the
Department is still hopeful that the bids can be completed this
winter in order for work to begin in the spring and be completed
for an August opening.
3. CORD - State Owned
Surplus Land, A.G.'s Opinion on LMAC/RMAC Authority - Tom Quarles
& Jacquie Colburn
Tom reported that the
Attorney General's Office has responded to the request of the LMAC
and RMAC regarding clarification of their degree of authority as
to disposal of state owned land.
Jacquie Colburn read
from the October 18th letter from Allen Brooks of the Attorney General's
Office:
"The Lakes Program Act and the Rivers Program Act do not provide
clear mandatory authority to the respective advisory committees.
The legislative history does not provide guidance sufficient to
give control over disposing state owned land to committees established
as advisory in nature. The statutes do require however, that the
recommendations of the advisory committees be received and considered."
Jacquie further elaborated
on the CORD process, which usually begins with the request of an
individual or a corporation interested in purchasing property owned
by a state agency. If the agency determines the property to be surplus,
the CORD process begins. CORD notifies all state agencies and the
county and municipality in which the property is located to determine
if there is any interest in these governmental entities obtaining
the property. CORD also notifies the LMAC, RMAC and PWAAB. The process
involves all of the above agencies/committees having the opportunity
to review and comment, as well as review by the NH Housing Finance
Authority. The NH Housing Finance Authority has the right of first
refusal, then it moves through the CORD process, then on to the
Long Range Capital Planning and Utilization Committee (LRCPUC) a
joint committee of the Legislature, then it goes on to Governor
and Council. However, some property owned by NHDOT, which was acquired
with federal or state highway funds is not required to follow this
process. NHDOT can move properties through this process much faster,
but is still required to allow review by RMAC and LMAC before moving
it along to the LRCPUC for review and approval before then moving
on to Governor and Council. The LRCPUC has the authority to override
or veto the recommendations of the above agencies and committees.
Currently there are three
properties involving requested leases on shorefront adjacent to
state railroad corridors still pending in the CORD process:
1) Sun Lake Village, on Lake Winnisquam in Belmont - CORD members
all recommended against disposal and it has been sent to the LRCPUC
where it has been put on hold.
2) Scenic Ledges, on Lake Winnipesaukee in Laconia - Has not been
brought before CORD at this time and according to a newspaper report
the owner has withdrawn the request.
3) Lake Waukeewan - a private citizen is looking to lease 75 feet
of frontage. This request has been through CORD and all members
have recommended against disposal, however, the LRCPUC did recommend
disposal.
Allen MacNeil questioned
whether there was an official form used to make these requests to
CORD. Jacquie stated that currently there is no form in place that
she is aware of, and offered to create such a form, as well as a
tracking sheet that can be used to follow the request through the
process. Allen further stated that in his opinion, if all agencies
and committees recommend against disposal, the LRCPUC should not
be able to override that decision. Jacquie then stated that because
the committees are advisory only in nature the LRCPUC does not necessarily
have to heed their recommendations.
Tom questioned whether
the LRCPUC or Governor and Council holds a public hearing on these
items or if they are simply part of the regular agenda for the committees.
Jacquie stated that she believed they are simply an agenda item
as she is not aware of any public hearings taking place.
Tom then questioned Derek
Durbin of the NH Lakes Association regarding any plans they may
have for the upcoming legislative session. Derek stated that their
organization was considering completing a land inventory to track
the uses of land, increasing the role of the advisory committees
to something a little more substantial, and possibly creating a
commission to study issues with disposal of state land. No decisions
have been made at this time but their legislative agenda will be
announced soon. Derek will report to Tom or Jacquie when further
information is available.
Jacquie then noted that
the Governor's Office had requested information from several state
agencies relative to land that is owned and maintained by each agency,
including how much is currently being leased by others.
4. DRED Access Matters
- Fall Mountain State Park and Plymouth/Common Man Surplus Land
- Tom Quarles and Johanna Lyons
Tom questioned if Johanna
had any input on the CORD surplus land review in Plymouth adjacent
to the Common Man restaurant. Johanna stated she did not have that
information but would check into the matter for discussion at next
month's meeting.
Tom asked Johanna to
describe the property listed as the Fall Mountain State Park in
DRED's PWAAB 2005 Annual Report. Johanna commented that Fall Mountain
State Forest (not Park) is a 943- acre parcel on the Langdon/Charleston
town line, consisting of two great ponds and three communities of
federally endangered species. The Nature Conservancy purchased the
land from New England Power Company and gifted the land to the state,
subject to a conservation easement. Pedestrian access, carry in
boating, and riding of snowmobiles in the winter on designated trails
are some of the activities allowed on the property.
5. F&G Project Update
- Daniel R. Lynch, F&G
As Dan Lynch was unable
to attend the meeting, Dave Mikolaities provided an updated Boat
Access Site Status Matrix to the board and discussed the updates
noted in red as follows:
1) Umbagog Lake (Cambridge)
- Repairs were scheduled to take place during the second week of
October, however, due to winter icing conditions causing extensive
damage the project will be changed to a complete refurbishment.
The intent is to use wider concrete planks, such as those installed
at Cedar Pond in Milan recently. The crew will wait to see how the
planks hold up through the winter at Cedar Pond before proceeding
with the repairs at Umbabgog Lake.
2) Baxter Lake (Rochester)
- Construction has been completed by NHDES's Dam Bureau but the
area will not be paved until spring due to the lateness of the season.
Tom requested that Dave provide photos of the site so the board
can see the accomplished project.
3) Hilton Park (Dover)
- Have not had the opportunity to proceed on this project as yet
but should be completing the work this month if the weather cooperates.
4) Pleasant Lake (Deerfield)
- Wetlands permit received from NHDES. Still waiting for Governor
and Council approval, hopefully by December.
5) Baker River (Plymouth)
- Contracts for the concrete grade beam construction and fabrication
of the steel handrail were approved by Governor and Council. At
this time we are waiting for the water to recede so work can begin.
Dave showed the board plans for the site and discussed the issue
of not extending the handrail to the bottom of the steps. It was
felt that due to siltation problems it would not be necessary to
install handrail for the bottom two steps. Allen MacNeil was in
agreement and offered to speak to the Plymouth Selectmen regarding
the decision.
6) Newfound Lake (Bristol)
- Dock ladders will be installed in Spring 2007. When total site
refurbishment is needed the dock will be redesigned and lowered.
Tom questioned whether the dock was equipped with reflective material
to promote snowmobile safety. Dave will look into this issue. (There
is a light installed at the site so the dock is fully visible at
night.)
Dick Smith questioned
if any progress had been made regarding the Wild Goose site on Lake
Sunapee in Newbury. Mike Pillsbury reported that to the best of
his knowledge there had been no further action. Dave noted that
the traffic study issue is still being addressed. Dave will research
progress and report at next month's meeting.
6. Proposed Legislation
- Big Island Pond, Hampstead (LSR-2007-S-0209-R) - Tom Quarles
As a long time resident
of the area, Pat Goodridge reported on the issue of legislation
regarding public access to Big Island Pond in Hampstead. A constituent
in the area is upset because a fee is charged for locked gate access
to the boat launch site and contacted Senator Barnes to see what
could be done. A $15.00 fee is charged yearly for a locked parking
area due to problems with theft and vandalism at the site. Pat has
spoken to Senator Barnes and has turned the proposal and information
over to the Executive Board of Big Island Pond Corporation for them
to handle as they are the entity that manages the launch site.
Pat stated that she had
also spoken to Senator Barnes about legislation regarding signage
of access sites, and questioned whether any of the legislators on
this board would be interested in co-sponsoring any such legislation.
Pat felt that legislation of this type should come from members
of this board, perhaps in concert with Senator Barnes. Pat also
felt that Director Perry should be consulted before moving forward
with this issue.
Tom stated that he did
not feel that legislation is necessary but that a group effort by
the agencies involved could bring this project to fruition. Dave
Mikolaities stated that this issue is more complicated than if first
appears. Currently, approximately half of NHFG's access sites are
signed with universal access signs. NHDOT was contacted regarding
signage and told NHFG that sign proliferation is a hot issue and
that a detailed plan of each and every sign location is necessary
and would need to be approved by NHDOT for state roads and by each
municipality involved for non-state roadways, prior to any signs
being erected. Also, the further in advance of the access site you
wish to place signs, the more signs are needed. With limited NHFG
maintenance staff available this would be a huge undertaking.
Dick Smith stated that
as tourism is a booming industry in New Hampshire that it's important
that signs be put in place to make it easier for tourists to find
their way to NH's available natural resources. Frustrated tourists
are not likely to leave with a favorable view of our beautiful state.
Dick also believes that a group agency effort could be effective
in making this initiative a reality. However, he also noted that
the information available online at the Fish and Game website needs
updating. Dave reported that this is in progress and that GIS information
is currently being gathered and that pending available funding,
new access maps should be available in 2007. Maynard Goldman reported
that the issue of signage on a statewide basis is the stuff of which
long novels could be written. He agreed that it is an important
initiative but that it would be important to have political support,
as there are likely to be many obstacles once the process begins.
As the issue of Bass
Tournaments seems to be raised often, Tom questioned whether NHFG
regulates the number of participants in these tournaments. Dick
Smith noted that Inland Fisheries of NHFG schedules these events
and the number of clubs allowed to hold a tournament on a lake is
determined by the size of the water body. Small lakes only allow
one club at a time, whereas larger lakes can handle several clubs
at the same time. Also, tournament participants are only allowed
to utilize half of the total number of parking spaces available
at access sites on each lake.
Tom stated that he will
soon be asking for volunteers for a Signage Sub-committee. Big thanks
to Dick Smith who was the first to volunteer. This item will be
put on the agenda for December in order to get input from Director
Perry.
Tom requested that a
member of the board keep apprised of and report on legislative issues
relevant to this board as they arise. Dunc Chaplin and Derek Durbin
both agreed to keep the board informed of any board related legislative
issues.
7. Update on Harilla's
Landing, Lake Winnipesaukee - Tom Quarles
Tom noted that the sub-committee
would be meeting following this meeting. NHDOT Bureau of Right of
Way is the lead agency working on the land swap. The Yacht Club
was asking for a fee interest rather than an easement, but has since
decided that an easement is fine so long as they have adequate access
and can gate the access for private use only. The process is moving
forward.
8. Long Term Projects
and Sub-committees - Tom Quarles
As the signage issue
was discussed earlier, Tom moved on to the other issue of accessibility
to public access sites as raised by Cheryl Killam. Cheryl felt that
with the help of a few board members she would be able to identify
accessible sites and note them on the OEP map but that a sub-committee
did not need to be formed to deal with the issue.
Old Business - None at
this time
New Business
Tom made the board aware
of a recent project in Tilton called Riverfront Park, dedicated
on September 9, 2006. Tom noted that this was once a factory, then
a superfund site but that visionary residents were able to create
a park with a canoe/cartop access onsite. There are parking and
bathroom facilities. It provides a take-out for a "quickwater"
stretch of the Winnipesaukee River, starting at the DOT informal
access site on Rt. 140 just south of Exit 20 off I-93. This river
stretch has water year round due to various hydro dams in the area.
Tom noted another project
on Route 9, SeaBees Bridge, on the Connecticut River between Chesterfield,
NH and Brattleboro, VT. The old bridge was left in place when a
new one was built. Tom believes the old bridge will be used as part
of a bicycle/pedestrian trail in the future. Route 9 on the N.H.
side is marked "no parking" but on nearby Bittersweet
Lane there is a dirt path that leads to the water. Tom questioned
whether the path could be used to access the water by canoe/cartop
boat and requested that Mike Pillsbury report back next month.
Tom further questioned
Mike Pillsbury regarding the Route 202, Peterborough widening project.
Tom noted that currently there is an informal access point to the
Contoocook River at the Route 202 and Scott Mitchell Road intersection.
Tom had previously spoken with Mike Burlage, NHDOT's former representative
to the PWAAB regarding this access site, and found that part of
the property necessary for access is owned by the Harris Center.
Separately, Tom noticed recently that about a mile upstream there
is a new access sign leading to parking at a NHDOT wetlands mitigation
site. However, access to the river is blocked by a downed tree.
Tom requested that someone at NHDOT work to improve access to the
river in this area, possibly using an old canal that is on one side
of the mitigation site. Mike Pillsbury will look into this issue
and report back next month.
Johanna Lyons noted that
the final meeting of the Study Commission of the State Park System
will be held on November 13th at 2:00 p.m. at the State House, Room
100, should anyone be interested in attending.
Other Items for Board
Consideration - None at this time
Public Comment - None
at this time
Adjournment
Carol Barleon moved to
adjourn the meeting. Seconded by Cheryl Killam. The Board unanimously
approved. Meeting adjourned at 11:15 a.m.
The next meeting will
take place on December 4, 2006 at 9:00 a.m. in the East/West Conference
Room at Fish and Game Headquarters in Concord, N.H.
<Return to top>
_____________________________
PUBLIC WATER ACCESS ADVISORY BOARD MEETING
MINUTES
October 2, 2006
9:00 a.m. - NH Fish and Game HeadquartersPUBLIC WATER ACCESS
ADVISORY BOARD
Members Present: Thomas
Quarles, Esq., Acting Chairman; Daniel R. Lynch, F&G; Jacquie
Colburn, DES; Dick Smith; Paul Blizzard; B. David Bryan; Brian Giles;
Allen K. MacNeil; Michael Pillsbury, DOT; Representative Duncan
Chaplin
Members Absent: Cheryl
Killam, GCD; Johanna Lyons, DRED; Maynard Goldman, NHLA; Carol Barleon,
OEP; Patricia Goodridge; David Barrett, DOS; Senator John T. Gallus;
Senator Joseph D. Kenney; Representative John Klose; and Roger J.
Bellerose, Sr.
Audience Members: Dave Mikolaities, NHFG
*****************************************************************************
MEETING CONVENED
Acting Chairman Tom Quarles
called the meeting to order at 9:06 a.m.
Chairman's Comments
Tom thanked Allen for
his years of service and stated at this time he will be the "Acting"
Chairman until confirmed by the Governor. Tom further stated that
Allen and himself had been in contact with the Governor's Office
and were informed that because the PWAAB statute states that a chairman
is to be "designated" by the Governor, Tom's elevation
to Chairman would therefore not need to be approved by the Governor's
Council.
AGENDA ITEMS
1. Approval of the September
11, 2006, Meeting Minutes - Tom Quarles, Acting Chairman
No changes were requested
so Allen MacNeil moved to approve the minutes of September 11, 2006
as presented, seconded by Brian Giles. The Board unanimously approved,
with Daniel Lynch abstaining.
2. Update on Winnisquam
Access Site - Daniel Lynch & Jacquie Colburn
Jacquie stated that the
working group did not meet in September, but that a meeting would
be taking place at Water Street on October 13th. At that point Jacquie
deferred to Dan for further update.
Dan reported that final design work is still in progress. Fay, Spofford,
& Thorndike (FST) is currently preparing the Wetlands and Site
Specific permits. The Wetlands Permit application requires three
abutters to sign off on acknowledgment of notification of the work
to take place within 20 feet of the property line. The three abutters
are Boulia-Gorrell Lumber Company, NHDES Wastewater Treatment Facility,
and Ralph Langevin, owner of Martel's. Another component requires
sign off by one abutter, Martel's, because the dredging will cross
the mid point of the channel. The goal is to have the applications
submitted by the end of October. NHDES will try to expedite the
permit process as much as possible. Submittal of the Federal Aid
Grant application is also in process. Environmental documentation
is being gathered for the application at this time. The grant should
take about 30 days for review and award notification, barring any
issues. Dan is hopeful that the project can be put out to bid by
December in order for construction to begin early in the spring
for completion by July.
Jacquie noted that at
the October 13th working group meeting the group should try to set
public hearing dates to help keep the process moving along.
Tom questioned if there
had been any further correspondence from Director Perry to Senator
Johnson since the August 24th letter. Dan responded that monitoring
well testing for contamination from the Boulia-Gorrell site had
been taking place regularly. A comprehensive testing report for
the seven monitoring wells, including historical data, was provided
in April 2006. Tests for well number seven, which is on NHFG property,
showed all tests below detection level, or substantially below acceptable
water quality standards, with the exception of the benzene testing
completed in April and July of 2005, which showed trace amounts.
This data is further substantiated by additional testing completed
by FST. Dan stated that there is no contamination issue at this
site. Anyone interested in seeing the testing report can contact
Dan for that information.
Dan also reported that
a request had come in via email, from a group called the Voting
Sportsmen, requesting information regarding how much had been spent
to date on this project and what the estimated completion costs
will be. The email also requested information regarding the cost
per parking space for this project in comparison with the cost per
parking space at Hilton Park in Dover, and how much of these costs
are being borne by the sportsmen. Dan presumed this request was
from the same group that had requested the information regarding
contamination at the Water Street site. Dan stated that the two
sites cannot be compared as one was a refurbishment project on property
already owned by the state, while the other is new construction
on recently purchased property. Brian Giles noted that there really
is no comparison between the two sites as one was a concept that
has never become reality while the other is well underway.
Allen MacNeil stated
that Voting Sportsmen is the same person who had contacted him regarding
this site that he had spoken about at last month's meeting. Allen
further stated that if this person had all his facts straight there
would be no issue. The question was previously asked and has been
answered as this person has called and spoken to several of the
board members. Allen urged board members to use caution when speaking
with this individual as he is just trying to muddy the waters with
his questions. Allen noted that if contacted, the best approach
may be to ask the individual to contact Acting Chairman Quarles
or Dan Lynch.
3. Town of Franklin Request
(Boat Ramp Repairs) - Daniel Lynch, NHFG
Tom noted that he had
been contacted by a Franklin City Councilor regarding a city boat
ramp in need of repair. Dan contacted City Manager, Greg Doyon,
by telephone to discuss the request. Basically the city was just
exploring the option of the use of NHFG's 30-year lease agreement
and looking for information on the Department's statewide boat access
program. Dave Mikolaities and Rich Tichko visited the site and then
met with City Manager, Greg Doyon and provided him with a copy of
a use agreement, similar to the one pending with the City of Nashua.
Dave stated that the ramp is not in bad condition at this time,
and the location is fair, although shallow water can make launching
difficult at times. Tom Quarles questioned if the ramp is posted
as city resident use only? Dave believed use is limited to residents
only, although there were no signs posted. Jacquie Colburn noted
that Webster Lake is a fairly small lake, which has water quality
issues. The lake was closed several times this year due to toxic
algae blooms.
Tom asked Dan the status
of the agreement with the City of Nashua. Dan stated that the Use
Agreement template had been sent to Nashua but no agreement was
ever reached. Tom further questioned the use agreement with Orford.
Dan stated that this agreement is still in review by the town's
attorney. There are two questions that remain to be answered to
the town's satisfaction regarding when the agreement would take
effect and when repairs would be made. Questions regarding refurbishments
in the later years of the agreement and their effect on the terms
of the agreement are still unanswered. Allen MacNeil stated that
the voters of the Town of Orford had approved moving forward with
the use agreement, however the town has not yet completed their
review process. Allen further stated that most towns and cities
are not aware that such an option exists. Tom suggested that NHFG
put out some kind of press release to make municipalities in New
Hampshire aware of this option available through the NHFG, once
the agreement with either Orford or Nashua have been completed.
4. CORD - State-Owned
Land Surplus Land Review - Tom Quarles
Tom noted two concerns:
The first being the proposal by NHDOT to dispose of land in Plymouth,
adjacent to the Pemigewasset River (SP-P4600H Plymouth/Logan); and
the second being ensuring that the board is notified of these projects
that do not need to go through CORD review.
Jacquie Colburn reported that LMAC and RMAC are working to improve
communication, as some NHDOT requests no longer go through CORD
review. Jacquie thought the easiest way to ensure the board is notified
is to keep this topic as a monthly agenda item so she can report
on anything relevant that comes through those channels.
Regarding the land in
Plymouth, adjacent to the Pemigewasset River (SP-P4600H Plymouth/Logan),
the RMAC discussed this item in August and conditionally approved
disposal of this parcel. Compliance with the Shoreline Protection
Act, making note of a well on the property, and continued use of
the parcel by snowmobiles are the conditions recommended. Once sent
back to NHDOT by the LMAC/RMAC these items go to the House Long
Range Planning Committee and are eventually sent through Governor
and Council for approval of disposal. Tom questioned how the agency
goes about actually selling the property. Mike Pillsbury reported
that the originating bureau handles the sale. Jacquie noted that
usually it is an abutter requesting to purchase the property that
starts the whole process. Other state agencies and municipalities
are notified and have first option to purchase before property is
disposed of otherwise. Tom will follow up with Johanna Lyons regarding
DRED's position regarding this parcel.
Mike Pillsbury reported
that there is another parcel that he was asked to investigate at
last months meeting, which is going through the same disposal process.
The parcel is in Holderness, local abutters have asked for a 50-foot
strip of property between the road and their property. The property
does not provide access to the lake, it is requested only so beatification
of the area can be completed.
5. Webster Farm Conservation
Project Update - Daniel Lynch, NHFG
Tom requested an update
on the efforts to provide canoe/kayak access to the river closer
than the cemetery, even if only for drop off and pick up as opposed
to parking. Dan responded that the item had gone before Governor
and Council as a "Replacement Easement Deed" by the Society
for the Protection of NH Forests (SPNF). For the approximately $30,000.00
provided by the Department, we were able to protect the public's
right to access the river. Dan read at length the affirmative rights
of the easement holder. Basically, SPNF was not amenable to the
Department's request to go back to the landowner and request the
right to take vehicles further than the cemetery. The principal
interest in the easement was the agricultural aspect and it was
felt that moving the parking closer to the river would interfere
with the agricultural functionality of the property. Tom questioned
whether the Department would be maintaining the site and necessary
signage. Dave Mikolaities will follow up regarding signage to direct
the public to the appropriate parking area for access to the river.
Otherwise, there will be no improvements or modifications made to
the access site: it will remain as is.
Tom felt it was important
that a member of the board visit the site and investigate the ease
with which one could put in a canoe or kayak and requested that
anyone with the opportunity do so and report back to the board.
6. 2005 Annual Report
-Tom Quarles
Tom had several questions
regarding the 2005 Annual Report. Questions for NHDRED will be answered
at next month's meeting, as Johanna Lyons was unable to attend this
month.
Tom's question for NHDES
was in regards to "Surface Water Quality Assessments"
as relates to designated uses for swimming and aquatic life support.
Jacquie Colburn stated that these figures were part of the Clean
Water Act's reporting requirements to the EPA. The 305B Report is
a comprehensive report of all surface water quality assessments
for lakes, rivers, oceans, etc. The 303D List is a list of impaired
waters. All this information can be found on the NHDES website.
All NH bodies of water are given designated uses and NHDES is tasked
with assessing these water-bodies to see how well they support their
designated use. Some designated uses include: primary contact recreation,
secondary contact recreation, swimming, aquatic life support, shellfish,
and drinking water. There are a number of parameters that must be
tested to aid in determining impairment for those designated uses.
There are many different things that can be considered impairments,
such as non-native aquatic plants, dissolved oxygen levels, sedimentation
and siltation. Jacquie noted that this process is ongoing and it
will take many, many years to fully assess all bodies of water in
NH. The data provided in the 2005 Annual Report was from the 2004
report to the EPA, and the information for the 2006 Annual Report
will be significantly updated as the report to EPA is due this year
as well. Brian Giles noted that this information, as provided, was
very alarming. Jacquie restated that this information is available
to the general public through the NHDES website. Jacquie suggested
that a meeting or two be set aside to go over the Annual Report
soon after it is provided, rather than waiting until someone has
questions.
Tom questioned whether
this information, as reported to the EPA, constituted violation
of the Clean Water Act. Jacquie stated that she would need to follow
up and would report on this in the 2006 Annual Report. Jacquie offered
to provide a presentation to the board at a later date to explain
this process and the data collected and what it all means in regards
to water quality.
Allen MacNeil noted that
in addition to the state agency representatives, any of the special
interest group representatives on the board are welcome to provide
information for the Annual Report as well.
Tom asked Dan Lynch to
provide clarification of the following statement from the Annual
Report: "During Calendar Year 2005, one new boat access site
was completed; two major access projects were under active planning
and pre-construction activities; a number of existing sites were
evaluated for improvements; an easement was secured; several properties
were evaluated for future acquisition or development; and 134 existing
sites were maintained. The Statewide Public Boat Access Program
expended $872,616.37 in 2005." Dan reported that the new access
completed was at Hawkins Pond in Meredith; the two major projects
under active planning were Lake Winnisquam and Merrymeeting Lake;
existing sites evaluated are discussed further on in the report;
and the easement secured refers to Hoyt Pond in Madbury. Dan briefly
discussed the particulars of this easement. The total expenditures
as listed were designated as follows: 'Transfers to Other State
Agencies' in the amount of $187,400.00 was to the NHDES Dam Bureau
for construction of the Baxter Lake Dam and access site in Rochester;
'Personal Services-Temporary' in the amount of $57,413.60 was payroll
for the seasonal maintenance personnel; and 'Reimbursement' in the
amount of $167,030.48 was payroll for Access Program personnel.
Tom questioned the total amount of the Statewide Boat Access Program
fund. Dan noted that this amount is approximately 1.5 million of
state dollars and approximately the same amount from the federal
side, for a total of $3,000,000.00. Tom suggested that on the 2006
Annual Report the amounts for both state and federal funding be
provided.
7. F&G Project Update
- Daniel R. Lynch, F&G
Tom requested an update
on the proposed access at Sunapee. Dan responded that the Town of
Newbury had requested that NHDOT re-review the traffic study but
Dan has not heard anything further. Dan stated that NHFG had not
pushed this issue due to staff being very busy with other sites
at this time. Dan is hopeful that once Winnisquam is well on its
way then we can move forward with Sunapee.
Dan stated that Dave
Mikolaities has been doing an outstanding job of keeping these projects
moving forward. Dave provided an updated Boat Access Site Status
Matrix to the board with updates noted in red.
1. Millsfield Pond (Millsfield)
-Repairs have been completed. Erosion and sedimentation issues have
been addressed. The timber company we lease this property from is
looking to possibly subdivide into lots. We need to ensure that
we do not lose this newly refurbished site.
2. Cedar Pond (Milan)
- Repairs have been completed.
3. Umbagog Lake (Cambridge)
- Repairs are scheduled to take place during the second week of
October.
4. Baxter Lake (Rochester)
- Construction is being completed by NHDES's Dam Bureau. Should
be completed by November 1, 2006.
5. Hilton Park (Dover) - NHDOT has received the permit for repairs
and work should be completed this fall.
6. Spectacle Pond (Meredith)
- Parking area has been formalized and signage is in place. Project
complete.
7. Pleasant Lake (Deerfield)
- Wetlands permit received from NHDES, but still awaiting 20-day
comment period, then will go forward to Governor and Council for
approval. Bids for tree cutting and pavement of the parking area
will be put out this fall for Spring 2007 repairs.
8. Baker River (Plymouth)
- Contracts for the concrete grade beam construction and fabrication
of the steel handrail are scheduled for Governor and Council review
on October 11, 2006. Work should begin soon after if contracts are
approved.
9. Eagle Pond (Wilmot)
- Tom questioned if there was room for multiple vehicles to cross
the highway and then the railroad tracks. Dan noted that a land
agent is working with NHDOT Rail and Transit Bureau to resolve this
issue.
10. Newfound Lake (Bristol)
- Allen MacNeil questioned when repairs at this site would be addressed.
Dave noted that instead of lowering the dock, ladders could be added,
similar to the Water Street site design and that repairs may take
a year or two as NHFG's limited construction staff is very busy
at other sites. Dan stated that snowmobile safety is also an issue
here and Tom questioned whether the dock was equipped with reflective
material. Dave will look into this issue.
8. Update on Harilla's
Landing - Tom Quarles
Tom is waiting to hear
from Attorney Cronin for the Yacht Club who is to speak with Paul
Goodwin, the contractor's representative, to discuss the wetland's
permit for dock reconstruction and other Phase One proposals. Attorney
Cronin is also meeting with NHDOT Bureau of Right of Way regarding
the land swap. The land swap will take a number of months to resolve.
Dick Smith questioned how many parking spaces would be available
at this site. Tom stated that the process has not really progressed
to that point yet but he expects at least 15 spaces or so. Roadside
parking will still be allowed as well. Dick believes that access
to Lake Winnipesaukee is critical and thought it would be a good
idea to have a brainstorming session to discuss creative options
for access in perpetuity to Lake Winnipesaukee. Tom noted that interested
sportsmen need to get involved in the legislative process, as this
board can be a catalyst, but cannot do everything.
Paul Blizzard noted that,
at least as far as Lakeport Landing is concerned, the issue is not
so much the fee for use of ramps, it is more the upkeep of the site
and the necessary services provided onsite that is the issue.
9. Long Term Projects
and Sub-committees - Tom Quarles
Tom noted that as both
individuals who requested special projects are not in attendance
today, he would briefly discuss the items and then wait until these
individuals are in attendance to move forward.
Pat Goodridge suggested
that all mapped sites, especially NHFG owned sites have proper signage
along the road to help promote their use. When Pat becomes an active
member of the board again she will be assigned as chairperson of
this subcommittee.
Cheryl Killam wanted
to have a list of access sites that are wheelchair accessible as
that information is not readily available at this time. Cheryl had
previously stated that she will only certify sites that she has
visited and confirmed as accessible. Cheryl will be appointed chairperson
of this subcommittee.
Chairman's Comments
Tom stated that he has
been a member of this board since its inception in 1993. Tom feels
the board does valuable work and does a great job of looking out
for the public's best interest, and he looks forward to working
with everyone as chairman. Tom is hopeful the Governor will officially
appoint him as chairman later this month. Tom further stated that
his term expires in October of 2007, but that he will seek to be
reappointed at that time.
Other Items for Board
Consideration
Dick Smith questioned
whether NHFG had a definition of minimum reasonable access. Dan
noted that the Statewide Public Access Plan outlines the recommendations.
This should be available in the PWAAB Notebook all members have
a copy of. Tom noted that this document is the foundation of this
board and the NHFG Public Access Program. Pages 28 and 29 of the
Plan outline the standards and goals for access. Dick questioned
expending funds and stocking fish if there is not adequate access.
Dan stated that if there is no available public access, the water
body is not stocked with fish. Jacquie noted that NHDES has similar
rules regarding expending funds for milfoil and other invasive plant
management. Jacquie will bring further information regarding these
guidelines to the next meeting.
Jacquie Colburn briefly
discussed public access in the state of Montana, where she recently
visited. She took a day to drive around Flathead Lake, which is
about the same size as Lake Winnipesaukee and has about six state
parks around the lake, each with access to the water. She will incorporate
pictures from her trip into the presentation she will provide on
water quality.
Mike Pillsbury offered
an update on the Woodstock railroad property providing access to
the Pemigewasset River and the pedestrian railroad crossing. A pre-hearing
meeting will be taking place in November, with the hearing to follow;
things are progressing along in establishing this crossing.
Public Comment - None
at this time
Adjournment
Allen MacNeil moved to
adjourn the meeting. Seconded by Mike Pillsbury. The Board unanimously
approved. Meeting adjourned at 11:51 a.m.
The next meeting will
take place on November 6, 2006 at 9:00 a.m. in the East/West Conference
Room at Fish and Game Headquarters in Concord, N.H.
<Return to top>
______________________________
PUBLIC WATER ACCESS ADVISORY BOARD MEETING
MINUTES
September 11, 2006
9:00 a.m. - NH Fish and Game Headquarters
Members Present: Allen
K. MacNeil, Chairman; Thomas Quarles, Esq., Vice Chairman; Daniel
R. Lynch, F&G; Cheryl Killam, GCD; Brian Giles; Patricia Goodridge;
Shari Colby, DRED; Michael Pillsbury, DOT; Maynard Goldman, NHLA;
Carol Barleon, OEP; Representative Duncan Chaplin
Members Absent: Jacquie
Colburn, DES; Dick Smith; Paul Blizzard; B. David Bryan; David Barrett,
DOS; Senator John T. Gallus; Senator Joseph D. Kenney; Representative
John Klose; and Roger J. Bellerose, Sr.
Audience Members: Dave Mikolaities, NHFG; Jared Teutsch; Derek Durbin;
and Denise Segault
*****************************************************************************
MEETING CONVENED
Chairman Allen MacNeil
called the meeting to order at 9:05 a.m.
Chairman's Comments
The meeting began with
Chairman MacNeil stating that the reason he had for resigning had
gone away as his brother-in-law is doing much better. He did state,
however, that this meeting would be his last as Chairman. A letter
was sent to Governor Lynch requesting that Tom Quarles be appointed
Chairman. Tom will begin acting in that capacity immediately following
this meeting.
Chairman MacNeil also
gave the board an update on Roger Bellerose. Apparently he is doing
well, with speech having returned, however, he still cannot move
his legs and has much rehabilitation ahead. We all wish him well.
Chairman MacNeil then
asked to board to join him in a moment of silent prayer in honor
of the fifth anniversary of the tragedy of September 11, 2001.
AGENDA ITEMS
1. Approval of the June
19, 2006, Meeting Minutes - Allen MacNeil, Chairman
Cheryl Killam requested
the following corrections to the minutes:
On page two, Item #2 - Webster Farm - Cheryl requested that in line
4 of paragraph 3 the words "handicap accessibility" be
changed to "wheelchair accessibility."
Tom Quarles moved to
approve the minutes of June 19, 2006 as amended; seconded by Carol
Barleon. The Board approved, with Maynard Goldman and Patricia Goodridge
abstaining. Tom questioned the status of making the approved minutes
available online. Ellen stated that the minutes are now posted,
beginning with January 2006. To access them from the Fish and Game
website simply follow the links to the PWAAB webpage and the minutes
are listed there by month.
2. Update on Winnisquam Access Site - Daniel Lynch, NHFG
Dan stated that the working
group met at Water Street for a project status update. The contract
extension for Hong Environmental has been submitted to G&C for
approval so that they can complete their work. 95% plan submittals
have been received and reviewed by NHFG staff, as well as the Winnipesauke
River Basin Program, NHDES, and comments have been returned to Fay,
Spofford, & Thorndike (FST). A cost estimate for the project
is underway at this time as well. Dan further stated that Wetlands
and Site Specific Permit applications are being completed by FST
at this time. 100% plan submittals are expected within the next
few weeks. Dan hopes the project can be put out to bid this fall/early
winter for construction early in the spring.
As the Governor and his
Council are meeting at Laconia City Hall this month, the hope is
that they will have time to visit the Water Street site following
their meeting.
Brian Giles requested
an explanation of the Senator Johnson letters sent to all board
members. Chairman MacNeil explained as follows: A constituent had
called various board members regarding contamination at the Water
Street site, and followed up with Senator Johnson when he felt answers
were not satisfactory. Chairman MacNeil stated that there is no
contamination on this site, other than that noted inside the digester
building, which has been blocked off to prevent access. The constituent
noted that there was possible contamination from a tank buried at
the lumberyard, which was sending a plume towards the site. Chairman
MacNeil further noted that the City of Laconia or an abutting landowner
put in a testing well that is checked monthly to monitor the situation.
No contamination from the lumber yard has traveled to the access
site.
Dunc Chaplin noted that
he had received an email from this constituent asking that several
board members meet him onsite to discuss the situation. Although
Dunc could not make it at the scheduled time, he did take the time
to visit the site and become familiar with the area and the issues
associated with it.
Patricia Goodridge questioned
what the constituent's point really was. She at first thought it
was to block access to the lake but has since found that is not
the case, the constituent is simply of the opinion that Ahern State
Park was the better choice of sites. Chairman MacNeil stated that
this constituent is an employee of the state, working at the NHFG
complex and that he has invited him to attend these meetings, which
has not happened to date. Chairman MacNeil further stated that we
would not be putting any contaminated soil under the parking lot,
as that is not how we build access sites. Patricia then asked Dan
to provide an explanation of Fish and Game's position regarding
contamination onsite, which he briefly provided.
Tom questioned what NHFG
has done to continue accessibility at Martel's in the interim. Dan
noted that NHFG leases a portion of a parking lot adjacent to Martel's
for 42 vehicles and trailers, and will continue to do so as necessary.
There were questions regarding All in One Storage not complying
with the terms of the lease, which have since been resolved. The
major issue seems to be the fees charged for access by Martel's
even though they are parking elsewhere.
Chairman MacNeil stated
for Patricia's benefit that the board had looked into building an
access at Ahern State Park and that he had received a letter from
NHDRED stating that under no circumstances would they entertain
putting in a trailer boat access point at the park. He also stated
that there had been legislation after that that required a boat
access on the site. Dan noted that the City Council of Laconia had
voted in July 2002 that they did not want motorized boat access
at that site, citing issues with sewer lines in the area and high
bacteria counts in the water along the shore. It was determined
that in order to provide access in a timely manner, that the Water
Street site would be used. Dan further stated that he felt it would
be irresponsible on the part of the Department to change direction
now.
Patricia questioned whether
canoe/kayak access is available at Ahern State Park, and was told
that yes, it is available. Patricia further noted that she would
like the board to pursue improved non-powered boating access throughout
the state. This could perhaps be as simple as putting up signs noting
access points. Dan recommended sending this issue to the Ahern State
Park Advisory Committee, and Chairman MacNeil stated he would contact
the chair of this committee to follow up.
Dunc Chaplin noted that
the real root of the matter is inadequate boat access on Lake Winnisquam
and that legislation is being looked at to provide public access
at Ahern State Park. The argument is that it is a good investment,
in the long run, for the state to undertake the development of an
access at the Ahern Park site. Dunc stated that the Water Street
site would not solve the problem of inadequate access to the lake.
3. Webster Farm Conservation
Project Update - Daniel Lynch, NHFG
The package for this
conservation easement was signed off on by the Director and was
sent to Governor and Council for their September 13, 2006 meeting.
Tom questioned how the public would be notified regarding availability
of this site, and questioned signage. Dan stated he was unsure how
that would be handled but that he would follow up. As Dan had to
leave for a meeting with the Director, he stated he would come back
with further information later in the meeting.
As Dan did not make it
back before the end of the meeting, this item will be moved to the
October meeting agenda.
4. CORD - State-Owned
Land Surplus Land Review - Tom Quarles
Tom sent letters to CORD
on behalf of the board opposing the following two items: Town of
Meredith SLR 06-006 - Property owners, Paul & Emilette Beaudoin;
and City of Laconia SLR 06-007. CORD voted not to approve item SLR
06-006, which was in line with the board's position, as well as
the earlier Belmont request, which was discussed in June. Tom reported
that CORD had not yet discussed the City of Laconia request (SLR-06-007).
Tom noted one new proposal
since the last meeting. The newest proposal is for NHDOT owned land
in Plymouth, adjacent to the Pemigewasset River (SP-P4600H Plymouth/Logan).
Currently, this land is being leased by the Common Man Restaurant,
a portion is used for parking, with the remainder left as undeveloped
land along the riverfront. NHDOT generally is trying to dispose
of unnecessary land after completing highway projects and is therefore
looking to surplus this parcel. The Rivers Management Advisory Committee
(RMAC) conditionally approved disposal of this parcel. Unfortunately,
this process began in May but this board was not notified at that
time. Tom will follow up to determine exactly what the RMAC conditions
are so the item can be discussed at the October meeting.
Chairman MacNeil noted
that this parcel is just a small wedge right beside Route 3 and
the Common Man Restaurant. This parcel is actually between the Pemigewasset
River and the Baker River, although neither one is readily accessible
from this parcel. To access the Baker River you'd have to cross
Route 3, and to access the Pemigewasset you must pass under the
interstate. This parcel is heavily used during the winter months
by snow-mobilers. Allen does not feel this parcel is worth pursuing
for public access as he feels it would be too dangerous to access
either river from this site.
Mike Pillsbury commented
on behalf of NHDOT. The Department is looking to surplus this parcel,
which was most likely purchased when the interstate was built. Mike
noted that there may be interest from NHDRED, Bureau of Trails.
Shari will follow up from the NHDRED perspective. Mike will follow
up on the status of this item so that it may be discussed in October.
Carol Barleon questioned
taking a more holistic view regarding the surplus of state properties.
Tom noted that in an earlier conversation with Jared Teutsch, Jared
told him that the Lakes Association had sponsored legislation for
a moratorium on leasing of state owned railroad land along water-bodies,
which was defeated. However, the Association plans to try again
this year with new legislation requesting a study commission. At
this point Derek Durbin, the new Lakes Association Legislative Representative,
introduced himself and spoke briefly about the proposed legislation.
5. 2005 Annual Report
-Tom Quarles
Chairman MacNeil urged
board members to begin preparing their 2006 reports at this time.
Please use the calendar year whenever possible for your reports.
Tom stated that he has
questions for NHDRED and NHDES, but that since Jacquie Colburn is
not available at this time, he will send his questions to her before
next month so a more detailed discussion can be had in October.
Tom's questions for NHDRED relate to Dodge Pond in Lyman and acquisition
of the Fall Mountain State Forest. Shari Colby and Carol Baleon
filled the board in on the Dodge Pond reconstruction. This waterbody
is in the Upper Connecticut Valley. Shari will find out about the
"Fall Mountain State Forest" and report to the board.
Tom urged anyone with questions regarding the 2005 Annual Report
to bring them forth next meeting.
Patricia Goodridge questioned
whether new maps had been printed since she last attended a meeting.
Tom noted that all of that information is available interactively
online now. Patricia stated that she would like to see more signs
at access sites. The problem is that NHFG is not likely to purchase
signs for non-NHFG sites.
Patricia also noted that
she would like to see more information/reporting on wheelchair accessible
sites. Cheryl Killam noted that she does not report on sites unless
she has actually been there herself to check accessibility. Tom
noted that this issue as well as increased signage, are among the
long term projects the board will need to address. Carol Barleon
stated that she is currently following up with municipalities regarding
accessible sites. Cheryl noted that there are specific questions
that can be asked of municipalities in order to ensure sites are
accessible. Tom questioned if Carol was gathering information regarding
which sites may have been purchased with Land and Water Conservation
Funds. Carol was not sure whether or not this information is available
on the OEP database. Tom questioned this due to historical issues
with towns designating properties as open to residents only which
is against the rules when using these funds. Shari noted that NHDRED
currently verifies this information, but mostly only for baseball
parks and similar recreational fields. Tom suggested that this information
be made part of the agencies' annual reports.
6. F&G Project Update
- Daniel R. Lynch, F&G
As Dan had not yet returned
to the meeting, Dave Mikolaities, Land Resources Supervisor gave
a very brief update on a few of the projects currently underway.
An updated Boat Access Site Status Matrix was provided to the board
with further updates noted in red.
1. Millsfield Pond (Millsfield)
- Dave reported that repairs had begun at the Millsfield access
site the first week in September (and have since been completed).
2. Cedar Pond (Milan)
- Repairs are scheduled to take place during the first week of October.
3. Umbagog Lake (Cambridge)
- Repairs are scheduled to take place during the second week of
October.
4. Baxter Lake (Rochester)
- Construction is being completed by NHDES's Dam Bureau.
5. Pleasant Lake (Deerfield)
- Wetlands permit received from NHDES. Bids for tree cutting and
pavement of the parking area will be put out this fall for Spring
2007 repairs.
Cheryl Killam requested
that NHFG provide information regarding accessibility of sites.
Dave stated that he would keep her informed when new construction
or repairs occurs.
Patricia Goodridge questioned
the issue of Onway Lake losing an access site at the Boy Scout Camp.
Dave was not aware of the situation.
Brian Giles questioned
the progress at Hilton Park. Michael Pillsbury stated that NHDOT
is still waiting for approval of the wetlands permit before work
can begin.
Maynard Goldman stated
that the Boat Access Site Status Matrix was very helpful and he
was very much appreciative of the update.
7. Update on Harilla's
Landing - Tom Quarles
Tom stated that Attorney
Cronin for the Yacht Club had talked to himm prior to Cronin meeting
with Paul Goodwin, the contractor's representative, to discuss the
wetland's permit for dock reconstruction and other Phase One proposals.
Attorney Cronin was also to meet with NHDOT regarding the land swap.
Work could begin on Phase One as soon as Spring 2007. Tom invited
any interested members to join him on the Harilla's Landing subcommittee.
Tom will follow up on progress at the October meeting.
Carol Barleon stated that it appears we've made much progress this
year on this project.
Other Items for Board
Consideration
Cheryl Killam noted that
the City of Concord had an issue brewing. The City is installing
temporary floating docks at the Everett Arena Boat Ramp. The Concord
20/20 group is attempting to put in an access to the docks that
are wheelchair accessible, however, the bank to the river is very
steep. The ground cannot be disturbed more than six inches due to
buried waste in the area. The GCD is working with the Concord 20/20
group and NHDES to come up with some alternative, and a waiver for
the accessibility requirement is pending. Cheryl will keep the board
informed.
Tom noted that he and
Chairman MacNeil had been contacted by City Councilor, Ken Field
of Franklin, regarding a city boat ramp in need of repair. The Town
is requesting help from the PWAAB in funding/completing repairs.
Rich Tichko had investigated the matter but Dave was unsure of the
outcome. The matter will put discussed further at the October meeting.
Tom noted that NHFG had
added depth maps for some of the water-bodies in the state. From
the NHFG homepage, click on the link for "Fishing" and
scroll down to the link for the depth maps.
Chairman MacNeil questioned
if or when the access maps would be reproduced. Dave Mikolaities
has looked into the matter in conjunction with the GIS initiative,
but is unsure if funding is available. Patricia Goodridge noted
that since NH agencies and businesses are interested in promoting
tourism in NH, they would possibly help to fund this project. Derek
Durbin of the Lakes Association stated that he has been contacted
by a company looking to produce such a map of New Hampshire, and
is looking for information to put on such a map.
Dave Mikolaities noted
that due to damage caused by the May flooding, several towns have
come forward asking for help to repair boat access sites. Allenstown
and Newmarket have both contacted NHFG, as well as Franklin as described
above.
Public Comment - None
at this time
Adjournment
Maynard Goldman moved
to adjourn the meeting. Seconded by Patricia Goodridge. The Board
unanimously approved. Meeting adjourned at 11:43 a.m.
The next meeting will
take place on October 2, 2006 at 9:00 a.m. in the East/West Conference
Room at Fish and Game Headquarters in Concord, N.H.
<Return to top>
________________________________
PUBLIC WATER ACCESS ADVISORY BOARD MEETING
MINUTES
July 10, 2006
9:00 a.m. - NH Fish and Game Headquarters
Members Present: Allen
K. MacNeil, Chairman; Thomas Quarles, Esq., Vice Chairman; Daniel
R. Lynch, F&G; Jacquie Colburn, DES; Cheryl Killam, GCD; Johanna
Lyons, DRED; Dick Smith; Michael Pillsbury, DOT; Carol Barleon,
OEP; Representative Duncan Chaplin; Senator Joseph D. Kenney
Members Absent: Paul
Blizzard; Maynard Goldman, NHLA; B. David Bryan; Brian Giles; David
Barrett, DOS; Patricia Goodridge; Senator John T. Gallus; Representative
John Klose; and Roger J. Bellerose, Sr.
Audience Members: Charles Bridges, NHFG; and Dave Mikolaities, NHFG
*****************************************************************************
MEETING CONVENED
Chairman Allen MacNeil
called the meeting to order at 9:12 a.m.
AGENDA ITEMS
1. Approval of the June
19, 2006, Meeting Minutes - Allen MacNeil, Chairman
Jacquie Colburn requested
the following corrections to the minutes:
On page two, Item #3, first sentence, correct spelling of Winnesquam
to "Winnisquam."
On page three, first paragraph, 5th line, change LMAC to "RMAC;"
and in the second paragraph, 3rd line, delete "just north of"
Meredith, N.H.
Johanna Lyons requested
the following change to page 1 under Members Present:
For the sake of consistency remove "NH Bass Federation"
after Dick Smith. With the exception of State agency representatives,
the only one nominated as representing an Association would be Maynard
Goldman of the NHLA. Those representing public interests will be
listed by name only.
Carol Barleon moved to
approve the minutes of June 19, 2006 as amended; seconded by Mike
Pillsbury. The Board unanimously approved.
Chairman's Comments
Tom Quarles questioned
whether the Board would like to meet in August or take the month
off as has been done the last several years. No members objected
and the next meeting was confirmed for September 11, 2006.
Chairman MacNeil reported
to the board that this would be his last meeting as Chairman as
he is resigning due to family health issues. Allen encouraged all
to continue the good works of this board and thanked all for working
with him over the years.
2. Webster Farm Conservation Project Presentation - Charlie Bridges,
NHFG
Charlie gave a brief
presentation regarding this site's history and recent efforts to
preserve this agricultural land for future generations. The buildings
will be kept as a separate parcel with the land being held under
conservation easement and farmed by the Fife family who also owns
an abutting farm. There will be public carry in access to the river
maintained under this agreement. Parking will be available at the
cemetery with a walk of about 1,500 feet necessary to access the
river. The total cost of the project is estimated at $2.5 million
with only $100,000 of Fish and Game funds being contributed.
Tom Quarles brought forth
a motion regarding access as follows:
* Original - Request that NHFG pursue modifying easement for future
use of this access site to allow vehicles to drive as close as possible
to shore to drop off a non-motorized boat and return to the parking
area at the cemetery.
Discussion regarding
access at this site ensued. There was concern that the walk required
would be an impediment to use of this site. Johanna Lyons stated
that the walk to the river should be seen as part of the experience
and is not necessarily an impediment to access. The question of
wheelchair accessibility was also discussed, although the details
of this are still being worked out at this time. Johanna reminded
the board that this is not an access project, but a conservation
project with an access component. Therefore, public access has already
been secured. Charlie Bridges stated that the easement language
is pretty well established and he is not sure the landowner would
be willing to make changes at this point. The landowner does not
want motorized vehicles passing over the agricultural lands causing
damage. Dan Lynch felt that as a small player in this project we
had done well to maintain the access as it stands.
Tom Quarles questioned
why the board had not been notified of this project at an earlier
date. Dan responded that final information was not available until
Fish and Game Commission approval on June 21, 2006. Tom also questioned
whether Fish and Game would have any ongoing responsibilities regarding
signage or maintenance at this site. Dan stated that as we do not
have an ownership interest in this property we would not have responsibility
for signs and maintenance. Charlie noted that we would not be involved
unless there were issues in which case the Department's Law Enforcement
Division would become involved. Tom stated this is all the more
reason to try to get access closer to the river now rather than
later.
Dick Smith questioned the safety of the current on this portion
of the river and was assured that the flow was slow enough to be
safe for canoes and kayaks at this site.
Senator Kenney questioned the categories of access sites, to which
Dan responded that there are several different types, from ownership
by other state agencies, such as DRED and DOT, to road to public
waters sites that are maintained by the towns.
Tom amended his earlier
motion to read as follows:
* Amended - Request that NHFG pursue either modifying the easement
language to allow boats to be dropped off at or near the shore-bank
with parking only at the cemetery; or that a similar provision be
explored in the conservation plan dealing with general public access
at this site.
Both the original and amended motion were seconded by Johanna Lyons.
The Board voted on the amended motion unanimously in the affirmative,
with Dan Lynch abstaining from the vote.
3. Update on Winnisquam Access Site - Jacquie Colburn, DES
Jacquie Colburn asked
Dan to provide the update as at this point in the project planning
process Fish and Game is carrying the majority of the workload.
However, she did state that Fish and Game had provided 60% plan
submissions to NHDES for review and comment, which should be completed
by the end of the week. Jacquie also reported she had visited the
site and that the butler buildings had been removed but that the
foundations were still being pulled out and demolished in order
to recycle the rebar. Hong Environmental was not on site due to
water problems at the site disrupting the process. Dan stated that
comments on the 60% plan submission had been provided to FST. Dan
introduced Dave Mikolaities, Lands Bureau Supervisor who had completed
the plan review and response. FST had guaranteed a two-week turn
around time for +/- 90% plan submission.
Dunc Chaplin reported that he had received a call over the weekend
questioning why the site had not been completed yet. Several other
board members, including Senator Kenney, had also received such
phone calls recently. Dunc suggested that Fish and Game provide
a press release regarding progress on the site to let the public
know what progress has been made to date. Johanna added that perhaps
a notice could be posted onsite with this information, as DRED does,
so those in the area with questions would have access to the information.
Dan had reservations regarding a press release as he felt some who
oppose the project could possibly drag out or stonewall the process.
Senator Kenney suggested it might be helpful to post the minutes
of these meetings online so they would be accessible to the general
public.
4. CORD - State-Owned
Land Surplus Land Review - Tom Quarles
Town of Meredith SLR
06-006 - Property owners, Paul & Emilette Beaudoin, are looking
for access across the rail corridor, for the purpose of constructing
a dock on Lake Waukewan. Tom noted that both the Selectmen of the
Town of Meredith and the Meredith Conservation Commission have recommended
to CORD that this lease not be granted. Jacquie Colburn stated that
the LMAC had also voted 6 -3 to recommend against leasing according
to their criteria. As documented in their letter to CORD, some of
their concerns are as follows: disturbance of existing vegetative
cover; water quality, to include conductivity levels increasing,
oxygen levels decreases, phosphorous loading, and toxic algae blooms
documented in the area; this area also falls within the zone of
concern of a buffer area for the common loon; and Lake Waukewan
serves as the public water supply for part of the Town of Meredith.
There is also concern that granting this 75' lease could lead to
the granting of other leases on the 1750' of frontage along the
lake, which would have a cumulative effect on the environment that
has not been fully investigated. Based on this information and ensuing
discussion, Tom Quarles made a motion to oppose the lease of this
property, due to the fact that public access is readily available
in close proximity and that there does not appear to be any public
benefit to granting this lease. Johanna Lyons recommend that the
motion be amended to include a request for a comprehensive study
of this process, including the issue of fragmenting currently undeveloped
shorefront and riverfront property, so the board would have a broader
view of the true impacts of granting these leases; the motion was
seconded by Dick Smith. The board voted on the motion, unanimously
in the affirmative, with Mike Pillsbury of NHDOT abstaining from
the vote.
Dick Smith commented
to the board that "pieces" of fishing available to the
public are being taken away by the granting of these leases to private
or commercial entities. Dick also noted that in his opinion the
$25 per foot to lease these properties is not enough and that any
money collected from granting such leases should be used to improve
public access.
City of Laconia SLR 06-007
- This is a request for commercial development of the rail corridor
by Gerald Stevens for Scenic Ledges Condominiums. Tom Quarles noted
that this request is the third purely commercial request made in
this area, the first being Eighteen Mile Point, the second being
the pending lease on Lake Winnisquam in Belmont. According to RSA
228:57-a, these leases are only for private use, and so this statute
was not meant to benefit commercial enterprises but private individuals.
Tom proposes recommending to CORD that this lease does not meet
the statutory requirement for private use; the motion was seconded
by Carol Barleon. Senator Kenney questioned whether Tom was happy
with the statute (228:57-a), to which Tom responded that yes, overall
he thought the statute was adequate. However, Tom noted that perhaps
the statute does deserve some focus and should be studied by the
legislature. Mike Pillsbury questioned the definition of "commercial"
according to the statute. He felt it would be helpful to get this
clarified should the legislature address this statute. The board
voted on the motion, unanimously in the affirmative, with Mike Pillsbury
of NHDOT abstaining from the vote.
5. PWAAB Priority List
& GIS Mapping Initiative - Daniel R. Lynch
Board members received
an updated version of the 1995 PWAAB Priority Listing and a draft
Boat Access Site Status GIS Mapping display. These were created
in conjunction with the goals of the Public Access Plan for NH's
Lakes, Ponds and Rivers. Dan discussed the recommended public access
planning standards for great ponds and the recommended public access
to rivers, which states that there should be one access for each
10 miles of navigable river. Existing sites were placed on a map
of the state, color coded by state agency and type so that we can
easily see where more access sites are needed. At this point, maintenance
crews are verifying information regarding sites to ensure the legend
for the map is correct. Once complete, this mapping information
will be provided to board members so they can assist in ensuring
sites where access is needed are identified. Knowing what opportunities
exist will help to provide direction for the board. Further information
regarding town or private owned facilities is available from the
Office of Energy and Planning. The more comprehensive the information
included on the map, the more useful it will be in drawing tourists
and visitors to sport fishing in NH. The board felt the goal should
be to have this information available to the public via an interactive
website at a future date. Johanna Lyons mentioned that a subcommittee
had been convened to verify this information in the past and that
perhaps it should reconvene. At this time the OEP is asking towns
to verify information to be included on an access map. Dan hopes
that the board can help in determining new priorities for boat access
sites as sites are removed from the priority list once the project
is completed.
6. 2005 Annual Report
-Tom Quarles
Tom decided that in the
interest of time, this item will be deferred to September's meeting.
He will send his questions to the applicable agencies in the interim
so a more detailed discussion can be had in September.
7. F&G Project Update
- Daniel R. Lynch, F&G
Dan gave a very brief
update on a few of the projects currently underway and an updated
boat access site project matrix was provided to the board.
1. Merrymeeting (New
Durham) - Dan attended the Lake Association's annual meeting to
discuss concerns. Dan stated that plans are +/- 95% complete and
hope to move forward with this project soon. The waterline replacement
project is also moving forward.
2. Sunapee - Wild Goose
(Newbury) - Director Perry will be following up with the Governor's
office regarding this site. The issue of the interface with Rte
103 and Birch Grove Road has been sent to NHDOT for another review
and clarification.
8. Update on Harilla's
Landing - Tom Quarles
The subcommittee met
last month to review a conceptual plan/proposal provided by the
marine contractor's representative, Paul Goodwin. The plan consists
of three phases. The first phase only will consist of: rehabilitation
and repair of existing facilities; permitting; and a land swap to
clear up encroachment issues, which will include involvement by
NHDOT. Comments should be directed to Tom Quarles, and this item
will be placed on the September agenda for further discussion.
9. Legislative Update
- Tom Quarles
Tom wanted to ensure
that board members were informed that CORD is now advisory only
to Governor and Council, with no veto authority on surplus land
issues. Earlier legislation from last session had taken away CORD's
veto authority on disposal of state property purchased with state
or federal highway funds.
Other Items for Board
Consideration
Carol Barleon questioned
if further information was available on the condition of Roger Bellerose,
Sr. who had been injured while on vacation in Ireland. Chairman
MacNeil stated that he had tried to get an update but had been unsuccessful
in reaching the family. He will continue to pursue this information
and make board members aware.
Tom Quarles took this
opportunity to present Chairman Allen MacNeil with a Certificate
Of Appreciation for his leadership, service and dedication to this
board and to the citizens of New Hampshire seeking public access
to all of NH's lakes, rivers, and seacoast.
Tom further stated that
Allen had joined the Board in 1993, the first year of its existence,
as the Board Member representing power boating interests. From the
beginning, Allen took an active role in the Board's meetings and
projects; always volunteering to investigate and work on any proposal
that could provide access in the Lakes region. He was elected to
the State House of Representatives in November 1994 representing
Plymouth. Allen became a member of the House Wildlife and Marine
Resources Committee and rose to that Committee's Vice-Chairmanship
in 1999. He also became that Committee's member designated to serve
on this Board. Allen was the Board's liaison with the House and
kept the Board apprised of all legislative developments affecting
public water access.
In 2004, Allen was approached
by Governor Benson to return to this Board as Chairman and to revive
this Board and its work, which had gone unattended since 2002. Allen
agreed to take on this challenge and has brought this Board back
to prominence within the state and within state government. He has
unwaveringly supported public water access, including reviving the
decade-old process to develop the Wild Goose site on Lake Sunapee.
He was one of the first leaders to recognize the opportunity for
a large lake access site for Lake Winnesquam at the DES facility
in Laconia, a project that is now well on its way to completion.
He has continued to be a champion for public water access for the
Plymouth area and the Pemigewassett River.
Public Comment - None
at this time
Adjournment -- Tom Quarles
moved to adjourn the meeting. Seconded by Carol Barleon. The Board
unanimously approved. Meeting adjourned at 11:36 a.m.
<Return to top>
_______________________________
PUBLIC WATER ACCESS ADVISORY BOARD MEETING
MINUTES
June 19, 2006
9:00 a.m. - NH Fish and Game Headquarters
Members Present: Allen
K. MacNeil, Chairman; Thomas Quarles, Esq., Vice Chairman; Daniel
R. Lynch, F&G; Paul Blizzard; Jacquie Colburn, DES; Shari Colby
for Johanna Lyons, DRED; Dick Smith; Michael Pillsbury, DOT; Maynard
Goldman, NHLA; Carol Barleon, OEP; B. David Bryan, Rep.; Duncan
Chaplin;
Members Absent: Cheryl
Killam; Brian Giles; David Barrett, DOS; Patricia Goodridge; Senator
John T. Gallus, Senator Joseph D. Kenney; Representative John Klose;
and Roger J. Bellerose, Sr.
Audience Members: Todd Baldwin; Wen Baldwin; Louis Barker, DOT;
Brian Lombard, DOT; and Don McGinley
*****************************************************************************
MEETING CONVENED
Chairman Allen MacNeil
called the meeting to order at 9:06 a.m.
Chairman MacNeil told
the Board about Roger Bellerose, Sr. who had been in an accident
while vacationing in Ireland. At this time he is at Massachusetts
General Hospital in critical condition. A card was sent around the
room for all to sign and was mailed to his home.
AGENDA ITEMS
1. Approval of the May
1, 2006, Meeting Minutes - Allen MacNeil, Chairman, PWAAB
Tom Quarles requested
the following correction to the minutes:
On page two and all successive pages the date in the header should
be changed from April 3 to May 1. Tom noted that the minutes were
very well done and easy to follow.
Carol Barleon moved to
approve the minutes of May 1, 2006 as amended; seconded by Tom Quarles.
The Board unanimously approved.
Chairman MacNeil then
asked the members of the audience to introduce themselves, which
they did.
2. Update on Winnisquam
Access Site - Jacquie Colburn, DES
Chairman MacNeil brought
to the Board's attention a Winnisquam Lake Boat Access Project Proposed
Timeline, provided by Dan Lynch. Please note that this timeline
is for discussion purposes only and is not a final document. The
projects target completion date is August 2007.
Jacquie Colburn stated that there had been a working group meeting
recently at the project site where this timeline had been reviewed.
Jacquie thought the timeline was very helpful to see what has already
been done at the site and also to see just how much still needs
to be done and give a sense of how everything has to come together.
Everyone is excited to see this site constructed. It should be noted
that this timeline begins with March 2006, but the project actually
began in August 2004. Jacquie will try to compose a timeline from
August 2004 through March 2006 as well showing all the work that
has already gone into, or generally goes into, the construction
of an access site. At the working group meeting Dan also showed
the group a slightly modified plan of the site.
Dan Lynch offered the following update on the site as well: Dan
showed the Board the modified plan as presented to the working group.
The major points covered were as follows:
- Parking lot and staging
area
- A 3-4 foot retaining
wall to maintain an area about 14 feet wide, which is part of
the fence line separating the boat access facility from the Winnipesaukee
River Basin Treatment Facility.
- A settling basin,
1 1/2 to 2 feet deep to handle storm water retention to meet site-specific
requirements.
- Slight modification
to allow for a river walk, which goes along the river in that
section of the city, to fit in with that concept and match the
design and image across the river at Martel's.
- Design provides means
to maintain existing floodway capacity, which is required by FEMA.
It also allows for an increase in the river channel due to dredging.
- Fully handicapped
accessible pier in the middle, between the other ramps and seasonal
docks.
- Changes in grade to
keep storm water runoff from Water Street from entering the settling
area and the river.
- 31 parking spots for
vehicles with trailers, 5 car-top sites and 2 for law enforcement.
The 60% plan submissions
are due by June 26, with a five-week turnaround time for review
by NHFG and FST. NHFG will be working with the Department of Administrative
Services, Bureau of Public Works because of the cost of the project.
According to the timeline, a Federal Aid Grant proposal will be
submitted by late summer to help with the cost of the project.
Chairman MacNeil opened the discussion up for questions. Tom Quarles
questioned what the dollar amount is that triggers Public Works
involvement. Dan responded that the amount is $250,000, and this
project is estimated at about 1.2 million to complete. Jacquie Colburn
informed the Board that the greenhouse structures were in the process
of being removed and progress was being made on getting the foundations
for those structures removed as well.
Chairman MacNeil stated that when the opening ceremony of the site
is held, hopefully in August of 2007, that all Board members would
be invited.
3. CORD - State-Owned
Land Surplus Land Review - Tom Quarles
Tom Quarles discussed briefly the Belmont parcel where a developer
is looking to lease the railroad corridor for access to Lake Winnisquam
to provide dockage for a private development. Tom questions whether
the employees of NHDOT Rail and Transit were in the audience to
answer questions about this matter, as well as the Hobo Railroad
site. Brian Lombard stated that they would be happy to answer any
questions the Board may have.
Before jumping into the general issue of leasing state owned property
for dockage, Tom decided to talk about two new state surplus land
reviews that CORD had asked PWAAB to review and provide its recommendations.
Foster & Colburn
State Forest, Wentworth - a local snowmobile club, in the Baker
River valley, is looking to formalize a lease for a temporary clubhouse
and maintenance building located on the state snowmobile trail,
corridor 5, and the state forest, adjacent to the south branch of
the Baker River. Tom asked Jacquie if there had been any discussion
at either the RMAC or the LMAC. Jacquie responded that the RMAC
would be meeting the next day and that this issue should not be
of any concern to the board. Tom agreed that it should not be a
problem and questioned whether the board should put the issue to
a formal vote or if we should let our inaction serve as tacit agreement.
Carol Barleon stated she did not feel comfortable voting on the
issue without having more information. Paul Blizzard agreed. Tom
restated that the clubhouse is already there and that the club is
just looking to formalize their existing squatters rights. It was
agreed that the board would defer taking a position on the matter
at this time.
Lake Waukewan, Meredith
- Tom noted that this matter is a bit more controversial as it involves
another proposed railroad dock lease. The CORD review is requested
by an individual landowner (Beaudoin) who owns property on Lake
Waukewan, Meredith, N.H. There is an existing rail line that follows
the south shore of the lake. The landowners would like to create
a pedestrian crossing of the railroad line to build and access a
dock. The railroad is under contract with Plymouth & Lincoln
Railroad. There was discussion about exactly where this lot is located
and whether other landowners would be requesting leases as well.
This lot appears to be the only one of several in the immediate
area that meets the requirements for leasing; Lou Barker thought
this to be true also. Tom questioned whether the Bureau of Rail
and Transit takes a position regarding this type of lease while
pending, or if they simply forwarded the information on to various
review agencies. Lou Barker stated that his bureau's rail operations
engineer and rail safety officer first review the proposed lease
to ensure there are no hazards to rail operations and to establish
one safe pedestrian crossing of the rail line. If that can be done,
their bureau forwards the proposal for review by the other agencies.
This location has already been through that safety screening by
NHDOT. Brian Lombard stated that the only requests the bureau rejects
are those where the landowner does not have legal access to a crossing
or if the location is unsafe for a crossing.
Tom Quarles had a few
general questions regarding leasing after reading the statutes.
The first question was in regard to the $25 per linear foot per
year fee associated with this type of lease. Is the lease rate based
on the dock width or the entire length of the frontage? Lou Barker
stated that the rate is based on frontage length, which must be
at least 75 feet. If more frontage is owned the landowner would
be charged for the extra only at their request.
The second question Tom
raised was in regards to the "one point of access across the
rail" statute, with regards to the CORD review for the Belmont
property, and whether the request was consistent with this requirement.
Lou Barker explained that the crossing would be at one point and
then would open up to access points to the lake from there. Brian
Lombard added that the requested crossing at that site was for pedestrian
traffic only as boats would be launched elsewhere and only docked
at this site.
The final question was
in regards to the 5-year review of these leases, part of which includes
cost and the current stated price of $25 per linear foot. How has
this issue been addressed in the past? Lou Barker stated that in
the past, when a price increase has been put into effect, the landowner
is notified of the new price at the review and that any lease renewal
will take place at the new cost. This has happened at lease twice
in the past when the legislature has raised the lease rate. This
statute does not allow a higher charge than what the legislature
has put into place. Dan Lynch stated that he thought the legislature
had recently passed an increase to $125 per linear foot. Chairman
MacNeil questioned Dunc Chaplin on the issue, but Dunc was unable
to verify any change in the statute.
Carol Barleon questioned
whether these requests for leases go through the town for approval
so that the town could do their own safety check of the area to
ensure new hazards are not being created. Lou Barker stated that
in fact they did and that the Town of Meredith had contacted NHDOT
with questions on the Lake Waukewan lease request.
Dick Smith questioned
what statute was being discussed. Tom stated the statute is RSA
228:57-a Leasing Certain Portions of Railroad Properties, enacted
effective May 6, 1994, and amended 1997 and again in 2001.
Dick Smith did not feel
comfortable making a judgment on this or any other site without
a better understanding of whether said waterfront should be used
as a public access for shore fishing, etc.
Tom Quarles questioned
whether Lake Winnipesaukee was the only lake on which a permanent
dock structure could be constructed. Jacquie Colburn stated that
permanent structures could be located on other water-bodies as well,
other than just docks. Dock length rules were changed so that docks
could be as long as necessary to get to 3 feet of water. It was
noted that NHDES is the agency that permits docks, not NHDOT, and
so permit requests must be submitted to NHDES prior to construction
of any dock, even when the land is leased from the state. Access
across the rail lines does not automatically grant the right to
construct a dock.
Tom Quarles asked whether
the board would like to make a decision on this CORD review. Carol
Barleon again stated she was not comfortable making a decision without
further information.
Jacquie Colburn questioned
the RSA regarding trespass on rail lines. If such a statute is in
place, why do people use them as snowmobile trails and such? Brian
Lombard stated that in the winter the rail lines are turned over
to DRED for use as snowmobile trails from January 1, through early
March because the lines are not in use by the trains at that time
of year. Brian gave Chairman MacNeil several articles relating to
injuries caused by the inappropriate use of rail lines. It is unsafe
to have mixed use of the rail corridor. Tom questioned the standard
right of way of rail lines. Brian stated that the amount of right
of way varies between 18 feet to as much as 50 feet on each side
of the track according to location and use of the particular line.
Because some rail lines run close to the waters edge, Jacquie questioned
whether someone anchoring near the rail lines and then swimming
in to shore would be trespassing. Brian stated that technically,
yes, they would be trespassing but that NHDOT has not had any issues
with that happening to their knowledge. NHDOT is more concerned
with people trespassing on the non-lake side of the rail lines.
Jacquie questioned who should be responsible for notifying homeowners
of the one spot that is allowed to cross the tracks. Mike Pillsbury
noted that during the permit process these issues would be addressed
and the requestor could be required to post signs and fence off
the area to allow crossing only at the permitted site.
Tom questioned whether
the LMAC had reviewed the Lake Waukewan request. Jacquie stated
not yet, that they would be meeting on Friday, June 23rd.
Jacquie questioned pedestrian
and fisherman traffic on rail lines in her area, stating that the
general public probably does not know they are not supposed to be
there. Chairman MacNeil questioned why signs are not posted. Brian
Lombard stated that signs are posted in some areas but that to have
them all along the rail lines would be impossible. Those that are
posted are often ignored, vandalized or torn down and NHDOT does
try to keep up but it is sometimes a losing battle.
Tom questioned again the possibility of public access at the Lake
Waukewan site. Town owned land, lot 25, is adjacent to this lot,
however, it is not accessible by boat from the lake, and therefore
would not be suitable for a public access point. Jacquie will be
going out and looking at the site prior to the LMAC meeting on Friday
and will report back to the board with her findings. It was decided
the board would conduct a vote on these CORD items via email after
the next LMAC meeting but before the CORD's next meeting on July
6th. [This has not happened as the CORD meeting has been moved to
later in July, giving the PWAAB time to discuss and vote on this
Lake Waukewan proposal at PWAAB's next meeting on July 10, 2006.]
Tom feels that email votes are problematic, but Dan stated that
the F&G Commission has conducted email votes in the past with
ratification at the next publicly noticed meeting.
Jacquie noted as an FYI,
that the Route 3 NHDOT right of way in Holderness, was brought to
the attention of the LMAC but there is no water access involved.
Proposed Developer's
Dock Lease on Winnesquam, Belmont, N.H.
Dan questioned the Belmont lease on Lake Winnesquam. The town is
looking to build a bike/pedestrian path parallel to the rail corridor.
How does it work given that in that environment there will be a
pedestrian crossing with a path paralleling on the inland side?
Brian Lombard stated that the town and the developer had agreed
to move the trail onto developer's property; the easement would
be going to the town. Dan questioned the interaction of the trail
with the rail crossing and the issue of the trail beside the tracks.
NHDOT has worked with several towns in the area in developing other
portions of the trail. NHDOT sets criteria such as 15 feet clearance
from the centerline of the tracks, 5-foot high chain link fencing,
stopping the fencing only at crossings to allow for vehicle or pedestrian
traffic and then continuing fencing after the crossing. This prohibits
anyone accessing the trail from crossing the tracks and therefore
trespassing where it is unsafe. They also require the towns to be
responsible for drainage and maintenance issues as well. NHDOT is
trying to develop the trail in a way that will not interfere with
future activation of the rail line. Mike Pillsbury stated that communication
between agencies is paramount. There are different interests that
are overseen by different agencies. NHDOT by statute must have a
provision to enable the lease of the properties, and impacts of
access to the shorefront and lake are governed by NHDES.
As Jacquie stated, at the site in Belmont, there is a well-vegetated
strip of land near where the developer is proposing to place the
docking structure, and so they will need to comply with the Shoreline
Protection Act managed by NHDES. Dan questioned whether DOT railroad
crossing lease provisions state that the proposed dock owner must
comply with the Shoreline Protection Act or any Endangered Species
acts or only have provisions relative to safe rail crossings. Brian
Lombard stated that all NHDOT regulates are the safe rail crossing
concerns. Jacquie noted that some Endangered Species concerns may
be addressed by NHDES's Wetlands Bureau.
4. Hobo Railroad - NHDOT
Mike Pillsbury of NHDOT spoke regarding this site. The NHDOT Bureau
of Environment is taking the lead, working with the Bureau of Rail
and Transit to provide pedestrian access to the Pemigewasett River
at this site. Some fencing will probably be put into place to secure
access to pedestrians only as the site is not suitable for vehicular
traffic. Mike will keep the board apprised of progress.
Dick Smith questioned
who had put up the "No Trespassing" signs at the Hobo
Railroad site. Brian Lombard answered that he is unsure where they
came from. He feels they were most likely put there to keep people
out of the NHDOT gravel pit for safety reasons. Brian will have
someone go out and check to make sure the site is accessible to
fisherman. Brian also noted that during the summer months these
tracks are in use and that anyone accessing the site should use
caution. Audience member, Don McGinley, stated that he was the one
who had seen the Hobo Railroad employees placing the signs and cable
up to keep people out of the area. He feels that if the area is
not going to be accessible to the public then NHFG should stop stocking
trout in that section of the river. Dan addressed the stocking issue,
stating that this portion of the river is still accessible by other
avenues, but agreed that we should not be stocking if the site would
not be available to fisherman.
Mike Pillsbury stated that the Hobo Railroad had gone above and
beyond in placing the signs and cable there. The contract with Hobo
Railroad states that public access is to be maintained at this site.
NHDOT is working on this issue, and will try to develop, by summers
end, a parking area there as well. The gate at the roadway should
be removed and a gate placed at the edge of the rail corridor to
ensure vehicular traffic does not cross the tracks. Mike Pillsbury
stated that the property does not belong to the Hobo Railroad, they
only lease the rail corridor, and the area in question is state
property and that this item should no longer be described on the
PWAAB Agenda as "Hobo Railroad" as it really is not their
issue.
Tom Quarles questioned
whether there was currently a gate stopping access? Brian stated
that the gate was open the last time he was there, and that he had
never seen it closed and locked. Tom also questioned winter use
of the rail line by snowmobiles, and if so, should a parking area
large enough for trailers be put in. Brian stated that yes, there
is winter use by snowmobiles but that he would not recommend a parking
area that size at this site as there are safety issues regarding
pulling off of Rte 175 in this area, especially in winter. This
property was purchased for and is reserved for future wetland developments
and so it would not be a proper use of the property to develop it
into a large parking area. Tom questioned whether the Hobo Railroad
has a defined lease area. Brian stated that there is a lease agreement
but that the property with the Polar Express building is not under
lease through Hobo but through the company that runs the Polar Express,
which is a different entity. Also, this land is owned by NHDOT's
Bureau of Right of Way not the Bureau of Rail and Transit. The question
of storage of materials on the site was also raised and Brian addressed
it by stating that the materials are owned by NHDOT and are used
to maintain the rail corridor.
Audience member, Todd
Baldwin, spoke about the Exit 31 River Restoration Project that
is currently in the implementation phase for approximately 2,900
feet of the Pemigewasset River in Woodstock. This is the area of
the river that can be accessed from the Hobo Railroad site discussed
above. The goals of the restoration project include stabilization
of the river, reduction of bank erosion and land loss, enhancement
of the in-stream and off-channel fisheries habitat, and restoration
of a once spring-fed pond. For further information contact the Pemigewasset
Chapter of Trout Unlimited, P.O. Box 1356, Campton, N.H. 03223.
Dick Smith questioned whether NHDES was able to expend funds for
milfoil control only if there was a public access area. Jacquie
and Maynard confirmed that there is a requirement of public access
for funding to occur.
5. Harilla's Landing
- Tom Quarles
Tom stated that there would be a Harilla's Landing subcommittee
meeting immediately following this meeting. Anyone wishing to stay
for the sub-committee meeting is welcome to do so.
6. Wild Goose - Chairman
Allen K. MacNeil
Chairman MacNeil asked Dan Lynch to provide an update on progress
at the Wild Goose access site. Dan stated that in mid April representatives
from NHFG, FST and the Attorney General's Office met with the Town
of Newbury, Board of Selectmen to go over site concept design and
acceptable improvements for access to Rte 103 off of Birch Grove
Road. A variety of other comments were discussed at the meeting
as well. Governor Lynch will meet with Director Perry and Commissioner
Bald of NHDRED regarding this location and access to Lake Sunapee.
Plans were discussed with NHDES and ACOE, both of whom made some
suggestions regarding the site. Historical clearance has been received,
and Phase I Hazard Assessment has been completed, with small amounts
of asbestos siding being found on site that will need to be removed.
The Department will most likely look toward further development
of this site after the new fiscal year begins in July, although
Dan was unsure when the meeting with the Governor would be taking
place. Dick Smith asked what the real issue with this site is: whether
it is access from Rte 103 or if people just don't want to see this
access site developed. He also asked what is the likelihood of this
site actually moving forward to completion? Dan responded that there
is limited impact to the shorefront, we are looking to use existing
geographic conditions onsite to our advantage, however, a stand
of Red Pine trees will need to be removed to create a parking area,
which is a concern but is allowable under the Shoreline Protection
Act. The existing breakwater will need to be reconstructed as well.
The ACOE asked for a stationary dock to be constructed on the south
side of the ramp. In Dan's opinion the Town of Newbury will continue
to fight to keep this site from being constructed, as they and the
Lake Association believe we should use the site at the existing
State Park beach rather than the currently selected site. In the
last 15 years 12-13 sites around the lake have been looked at, however,
the environmental impacts at alternate sites are much worse than
at Wild Goose. Chairman MacNeil stated that NHFG owns the land and
the Town of Newbury should just allow the site to be developed rather
than continue fighting it.
7. F&G Project Update
- Daniel R. Lynch, F&G
1. Pleasant Lake (Deerfield)
- Remedial repairs are being made to the parking area. The wetland
permit application has been received by NHDES and we are waiting
to hear from them.
2. Lambert Park (Hooksett)
- (Merrimack River) Wetlands permit has been sent to DES. Remedial
repairs are being made at the site as recent flooding exacerbated
existing damage.
3. Manning Lake (Gilmanton)
- Permit application for Manning Lake will be submitted this week
if it has not already been done.
4. Merrymeeting (New
Durham) - Met onsite with abutting landowner and the Merrymeeting
Lake Association to discuss the Powder Mill Hatchery waterline project
and the boat access facility. Dan will be attending the Lake Association's
annual meeting to discuss concerns some members have. The arborist
onsite for the meeting had no concerns and should have a formal
report for the Association by the annual meeting. Dan hopes to move
forward with the land acquisition as plans are 90% complete.
5. Sunapee - Wild Goose
(Newbury) - This site already discussed.
6. Other sites - Other
sites are being surveyed by the Bureau of Public Works (since NHFG
Land Resources Bureau does not have a surveyor). They are: Meetinghouse
Pond, Marlborough; Stinson Lake, Rumney; Purity Lake, Eaton; and
Connor Pond, Ossipee.
The latest version of
the matrix, from April 2006, shows Glen Lake as in the concept phase.
Tom questioned which part of the lake this site is on. Dan responded
that the site is towards the north side and east end of the lake,
sometimes referred to as the Goffstown Back Road site. The Town
has a ramp in place there with limited parking and NHFG is in the
process of securing additional parking through PSNH at this site
and making improvements to the ramp.
8. Legislative Update
- Chairman Allen K. MacNeil
Chairman MacNeil noted
that according to Jared Teusch, President of the Lake Association,
there was nothing pending regarding public access at this time.
Guest, Don McGinley, questioned HB 1343 which was passed that takes
away CORD's ability to decide whether to grant railroad crossing
leases for docks, which he feels is key to public access. Tom Quarles
stated that this has been discussed at previous meetings.
Tom Quarles noted that the legislature had passed a comprehensive
ethics re-clarification that affects volunteer board members that
work for entities that employ lobbyists. This affects Tom as he
is a partner in a law firm that employs lobbyists with business
in front of the legislature. This statute became effective 6/2/06,
Chapter 21, Senate Bill 206-FN, amending RSA 21-G:25, I. Tom read
the pertinent language to the board and gave his judgment that because
his position on the board went through Governor and Council nomination
and approval that his service on this board continued to be lawful.
Chairman's Comments
Next meeting to be held July 10, 2006. Tom briefly discussed items
for the July agenda.
Other Items for Board
Consideration
Dan Lynch made the board
aware that the new Lands Bureau Supervisor, Dave Mikolaities, would
be starting on June 30, 2006 and that Mark Kirouac, Project Manager,
would be leaving the Department as of June 22, 2006.
Old Business
None at this time.
ADJOURNMENT
Tom Quarles moved to
adjourn the meeting. Seconded by Mike Pillsbury. The Board unanimously
approved.
Meeting adjourned at
11:25 a.m.
<Return to top>
________________________________
PUBLIC WATER ACCESS ADVISORY BOARD MEETING
MINUTES
May 1, 2006
9:00 a.m. - NH Fish and Game Headquarters
Members Present: Allen
K. MacNeil, Chairman; Daniel R. Lynch, F&G; Paul Blizzard; Jacquie
Colburn, DES; Cheryl Killam; Brian Giles; Johanna Lyons, DRED; Dick
Smith, NH Bass Federation; Michael Pillsbury, DOT; Carol Barleon,
OEP; B. David Bryan, Rep.; Duncan Chaplin;
Members Absent: Thomas
Quarles, Esq., Vice Chairman; David Barrett, DOS; Patricia Goodridge;
Senator John T. Gallus, Senator Joseph D. Kenney; Representative
John Klose; Maynard Goldman, NHLA; and Roger J. Bellerose, Sr.
Audience Members: James Nagle
*****************************************************************************
MEETING CONVENED
Chairman Allen McNeil
called the meeting to order at 9:08 a.m.
AGENDA ITEMS
1. Approval of the April
3, 2006, Meeting Minutes - Allen MacNeil, Chairman, PWAAB
Jacquie Colburn requested
the following corrections to the minutes:
Page 2, paragraph 1, 8th line; change "ACOE" to "DES."
Page 2, last paragraph, first sentence; after "...City Mayor"
insert "and the City Manager."
Page 2, last paragraph, second sentence; strike "Dale Kierstead
and".
Page 2, last paragraph, third sentence; after "...review sediment
and the Dam at..." insert "the Belknap Mill and".
Cheryl Killam requested
the following correction:
Under Members Absent: Add "Cheryl Killam"
Tom Quarles requested
the following correction to the minutes:
Page 4, paragraph 2, last sentence; change "DES" to "DOT".
Carol Barleon moved to
approve the minutes of April 3, 2006 as amended; seconded by Michael
Pillsbury. The Board unanimously approved.
2. Update on Winnisquam
Access Site - Jacquie Colburn, DES
Jacque Colburn stated
the Lee Perry, Dan Lynch and herself had met with Laconia City Mayor,
Matt Lahey, and City Manager Eileen Cabanel, to introduce the project
to the Mayor and to update Eileen who has been involved with the
project from the beginning. Dan provided aerial photos; one showing
the site as it now is and another, which has been superimposed to
show the site as it will be upon completion. These were very helpful
in describing what the site will be once completed. DES is working
closely with Fish & Game to develop a proposed project timeline.
There is much public interest in seeing this project completed as
soon as possible. However, those involved in the project know all
the many steps that must be taken to get there, and it would be
helpful to get this information to the public. Working group meetings
will be part of the proposed timeline as well. At this time, the
proposed timeline shows construction beginning in early fall, 2006.
Allen MacNeil commended Jacquie for all her efforts on this site
so far. Allen has received several calls regarding this site and
would like to see some kind of publicity regarding the site. This
item will be discussed at the next working group meeting. Information
was posted prior to April 1 but updated information needs to be
made available. Allen believes any publicity should come from DES
and/or Fish & Game.
The Board did a site visit in August of 2004, and although it appears
to be taking a very long time, the project is actually moving along
towards completion quite well. All the other agencies and committees
involved should be commended for their efforts as well. Allen MacNeil
stated that as the only public access on Lake Winnisquam, this access
site will be a thing of beauty and joy forever.
Dan Lynch offered the following update on the site as well: The
contractor performing the Butler Building demolition will be Hong
Environmental of Portsmouth, NH. Final permitting for the building
demolition is being completed through DES and the EPA, including
submittals for stockpiling of materials, with demolition to be completed
by mid August. Site design issues: regarding dredging and flow analysis/modeling,
through discussions with DES, it was determined that in order to
address the current and future needs for dredging it is necessary
to establish a benchmark when initial dredging is done and then
on an annual basis measurements be taken to determine what level
of sedimentation is occurring at the site. This will allow projection
of future dredging needs. FST and the Bureau of Public Works have
been provided with the proposed timeline. Public Works will be handling
the bidding and awarding of the project and overseeing the project
through completion.
Dan stated that the Department is required to attend an informational
meeting with the city's Planning Board and the City Council. In
speaking with the Mayor, it was determined that a meeting with the
City Council would not be needed as they are being kept abreast
of the situation, but that a presentation to the Planning Board
would be helpful. That meeting will take place on June 6, 2006 and
will be attended by Dan Lynch and a representative from FST.
The Department is also looking to meet with the Conservation Commission
in order to keep them up to date on progress as well, as they had
previously endorsed the project and the location.
Dunc Chaplin questioned if this was the same access point that former
Governor Benson had been involved with. Allen said, indeed it is.
Representative Chaplin stated he has received several calls from
constituents wanting to know the status of the access being available
and fully supports some type of media to inform the public regarding
project status. Allen MacNeil stated he had also received calls
regarding the same.
3. CORD - State-Owned Land Surplus Land Review
Chairman MacNeil stated
that there is a parcel of land in Belmont, which has been reported
in the newspapers of late, regarding access issues. Unfortunately,
Vice Chair Tom Quarles is not available to talk about this issue
today.
Cheryl Killam questioned whether the property in Weare (SLR 06-004
- Town of Weare) was for pedestrian or vehicular traffic. Dan responded
that this parcel was for vehicular traffic. The town is looking
to upgrade a current one-lane bridge to a two-lane bridge and needs
easements in order to accomplish this. Jacquie Colburn stated that
this parcel fell under the jurisdiction of, and was subject to review,
by both the Rivers Management Advisory Committee and the Lakes Management
Advisory Committee. Both have recommended approval.
4. F&G Project Update
- Daniel R. Lynch, F&G
1. Umbagog Lake (Cambridge)
- One permitted project approved for this season, reconstruction
and improvement of existing ramps to reduce ice damage.
2. Baker River (Plymouth)
- Wetlands permit received. Additional information provided to DES
and ACOE for review, currently awaiting response due within 30 days.
Once complete will be permitted and able to move forward for construction
this season.
3. Millsfield Pond (Millsfield)
- Wetlands permit received. Additional information provided to DES
and ACOE for review, currently awaiting response due within 30 days.
Once complete will be permitted and able to move forward for construction
this season.
4. Turtletown Pond (Concord)
- Wetlands permit received. Additional information provided to DES
and ACOE for review, currently awaiting response due within 30 days.
Once complete will be permitted and able to move forward for construction
this season.
5. Pleasant Lake (Deerfield)
- Looking for response to wetlands permit application soon. Many
inquiries about this site. Boulders on site will be removed. A parking
lot and staging area will be constructed, current asphalt ramp will
be replaced, and handicapped access provided.
6. Lambert Park (Hooksett)
- (Merrimack River) will be submitting wetlands permit to DES within
the week. Damage to concrete logs due to plowing of snow, and the
river has been undermining the approach to the ramp and the ramp
itself. Permit will allow for reconfiguring of the existing double-wide
ramp to be more in line with angle of downstream.
7. Manning Lake (Gilmanton)
- Permit application for Manning Lake will be submitted in approximately
two weeks to take out asphalt ramp that stops short of the water
and replace it with a full concrete ramp.
8. Merrymeeting (New
Durham) - Dual project: Replacement of water line to Powder Mill
Hatchery and boat access site. Met onsite with landowner to discuss
the Powder Mill Hatchery waterline project. Information regarding
reconfiguration of waterline presented to the landowner who would
like to sell us one acre for construction of a parking lot. Plans
are 90% completed and should be moving forward with permitting in
the near future. Project was discussed with both DES and the ACOE
and both seemed pretty much on board with the project.
9. Sunapee - Wild Goose
(Newbury) -Director Perry, a representative from FST, and a representative
from the Attorney General's Office met with the Newbury Board of
Selectmen on April 17, 2006 to present the concept for design of
the site, as well as what has been worked out between F & G
and DOT regarding intersection improvements. The town had completed
their own traffic study and that report will be reviewed by FST
to look for correlation with the study completed by the state. Common
issues were addressed including the attempt to move the ramp back
in closer to the shore and having the breakwater come out past the
toe of the ramp, and having a double-wide ramp with a stationary
dock in the middle and another dock on the outer side of the second
ramp to alleviate any problems pulling in to the ramp. There are
currently two handicapped parking spots in the design, one of which
falls within the 50-foot setback for shoreline protection. At this
time it is unclear how this will be addressed due to limited space
because of existing topography of the site. Most discussion with
the selectmen focused on traffic issues at the intersection at Route
103.
10. 1995 PWAAB Priority
Listing - Dan stated he should have this updated and ready for the
June meeting. Also the GIS Mapping Initiative based on boat access
sites will also be presented to the Board in June, showing what
sites are available and what state agency they are owned/maintained
by, this will also show the Road to Public Waters sites as well.
Brian Giles questioned whether this information would be in a format
available to the public. Dan stated that, yes, it would be available,
most likely broken down by county. This information will help the
Board to know what sites are out there and determine where additional
sites may be needed.
Brian Giles asked Dan
about the status of the Hilton Park boat ramp repairs. Mike Pillsbury
of DOT answered. DOT has submitted the wetlands permit but has not
yet heard back from DES in order to initiate repairs. Mike was not
sure when the permit would be approved or when repairs would take
place. Dan Lynch noted that the permits do sometimes take longer
to approve, this is especially true for tidal waterways, which also
require Governor and Council approval. Chairman MacNeil stated that
the permitting process can be slow and tedious with many hoops to
be jumped through which can be very frustrating. Thanks to all for
your patience.
It was noted that an
updated version of the matrix would be sent along with the meeting
minutes.
5. Legislative Update
- Chairman Allen K. MacNeil
Chairman MacNeil noted
there was nothing to report at this time.
Jacquie Colburn asked
whether the Board should consider taking a position regarding Surplus
Land Review SLR 06-004 - Town of Weare. Jacquie made a motion to
discuss, which was seconded by Dan Lynch. Carol Barleon questioned
if this was the same item that both the Rivers and Lakes Management
committees had voted in favor of. Jacquie stated that it is and
that the Piscataquog Local Advisory Committee had also reviewed
this item under the Rivers Program and is also in favor of its moving
forward. This is based on public benefit and public safety, as there
is not a big impact on the land. Carol Barleon made a motion to
concur that the land be turned over, motion seconded by Cheryl Killam.
The Board voted unanimously to approve.
Chairman's Comments
Please take note that
the June meeting has been rescheduled to June 19th, 2006. Chairman
MacNeil thanked the Board for responding to the Administrative Secretary
regarding attendance at these meetings. It is helpful to know ahead
of time if there will be enough members in attendance to be able
to conduct business.
Carol Barleon questioned
the date of the July meeting, which was confirmed to be July 10,
2006 in order to accommodate the holiday.
Dan Lynch spoke regarding
the CORD surplus review item in the Town of Belmont. When CORD was
discussing this item there was much talk about the Railroad right
of way. Representatives from the DOT's Bureau of Rail and Transit
will be invited to attend the June meeting.
Other Items for Board
Consideration
Paul Blizzard initiated
discussion about the issue of the state leasing land along the rail
corridor. There was a house bill regarding leasing of shorefront
railroad right of ways, sponsored by the NH Lakes Association. NHLA
was strongly opposed to leasing and asked for a study to be done;
the bill was killed in the House. Paul believes the state should
lease that land and benefit from the revenue while the people benefit
from the access to the land. In a former vote by this board it was
determined that is was best to not lease that land due to the fact
that it was mostly contractors and developers who were benefiting
by leasing from the state and then charging homeowners large fees
for access. Representative Chaplin stated that the people would
not benefit, only the real estate agents and developers Chairman
MacNeil stated that the Board should really look at the good of
the whole not just the few when determining access.
Dan Lynch spoke from the perspective of F & G. Aside from the
public access issue the rail corridor right of way actually goes
into Lake Winnesquam. It would be best to have DOT come to explain
the issue. Each site needs to be looked at individually as they
all differ in the ways in which the public could plausibly access
them. Dan believes DOT will be able to clarify some of these issues
so the Board will have a full understanding of the rail corridor
provisions and parameters. While public access is an issue, F &
G's larger focus at this particular site had more to do with management
of endangered wildlife habitat, as this area is a winter roosting
area for eagles. There was much discussion at CORD regarding an
abutter providing easement to the Town of Belmont for a bike path
that would be on the inland side of the rail corridor that is being
looked at in conjunction with the City of Laconia River Walk, which
also includes portions of the corridor. There are many concerns
from a biological standpoint and a biologist from Fish & Game
will meet with the abutter to investigate further. Apparently, according
to Lou Barker of the DOT, who spoke at the last CORD meeting, there
is no public access opportunity at this site.
Jacquie Colburn stated that the LMAC recommended against the lease
disposal at their March meeting because as they understand it and
the way they put it is this: "Existing railway that runs parallel
to the lake and the right of way in which it resides presently provides
the public the opportunity to travel along the lake via foot or
motorized vehicle i.e. snowmobile" and it is obvious that snowmobiles
do use that corridor regularly. "Since the state owns the land
to the water's edge the public has the opportunity to sit along
the lake, swim from the shore or fish from the shore. While the
granting of the lease would not legally prohibit the public from
using the leased area, in practice the public's ability to engage
in recreational activities along this area of Lake Winnesqaum's
shoreline would be significantly impacted." Jacquie stated
that if the DOT is saying that the public does not have access to
this area that is something she is not familiar with and having
them explain at a future meeting is necessary. If anyone has questions
regarding this item they should write them down and bring them to
the June meeting where representatives from DOT are expected to
be in attendance. Johanna Lyons stated that this will be a good
discussion to have, not only for this site but perhaps there should
be a bill to study all state owned lakefront property to determine
if we in fact do want to lease out this property. It could be of
benefit not to lease any of this type of property because there
may be many public benefits to be considered in not leasing, other
than monetary benefits.
Paul Blizzard questioned why we would want to stop such a huge tax
base? Ninety percent of the homes on the lakes are second homes
and so are not a drain on the city's resources for the taxes they
pay.
Carol Barleon stated
that the issue can get out of hand when looking at it one piece
of property at a time. The Board needs to know the total effects
of these leases on our resources before we can make good decisions.
We need to look at the aggregate effects, not just the individual
effects. Chairman MacNeil stated that Fish & Game is totally
responsible for providing boating access to the state's waterways
and this Board is there to support them. We need to look at the
big picture, even when the issue is controversial.
Dan Lynch spoke to the
Board regarding Harilla's Landing. Dan will be providing an old
concept plan to Tom Quarles for review. Allen will place this item
on the June meeting agenda. Paul Blizzard said that was the reason
that guest Jim Nagle was in attendance at this meeting. Mr. Nagle
stated that as a contractor he wants to ensure that contractors
have some say in the planning and will be able to access the landing
as necessary to get their business done. There is currently very
limited access for contractors. Island development has dramatically
increased and frequently contractors doing marine based work have
no access. Chairman MacNeil will make sure Vice Chair Tom Quarles
is aware of this issue and can speak to it at the June meeting.
Mr. Nagle will plan to attend on June 19, 2006.
Chairman MacNeil stated
that his term would be up as of October 27, 2006. However, due to
his brother in law being seriously ill, he must spend time with
him during rehabilitation. July will be Allen's last meeting as
Chairman, with Tom taking over in August. Allen is very sorry to
be leaving the Board as he has enjoyed tremendously his time here.
Allen urged the Board to please keep up the good work.
Old Business
Representative Dunc Chaplin
questioned Chairman MacNeil's request for a meeting with the Governor
regarding certain member's non-attendance at these meetings. Allen
has not heard anything yet but will be talking with his assistant,
Kathy Goode soon. Dunc stated that he anticipates follow up on that
issue would be favorably received by the Governor.
ADJOURNMENT
Paul Blizzard moved to
adjourn the meeting. Seconded by B. David Bryan. Unanimously approved.
Meeting adjourned at
10:15 a.m.
<Return to
top>
________________________________
PUBLIC WATER ACCESS ADVISORY BOARD MEETING
MINUTES
April 3, 2006
9:00 a.m. - NH Fish and Game Headquarters
Members Present: Allen
K. MacNeil, Chairman; Carol Barleon, OEP; Paul Blizzard, Roger J.
Bellerose, Sr., B. David Bryan, Rep. Duncan Chaplin; Jacquie Colburn,
DES; Johanna Lyons, DRED; Maynard Goldman, NHLA; Michael Pillsbury,
DOT;
and Daniel R. Lynch, F&G
Members Absent: Thomas
Quarles, Esq., Vice Chairman; David Barrett, DOS; Brian Giles, Patricia
Goodridge, Senator John T. Gallus, Senator Joseph D. Kenney, Cheryl
Killam, and Representative John Klose
Audience Members: Dick Smith, NH Bass Federation
*****************************************************************************
MEETING CONVENED
Chairman Allen McNeil
called the meeting to order at 9:03 a.m.
Chairman MacNeil introduced
Richard Smith a member of the audience who had been nominated by
Governor and Council to replace John Cowan on the PWAAB. If confirmed
at the April 5, 2006, Governor and Council meeting, he will officially
be on the Board at the May meeting.
AGENDA ITEMS
1. Approval of the February
6, 2006, Meeting Minutes - Allen MacNeil, Chairman, PWAAB
Jacquie Colburn requested
the following corrections to the minutes as follows:
Page 2, paragraph 1, last sentence; change "Towle" to
"Toll."
Page 2, Paragraph 2, last sentence; add the word "boats"
at the end of the sentence.
Page 2, Paragraph 4, 3rd sentence; change "we have secured"
to "F&G has secured the demolition permit."
Page 3, 3rd Paragraph, change spelling of "Cabrinelle"
to "Cabanel."
Page 4, paragraph 2, last sentence; change . . . "therefore
the public will not (delete with) come in contact with the soil."
Roger Bellerose requested
the following change to the minutes on page 3, last paragraph:
Change the word . . . an attempt by the City to " . . . an
attempt by F&G to . . ."
Dan Lynch requested a
change to page 4, 1st sentence, 2nd line: ". . . and Mr. Lynch
(delete "was not sure") and replace with F&G's consultant
had subsurface exploration completed."
Maynard Goldman requested
the rewording of Paragraph 5, 2nd sentence through the rest of the
paragraph as follows:
"Maynard Goldman felt we should contact the Winnisquam Association.
It sounds like a deal for the developer and the Board should not
support such private arrangements. He believes it might require
a change in legislation and the cost is very low. However, even
if the cost is raised, he believes there are issues. There are too
few areas left for public access."
Roger Bellerose moved
to approve the minutes of March 6, 2006 as amended; seconded by
Maynard Goldman. The Board unanimously approved.
2. Update on Winnisquam
Access Site - Jacquie Colburn, DES
On March 17, 2006, a
permitting meeting was held at Fish and Game. Two hours was devoted
to discussion of the Winnisquam site with representation from FST,
F&G, DES, and Army Corp. of Engineers. An additional two hours
was spent discussing sites at Sunapee and Merrymeeting Lakes. Kevin
Gagne of FST did introductions for the concept of the Winnisquam
access site. A wharf type structure with some dredging was determined
to be the best approach. The Corps of Engineers asked about the
river environment because of sediment. ACOE would like to try and
look at sediment transport to see what type of sediment is coming
down the river. Jacquie Colburn did note DES did not want to slow
the project down but wanted to know how the need for dredging in
the future would be addressed. The Butler Building demolition was
discussed in detail and it was determined that no Wetlands approval
is required. There was in-depth discussion about surface water treatment
and how best to handle that aspect of the project.
Dan Lynch referenced
the RFP for the Butler Building demolition and noted two responses
were received: one for about $180,000 and one for about $86,000.
Dan briefly reviewed the asbestos and lead issues on the buildings
based on a report completed by DES contractors. The buildings are
old greenhouse frames, one has no siding or roof. The other one
is covered with sheet metal siding and windows. Some of the paint
in the covered building has been identified as lead-based and some
of the glazing on windows is asbestos. All of this has to be handled
in accordance with DES and EPA standards for dealing with hazardous
material abatement. Based on the borings we did on site, what we
are looking to do is to take and move the top layer off the site
and deposit in hole left from removal of the Butler Building foundations.
Mr. Lynch informed the Board that the contractor paperwork was received
Friday, March 31, and F&G was looking to have that contract
as a late item at the April 5, 2006 Governor and Council meeting.
The contractor has 120 days to complete the removal. They will have
to work their schedule around the work hours of the Winnipesaukee
River Basin Wastewater treatment facility (7 am - 3 pm) as that
is when they will have access to that part of the site.
Jacquie Colburn discussed
flow model. Mr. Lynch stated he did not think F&G will be doing
flow model. The cost could be $35,000.00 and would take 3 months.
We are trying to review contour plans for some of the sewer lines
that are downstream of the access site parcel to include trying
to get information from the Laconia Public Works.
Jacquie Colburn stated,
we will be meeting Friday, April 7, with the working group and will
brief the City Mayor and the City Manager. Ms. Colburn mentioned
that in the last week of March a site visit was done with Darlene
Forst (DES). Darlene had not seen the site yet and we reviewed the
river along the edge to review sediment and the Dam at Belknap Mill
and Lake Opechee. Jacquie requested that Dan Lynch send her FST's
flow modeling estimate.
Dan Lynch reported the
NHFG contacted Ralph Longevin, owner of the land which is now Martel's
to tell him we will be doing some river dredging and to see if he
would be comfortable to sign off on a letter required to go with
the wetlands permit application. Mr. Longevin said he would sign
off on a letter. F&G moved further with the leasing of parking
at the storage center on Winnisquam Ave so folks could use Martel's
ramp. Parking on the property would be for 42 trailered spots and
very hopefully this will be the last time NHFG will lease.
Carol Barleon noted that
the City of Laconia has received a grant for a car-top/canoe site
on the Winnipesaukee River by Belknap Mills site.
Roger Bellerose mentioned
the coffer dam requirement. Mr. Dick Pinney expressed to him that
he did not know. However, according to the NH Sunday News, it states
that Mr. Pinney stated there has been quite a lot of controversy
about the proposed state boat ramp slated to be built on property
just purchased on the river. Mr. Pinney reported the site is fraught
with problems, such as removal of buildings and launching/retrieving
boats during times of big flow. Mr. Pinney further reported that
the Army Corp was never solicited for its input into this construction
project but has now injected its presence and raised a number of
very serious doubts and possibly the need for coffer dams, etc.
Mr. Pinney further reported that much of this information was known
before the Executive Council okayed this land purchase and members
of the public were very disappointed that they gave their approval
to purchase the land. Mr. Bellerose said the article mentioned the
cost of the project could wipe out the whole amount budgeted for
access projects and was this true.
Dan Lynch responded to
Mr. Bellerose that it was a shame that Mr. Pinney was provided inaccurate
information. Mr. Lynch reported that the ACOE was present at an
on-site meeting in August 2005, as well as at the March 17th project
meeting with DES and Ms. Colburn has communicated ACOE comments.
Mr. Lynch further reported that initial estimate of the project
was at about $1 million, and between available state boat access
funds and federal boat access funds there is about $3 million available
for boat access projects.
3. CORD - State-Owned
Land Surplus Land Review (Vice Chair Quarles and Jacquie Colburn)
Chairman MacNeil stated
that Vice Chair Quarles was unable to attend the meeting due to
prior work obligations, but if at all possible will try to make
it by 11 a.m.
There was a brief discussion
on the Laconia Sun article about where it mentioned the Board had
voted "for" the lease. Chairman MacNeil did speak with
the author of that article to correct his misinterpretation and
to let him know that he misquoted the vote of the PWAAB. For the
record, the Board voted not to support 11-1 the lease of the railroad
corridor in Belmont along Lake Winnisquam for a private development.
There was continued Board
discussion on the issue of $25/linear foot. Mr. Blizzard felt the
Board should be discussing business relative to current access not
the fee structure.
Richard Smith felt the
public should be getting something back and that the fee of $25
per linear foot is too low. Also, can that fee by put back into
boat access? The question was referred to Rep. Chaplin for a response.
He replied, 1.) public use, and (2.) what should it be used for
and how much.
Jacquie Colburn reviewed
the agenda of the Lakes Advisory Management Committee meeting of
March 24, 2006, in which the LMAC voted against disposal. A memo
to that affect will be going to Peter Helm of CORD. CORD meets every
other month and the next scheduled meeting is April 6, 2006 and
then again in June.
Jacquie Colburn referenced
another Land Surplus Review that needs to be placed on the PWAAB
May agenda for review. SLR 06-004 - Town of Weare from DOT to take
land near a bridge for a bridge replacement project.
4. F&G Project Update
- Daniel R. Lynch, F&G
1. Baker River - Confirmation
from DES for issuance of wetlands permit. Army Corps of Engineer
has asked F&G for additional information (April 27 to respond).
2. Lambert Park (Hooksett)
- (Merrimack River) will be submitting wetlands permit to DES within
a couple of weeks. Maynard Goldman noted that the ramp is deteriorated.
It is more so upstream due to the river eroding part of the approach
to the ramp. Final plans and documents are ready to submit for the
wetlands permit.
3. Connecticut River
(Orford) -Worked out the MOA and provided final copy back to the
Town. Trying to get town attorney to review and when F&G hears
can start finalizing plans.
4. Hoyt Pond (Madbury)
- Right-of-way to Pond. There is a subdivision going on in the area.
Agreed to a swap of ROW. Legal documentation on file. Will be putting
up sign on the location.
5. Winchester - Forest
Lake. The landowner closed the ramp due to liability issue. F&G
is looking to purchase some portion of land: One-acre parcel and
a three-acre parcel. 2 scenarios have been provided to property
owner.
Roger Bellerose asked
about the appraisal but Dan Lynch did not have a figure.
6. Merrymeeting (New
Durham) - Dual project: Replacement of water line to Powder Mill
Hatchery and boat access site. Landowner where boat access parking
would go wanted to see what was happening with waterline project.
Looking to schedule a meeting with the landowner, Lake Association
members and town members. It may or may not negate a parking issue.
Plans are 80% completed. The parking abuts to DOT right-of-way.
Mr. Lynch explained to Roger Bellerose what F&G was attempting
to do relative to the gravity base waterline. Looking to put the
new line in as close as possible without impacting the existing
line.
Chairman MacNeil asked if Chuck Miner was involved in the project.
Dan has the plans for the site as they exist. Mr. Bellerose discussed
asbestos pipe issues. DES says you have to bag it up and dispose
of it properly.
7. Sunapee - Wild Goose
(Newbury) - Discussion took place with the engineers in mid-March.
Submit application with plans. Dan has sent a request to the town
to go over plans and the intersection concept. The Newbury Board
of Selectmen meeting scheduled for April 17 is for informational
purposes only. Dan told Roger that he was not sure what weighs in
on the Governor's decision. Besides, NHFG does not want to impact
DRED's park operations. Discussed dredging, loons, lake depth. Looking
at 400' out into the lake for boats to get into deep enough water
in the lake.
Carol Barleon looking
for updated matrix. It was noted that the matrix would be sent along
with the meeting minutes.
8. Hilton Park - Received
100% completed plans, which were submitted to DOT who will handle
the permit. Mike Pillsbury said they have been sent to DES and hope
to have permit in April.
9. Pleasant Lake (Deerfield)
- Awaiting response on wetlands permit application. DES confirmed
that the application was administratively complete. Mr. Bellerose
asked about tree removal and Dan explained there were about 7 trees
that met the scenic road criteria and about 17 total in right-of-way
of town.
5. Legislative Update
- Chairman Allen K. MacNeil
Chairman MacNeil noted
there was nothing to report at this time.
7. Hobo Railroad - Mike
Pillsbury/DOT
Mike Pillsbury updated
the Board on the research the subcommittee had completed to date
relative the Hobo Railroad. The entire management plan was located
in the DOT files and they will be moving forward with the Management
Plan. There is a process that needs to be followed to address public
access at the railroad corridor. He will keep the Board informed
as it moves forward.
5. Legislative Update
- Continued Discussion - Legislative Activity
Rep. Chaplin - Of the
Senate bills that he sees in the Recreation area it seems the concentration
deal with Trail issues.
Jacquie Colburn as an
FYI mentioned HB1343, which is before the House, which would change
CORD's status as being an "advisory" board only versus
approval authority for surplus land reviews.
Dan Lynch asked Mike
Pillsbury a question relative to the Hobo Railroad and the time
frame for getting this done. Bill Hauser is the person who will
assign someone to do this and at this time Mike did not know. Land
Management plan might not take a lot of time. Railroad line - adds
a wriggle.
Hobo Railroad to be on
the agenda for May.
8. Comprehensive Shoreland Protection Act
In 2005 there was a bill
that created a Commission to study the Shoreland Protection Act
and make any recommendations. Rep. Currier, Chairman of the Recreation,
Resources and Development Committee of the House is the Commission
chair. Discussion took placed on the CSP Act and the role PWAAB
plays relative to Chapter 483, 403A and 430B. Board members suggested
Dan and the Chairman compose a letter to Rep. Currier to outline
that the Commission take a look at Public Boat Access sites and
permitting requirements. There is some discussion about primary
structures and water-dependent structures and how those provisions
in the CSP Act apply to public boat access facilities, such as boat
ramps, approaches to the ramp, handicap parking and parking lots.
The motion to write to
Rep. Currier relative to the Board interest in having the CSP Act
Commission look at public boat access facility permitting compliance
was made by Maynard Goldman and seconded by Jacquie Colburn. With
10 members voting, 9 were in favor and one abstained (Dan Lynch).
Johanna Lyons asked about
the letter addressing all type of public access, such as swimming
beaches.
ADJOURNMENT
Paul Blizzard moved to
adjourn the meeting. Seconded by Roger Bellerose. Unanimously approved.
Meeting adjourned at
10:38 a.m.
<Return to top>
________________________________
PUBLIC WATER ACCESS ADVISORY BOARD MEETING MINUTES
March 6, 2006
9:00 a.m. - NH Fish and Game Headquarters
Members Present: Allen K. MacNeil, Chairman, Thomas Quarles, Esq.,
Vice Chairman, Carol Barleon, OEP; Paul Blizzard, Roger J. Bellerose,
Sr., B. David Bryan, Rep. Duncan Chaplin; Jacquie Colburn, DES;
Shari Colby, DRED; Maynard Goldman, NHLA; Cheryl Killam, Gov's Commission
on Disability; and Daniel R. Lynch, F&G
Members Absent: David
Barrett, DOS; John Cowan, Brian Giles, Patricia Goodridge, Senator
John T. Gallus, Senator Joseph D. Kenney, and Representative John
Klose; and Michael Pillsbury, DOT
Audience Members: Dick
Smith, NH Bass Federation, and Jared Teutsch, NH Lakes Association
*****************************************************************************
MEETING CONVENED
Chairman Allen McNeil
called the meeting to order at 9:06 a.m.
AGENDA ITEMS
1. Approval of the February
6, 2006, Meeting Minutes - Allen MacNeil, Chairman, PWAAB
Corrections to the minutes
as follows:
Page 1, paragraph 2,
1st sentence; delete the "t" following B. David Bryan's
name.
Page 3, item 3, middle of paragraph 2; at the end of the sentence,
"He explained what you would see as you rode . . . " delete
the period at the end of the sentence and continue on to read, "
. . . cross the property line between the State and Harilla's Landing
Yacht Club." New sentence to begin with "The dock area
near . . ."
Page 4, 2nd paragraph; add quotation mark following the words unload
dock," so cars . . .
Page 5, 4th paragraph, last sentence; Add the word help. Dig-Safe
cannot help because . . .
Page 8, 1st paragraph, add "per year" following $25 per
linear foot per year.
Page 8, last paragraph, change HB 1364 to HB 1426.
Carol Barleon moved to
approve the minutes of February 6, 2006; seconded by Maynard Goldman.
The Board unanimously approved the minutes as amended.
2. Update on Winnisquam
Access Site - Jacquie Colburn, DES
Jacquie Colburn gave
an update on the working group meeting held Friday, March 3, 2006.
One of the agenda items for this meeting consisted of a review of
her presentation of February 22, 2006, in which Jacquie reviewed
the Winnisquam Boat Access project status at a Governor and Council
Breakfast held at DES. Jacquie gave the Governor and Council and
others an overview of the site and stated that when this project
is complete it will be the one and only publicly owned and maintained
access site on the lake, and it will be open to the public on a
non fee basis. She used aerial maps to point out the access area
where the Winnipesaukee River flows into Lake Winnisquam. She further
talked about the status of access on the lake and that one time
there had been as many as 14-15 privately owned and maintained access
sites and that in the summer of 2004 Martel's was the only one available.
Further, because of the parking problems the owner of Martel's closed
it and brought it to the attention of former Governor Benson. Then
Fred Toll, former City Councilor, asked if the State and the City
could work together to develop the area across from Martel's, which
is the Laconia compound we are working on.
Ms. Colburn reviewed
the area noting the regional sewage treatment collection system
as well as the property that used to be the Laconia Wastewater Treatment
facility. Because there are many on site structures that are active
as well as abandoned, and some of these structures are more than
50 years old, it was necessary that they be reviewed by the NH Historical
Resources Division. Jacquie reviewed another aerial map which showed
what the access site area would look like when completed. With 35-36
parking spaces for trailered and canoe car top as well as several
spaces for handicapped van accessible, one space for marine patrol
and one for a conservation officer. She reviewed the docking structure
and the area for tying up boats.
Jacquie then gave the
Governor and Council a synopsis of what we have accomplished to
date. Another map showed the property transfer between Fish and
Game and the City of Laconia which has taken place. Also, the MOA
had been signed and approved. The Digester Building, which had been
part of the Winnipesaukee River Basin Program, is now going to be
used as part of the Fish and Game access site. We have completed
the environmental site assessment, the hazardous materials audit
for the building, completed the open house last summer, and have
submitted the papers to the NH Historic Resources (NHHR). NHHR determined
that the site was eligible for the State and National Historic Register
(there is no other sewage facility left in the State in this condition).
The NHHR is most interested in the Digester Building and has asked
that it be retained. As a result, Councilor Burton and Commissioner
Nolin asked a few DES staff to research the feasibility of federal
funding to rehab and reuse this building in the future.
Jacquie Colburn informed
Governor and Council that the next steps are to obtain all the permits,
and that F&G, DES and Faye, Spofford & Thorndike (FST) would
be meeting soon to prepare applications and plans to obtain all
the federal and state reviews and permits. Fish & Game is working
on their bid package for the demolition work and also working with
the USFWS to complete the NEPA environmental checklist and finalize
the funding package for federal aid grant review. She noted that
F&G has secured the demolition permit with the City of Laconia
to remove the Butler Buildings. She mentioned the various agencies,
private and public, as well as neighbors involved in the site, and
that the timeframe for construction of the ramp is late summer or
early fall and plans are to have the site open for the 2007 boating
season.
Jacquie shared questions
received from Governor and Council. Councilor Burton asked that
Fish and Game and the Department of Environmental Services meet
with the new Mayor of Laconia to make him aware of the project and
bring him up to speed. He further talked about the number of parking
spaces and said that based on his observation there is always more
demand for spaces than available. Councilor Burton further discussed
the future use of the Digester Building as some kind of resources
and/or museum type facility and how water quality has improved immensely
since the 70's when wastewater was being discharged into the lake.
Governor Lynch asked
Jacquie Colburn about the timeframe and mentioned that Representative
Veazey was interested in having something done on the site in April
and she explained that we still had a great deal of work left to
do and would be focusing on doing the ramp construction in preferably
lower flow periods. Councilor Pignatelli also asked if there would
be anyone from F&G or DES at the ramp once the site was opened.
Ms. Colburn replied that the Winnisquam Watershed Association had
expressed an interest in participating in the Lake Host Program.
The remainder of the
meeting on Friday was spent going over our planned schedule. Dan
Lynch will e-mail the group a detailed work schedule for the next
several months of what needs to be done and when, as soon as possible.
There was a pre-bid meeting
held Friday, March 3, 2006 attended by several contractors who expressed
interest in securing the contract to remove the buildings.
Dan Lynch commented that
Director Perry did contact City Manager Eileen Cabanel to coordinate
a meeting with the new Mayor. In follow up on the demolition of
the Butler Building/demolition work, Mr. Lynch noted that responses
for the RFPs were due March 17, 2006, and we would be reviewing
them and awarding a contract. Based on the dollar amount, this contract
will require Governor and Council approval. We hope to make it onto
one of the G&C April meetings for their approval. The plan is
to have the work completed within 120 days of contract approval.
F&G is looking to
move forward with renewing our agreement for parking so the public
can utilize the ramp at Martel's again this boating season. As in
the past, we hope to have parking provided from April 1 - October
1. Dan reiterated Jacquie's earlier comments relative to working
out a timeline schedule to get this work started in late fall so
that the site will be ready for the 2007 boating season.
Dan Lynch noted one issue
that has not been dealt with by Fish and Game before on a project
of this size. A recent change in State Statute RSA 21-I:80, allows
Fish and Game to do public works projects up to $250,000 without
going through the Bureau of Public Works/Design and Construction
under the Administrative Services Department. Based on the estimates
for the cost for this site, it will be over this $250,000 cost estimate,
therefore, we do have to work through the Bureau of Public Works/Design
and Construction under the Administrative Services Department. We
did meet with the Public Works people on Friday, March 3, 2006 to
discuss this and other access projects that will go over the $250,000
threshold. They are not going to get involved in the building demolition
component, but from this point forward they are more or less the
lead agency. They will be overseeing the plans done for the design,
and they will be bidding out the project for the State of New Hampshire.
The plan is to have an outside contractor. It adds another dimension
to the project. Hopefully, it will not impinge on the timeline.
Roger Bellerose asked
about the land transfer and if there was an attempt by F&G to
have the Butler Buildings removed. Dan Lynch answered that when
an appraisal was done for the property it was laid out as a vacant
lot (no structures) which would provide the highest, best value.
The estimated appraisal value of the Butler Buildings is near $0
and the estimate for what it would cost to have those buildings
demolished was provided to the City. In its current state the value
of the land was approximately $235,000 (with the Butler Buildings)
and the City agreed to a price of $180,000. The land was valued
at $265,000 - it was estimated to be about $30,000 to take the buildings
down.
Mr. Bellerose further asked if any subsurface exploration for contaminants
in the soil was considered, and Mr. Lynch stated that F&G's
consultant had subsurface exploration completed. He did say that
part of that is being addressed in the demolition work. In working
with DES, the whole site will be covered, therefore the public will
not come in contact with the soil.
3. CORD - State-Owned
Land Surplus Land Review (Vice Chair Quarles and Jacquie Colburn)
Vice Chair Quarles reviewed
CORD's memo of February 1, 2006 in which DOT proposes to lease 1,305
linear feet of lakefront on Lake Winnisquam to Sun Lake Village,
LLC, to allow permitting of a docking structure and construction
of a pedestrian crossing as provided in RSA 228:57-a. This law allows
leases of State-owned railroad property to landowners whose property
is separated from public waters by the railroad for the purpose
of constructing docks or mooring fields. The applicant owns property
abutting the State-owned railroad corridor in Belmont.
This State Owned Land,
Surplus Land Review, Town of Belmont SLR 06-001, and a series of
news articles about the general issue of leasing State-owned property
for private docks were discussed. In particular, a Union Leader
article of September 3, 2005, which focused on Winnisquam issue
at hand, was discussed at length.
Using the Winnisquam
map, Mr. Quarles pointed out where along the shoreline the railway
was located. The dock proposal under discussion is near Mosquito
Bridge on Route 3 going from Tilton to Laconia. On the north side
of Mosquito Bridge there is shoreline which the rail line follows.
The developer is proposing to get water access across the state-owned
right-of-way under this leasing statute. The plan is for 12 docks
so with a 24-unit subdivision each owner would have one side of
a dock.
PWAAB has been asked
by CORD to give its recommendation on this Surplus Land Disposal
proposal under our statutory duty to advise CORD on public water
matters. There still is an outstanding issue as to whether the statutory
role of the LMAC and/or RMAC in reviewing these proposals means
the recommendation from either of these boards is a veto. This issue
has been with the Attorney General's Office for an opinion for a
number of months and it is still there awaiting a decision. Also,
in previous meetings we have discussed legislation of one or more
bills that would call for a study commission on this issue and a
moratorium on this leasing while that study commission is in process.
Tom Quarles noted that
once these various boards weigh in and give their recommendations
to CORD, it is up to CORD to decide if they think it is a suitable
surplus land disposal. If CORD agrees, the proposal goes before
Governor and Council. Jacquie Colburn clarified that it goes through
the Legislature's Long Range Capital Planning and Utilization Committee
and then onto Governor and Council. Vice Chair Quarles stated that
although the response date to CORD was due March 6, 2006, there
is an agreement with CORD on projects of any magnitude or controversy
where they will allow us extra time. Jacquie Colburn confirmed that
CORD meets every other month and will not be meeting until April
6, 2006. PWAAB will be meeting next on April 3, 2006. Jacquie stated
that the LMAC discussed this at their last meeting, and it will
be on their agenda at their next meeting.
Chairman MacNeil mentioned
a newspaper article referring to the leasing fee of $25 per linear
foot per year. Ms. Colburn thought it might be under consideration
in some proposed bills, however, referred the question to Jared
Teutsch (NH Lakes Association). He was not familiar with any such
referenced legislation. Jared explained that HB 1684, which is a
NH Lakes Association bill, would create a study commission with
a moratorium on leasing. The committee voted inexpedient to legislate
which is their recommendation to kill the bill. Jared thought it
would go to the full House February 7, 2006 and that NHLA plans
to fight it. He believes the committee did not understand the intent
of the bill. NHLA questioned if we should be giving state-owned
property for private use. The committee looked at the bill as a
CORD process.
Rep. Chandler's bill,
HB 1342, would essentially eliminate CORD as a reviewing body; it
would become an advisory body to advise the Long Range Capital Planning
Committee. It would no longer have the ability to vote up or down
on lease proposals. Chairman MacNeil asked who would make those
decisions if CORD was out of the picture, and Jared said the Long
Range Capital Planning Committee would make them and then pass them
on to Governor and Council. Jared informed the Board this was proposed
under HB 1343 which did pass the Public Works Committee. Vice Chair
Quarles asked if this passed would the LMAC and RMAC make their
recommendations to the Long Range Capital Planning Committee and
Jared replied, "No." Jared Teutsch said the current process
would continue. The only change would be that CORD would no longer
have authority to vote up or down on the leasing or sale of state-owned
property. CORD will simply advise committees such as PWAAB, RMAC
or LMAC on the leasing or sale of state-owned property. Mr. Quarles
asked Jared if Rep. Chandler's bill changed the language regarding
how the RMAC or LMAC make that recommendation. Jared believes what
they discussed was the procedural details of what these boards already
have - they have to review it and vote "yes" or "no."
If they table the project, it essentially is a veto of the project
from a procedural standpoint. The House Public Works Committee did
not like the procedural veto ability of RMAC, LMAC or PWAAB so they
insisted upon an amendment to HB 1343. The amendment would include
that all those bodies would have to submit their minutes to the
Long Range Capital Planning Committee. This would allow Public Works
to be aware of these leasing/sale issues before they come before
them. This amendment was approved and Jared agreed to supply the
Board a copy.
Tom Quarles expressed
concern about the language of our statute and how much flexibility
PWAAB has on this project. If we are constrained by this language,
how are we are suppose to "serve as advisory committee to CORD
and alert CORD to any potential problems which may inhibit state
public water access efforts." There is no existing public access
at the present time. Jacquie Colburn responded there is access to
the area from the water and pedestrians can travel within the railroad
right-of-way to access the shorefront and water.
Mr. Quarles stated that
if and when this proposal is approved, there will be 1,300' of frontage
that has no public usage for at least 5 years at a bargain basement
rate. Furthermore, the expectation is that these leases are always
renewed. Mr. Quarles noted that the docks are not permanent; however,
he gave an example of the 18 Mile Point on Meredith Bay lease where
they were allowed to put in permanent docks. He felt this was an
example of where things could go.
Carol Barleon clarified
that this would open up 24 dock spaces for "high-end"
users, which would probably be used by non-residents of New Hampshire
traveling to the area. She questioned the traffic impact on the
lake. Carol asked, even though we are looking at access for the
State, do we also have ability to bring other issues to the table
for CORD and anyone looking at this request (for example, water
usage for our water bodies in the State)? Mr. Quarles asked the
Board if they were familiar with this area. Tom was familiar with
some very shallow water offshore in this area. It was known as a
very popular rafting area where power boats often anchored to beach
and party.
Tom Quarles asked Paul
Blizzard if he had any information on that part of the lake. Mr.
Blizzard discussed seasonal vs. permanent docks and felt that seasonal
docks tended to fall apart and that permanent docks had better longevity.
It was Mr. Quarles' understanding that permanent docks would not
be allowed. Tom questioned whether we should take a position to
preserve this site as a public assess site. Further, you could take
the position that anytime you have one of these private railroad
leases that some accommodation for public access should be made,
but it begs the question should it be developed at all as an access
site for either private purposes or a mixed private/public site.
Johanna Lyons felt that
if we continue to lease these lakefront railroad sites there should
be some type of public good that is shown. We have not seen these
leases and do not know the public benefit. She has been trying to
pull lease language from some DRED leases to see if there are some
good examples of resource protection, resource restoration or some
sort of public access benefit. If this is still the direction the
Legislature wants us to take in continuing to lease lakefront, there
needs to be public benefit to us.
Jacquie Colburn felt
we needed to keep in mind what the statute says for our particular
Board. That is, what public access is presently available at this
particular location? We need to think about the conditions that
exist; an undeveloped shoreline which means people can anchor right
near the shore at the present time and could go on to the property.
Because it is state-owned land, they could fish from their boat
or from the shoreline, and they could walk up the railroad corridor
to take advantage of any fishing. The Board needs to consider what
are the present opportunities now and how the proposal would inhibit
public access.
Tom Quarles asked Jacquie
if she knew if the Winnisquam Lakes Association has looked at this
request and taken a position. She did not know but would look into
it. Maynard Goldman felt we should contact the Winnisquam Association.
It sounds like a deal for the developer and the Board should not
support such private arrangements. He believes it might require
a change in legislation and the cost is very low. However, even
if the cost is raised, he believes there are issues. There are too
few areas left for public access.
Paul Blizzard did not
feel we should get into the fee or cost of rental of boat slips
as stated in one of the news articles. A $25,000 rental fee is not
going to happen. He felt it was thrown in by someone who was misinformed.
The boat slips should stay with those homes or condos and not be
for sale. He felt that houses should go for fair market value and
have a State fee for boat fees. Roger Bellerose felt it was a boat
access in reverse -- land that you access by boat only. He did not
feel that this Board should weigh in on whether or not this should
be leased.
As a member of the Resources,
Recreation & Development Committee, Rep. Chaplin would argue
any provisions that were made for the leasing of this should also
include equal opportunity for citizen of our State to access that
land. We are talking about selling their rights to protect future
waterfront and further felt it was a political issue and advised
the Board to think twice before making a decision.
Vice Chair Quarles brought
the discussion back to Johanna Lyon's comments in that there is
no public benefit to the project as presently proposed. The only
way from our Board's perspective to add public benefit would be
to recommend in some fashion that there be public access to these
proposed docks. Is this the direction to go in or does this Board
want to recommend that we see no public benefit unless or until
there is public access to these docks. Or being familiar with the
public access issues at Winnisquam, knowing we have a full state-of-the-art
site coming on line shortly on Water Street, plus we have the informal
access further up the east side at Governor's State Park, does this
Board think there is a need for an additional access site here?
Rep. Chaplin spoke relative
to the attractiveness of the site and in terms of how nice it is
to be able to be out in a boat or canoe and to be able to moor and
go onshore to picnic, etc. Tom Quarles pointed out the nearby location
of the Belmont Town Beach and did not recall much of any development
near this area for probably half a mile. Rep. Chaplin felt it might
be very attractive to boating and fishing to have this left undeveloped.
Mr. Quarles stated that allowing the proposal would be fragmenting
a very large piece of shorefront.
Dan Lynch referenced
a news article about action taken at a previous CORD meeting. The
article referenced information provided by Peter Blakeman, Chairman
of the State Conservation Commission. In his letter to CORD, it
said that ownership or leasing of shorefront land brings with it
the right to apply for concurrent mooring fields which pushes development
further into the lake. Dan questioned whether this was true. Jacquie
Colburn thought that it was correct, but this proposal would result
in an application to DES for docks. A mooring field proposal would
go before the Department of Safety.
Further, Dan had questions
relative to the September 3, 2005 Union Leader article. Recreational
trails are planned for folks to walk or ride to downtown Laconia.
It was Dan's understanding that Laconia is working on a bike/pedestrian
trail that goes either along or down this rail corridor. If there
is a proposal to do it here as well as the stretch the Town of Belmont
owns and then you consider this proposed private section of trail,
then it doesn't make sense. Dan felt the Board needed to gather
more information about this before making a decision. He thought
the public did not have the right to cross an active rail line.
F&G had looked at a parcel with a similar situation and did
not move forward because of that concern. We have some other concerns
relative to biological issues which will come up in permitting later.
It seems like we have bits and pieces of projects happening in this
area. Why should they have a specific benefit that the rest of the
public does not.
Rep. Chaplin would be
looking to the Attorney General's Office to provide a legal opinion
on this issue. Chairman MacNeil asked Rep. Chaplin if his committee
would ask the Attorney General's Office for that opinion and he
agreed and felt his committee would support him. Tom Quarles felt
we could get more information, but felt we had enough information
to vote and felt the issue was do we see any public benefit with
or without public access.
Johanna Lyons felt we
should be able to ask what the plan is for the 1,300' of shoreline
along that rail line. The Bureau of Rail & Transits should be
able to provide us with just how many miles of rail line they own
and how much has been leased. Board member Johanna Lyons moved that
the Public Water Access Advisory Board recommend against approval
of the proposed state surplus land disposal, Project SLR 06-001,
because there is no indication of any public benefit. In addition,
the Board recommends that CORD and the DOT Bureau of Rails examine
the entire issue of leasing State-owned railroad corridors that
provide lake and river access on a comprehensive basis including
the issue of fragmenting currently undeveloped shorefront and riverfront
property. The motion was seconded by Rep. Duncan Chaplin. With eleven
(11) members voting in favor and one (1) opposed (Paul Blizzard),
the motion passed.
Rep. Chaplin asked Jared
Teutsch what the NH Lake Association's viewpoint was. Jared said
the motion pretty much defined the purpose of HB 1684, which was
proposed by NHLA. The bill also addressed that the State shouldn't
be leasing shorefront at all, which was addressed by Rep. Chaplin
at this meeting. DOT does not know how much land they have, and
the fee of $25/linear foot per year is ridiculous.
Tom Quarles asked Jared
if he knew if the Winnisquam Lakes Association had taken a position
on this and he did not know. Paul Blizzard felt we should stay of
out the pricing issue and felt we should get away from lake access.
He noted that there was a multitude of private crossings. Vice Chair
Quarles stated that private crossings were not in the motion and
not what was being addressed.
Jacquie Colburn mentioned
that the Department of Transportation is working on an inventory
and that the question has been raised on how much waterfront land
does DOT own? In talking with them, DOT has multitudes of file cabinets
full of land they own. Jacquie would like to see other state agencies
work on an inventory of their property as well. DES, DRED and F&G
all have waterfront property. To address Paul's concern, the Board
is talking about the leasing of state-owned land which is the motion
before us.
Vice Chairman Tom Quarles
will compose a letter to the NH Council on Resources and Development
(CORD) to include the motion. It was agreed that the following committees
would be copied: Long Range Capital Planning, LMAC, RMAC, Chairmen
of the legislative committees and Governor and Council. In addition
to the motion, Carol Barleon requested that we include in our memo
the concern the Board has regarding public access.
Jacquie Colburn will
contact the Winnisquam Lake Association and report their position
at the April 3, 2006 meeting. Mr. Teutsch said he would keep the
Board abreast of any upcoming legislation and plans to attend the
PWAAB meetings on a regular basis.
4. Update on Harilla's
Landing - Vice Chairman Thomas Quarles
There has been little
follow-up since Paul Goodwin came before the Board last month. Mr.
Quarles has not heard from Mike Pillsbury from DOT to get him up
to speed. As stated at the February meeting, the land currently
is managed by DOT so we will need to move on the land swap issues
before we can proceed. It may be at least another two months before
we move forward.
5. F&G Project Update
- Daniel R. Lynch, F&G
Dan Lynch provided a
hand-out for each member's manual. This is a list of completed projects
by the Fish and Game Department related to boat access and whether
it was a trailered craft or cartop project. This list goes back
to 1991. Dan answered questions on how to read the report. He stated
that in 1995 the Board came up with a list of priorities on a County
level. This list was updated and provided to the Board six months
ago. This new list will be updated in a table summary. Also, Dan
Lynch will be providing information from the Office of Energy and
Planning's GIS database, which will give the Board a visual depiction
of where state-owned and controlled boat access exist on the public
waters of the State. Hopefully, this will guide the Board to set
priorities and determine where public access sites are needed. Information
relative to other state departments will also be referenced.
1. Pleasant Lake (Deerfield)
- Fish and Game owns the land. The design has been completed. We
have submitted the wetland's permit application and are waiting
to hear from DES.
2. Baxter Lake (Rochester)
- This is a site Fish and Game owns.
3. Hilton Park (Dover)
- Based on direction by the Board, using our consultants we developed
plans to provide temporary repairs to the existing ramp. Those plans
have been provided to the DOT who will be handling the application
for the wetland's permit.
4. Millsfield Pond (Millsfield)
- This is a parcel F&G leases. We have received the permit to
reconfigure some of the parking to control some of the run off and
drainage that has made the site not as user friendly.
5. Baker River (Plymouth)
- Fish and Game has submitted a wetland's permit to make modifications
to the existing site so that it meets the OSHA stairway requirements.
6. Big Diamond Pond (Stewartstown)
- This is an existing access. Fish and Game leases two lots from
the town which provides driveway access from the town road into
the property we own. We are working toward acquiring those 2 parcels.
7. Stratford Bog - A
site Fish and Game has worked in partnership with NH Environmental
Services/Dam Bureau. The dam area was reconstructed; the property
owner looked to provide a small area for formal parking and some
parking up by the dam. The survey has been completed and we are
looking to move forward. This would secure a permanent access opportunity.
8. Merrymeeting Lake
- 100% completed plan. Fish and Game has not submitted an application
for a wetland's permit. There are still ongoing discussions on the
waterline project that is going through the same area which also
serves the Powder Mill Hatchery.
9. Lake Sunapee (Newbury)
- Fish and Game has squared away with DOT what would be acceptable
treatment for the Intersection off Birch Grove Road with Route 103.
A letter has been sent to the Town of Newbury providing them that
documentation, and we hope to meet with them in April. In March,
we hope to meet with DES to go over the permitting project.
Chairman MacNeil asked
Mr. Lynch about the area near Stinson Lake (a road to public waters).
He informed the Board that this was a graveled access off the lake
and noted to Dan that there were some very large rocks near the
water. Dan was familiar with this and explained what he had seen
after making two trips to Stinson Lake. F&G is looking to make
improvements to this area. F&G also needs to clear up a right-of-way
issue a local store has in this area. In fall of 2005, Dan Lynch
and Pat Tate from Fish and Game checked the site and at least some
of the rocks had been removed (not by Fish and Game).
Out of 150 Roads to Public
Water sites that were done, there are 15 that Fish and Game oversees
and controls (federal money was brought to the table to do this).
The USFWS and the AG's Office have recognized that we have a vested
interest in those so we maintain them.
We do not have authority
to circumvent what was set out by Executive Council for the other
135. Responsibility lies with the town. Vice Chair Quarles asked
Dan, "You are not saying that you cannot take over roads to
public waters sites?" Could the town deed it back? Dan did
not know. However, the AG's Office has stated that Fish and Game
cannot move forward on these anymore. Mr. Quarles thought there
was an issue with DOT, and Mr. Lynch said that DOT does not have
the authority to given them to anyone. Johanna Lyons stated that
there would have to be an amendment to the original by road layout
by Governor and Council to do so. Mr. Quarles questioned whether
it was possible to put the town's maintenance responsibility back
to the State.
Tom Quarles asked Dan
Lynch if the Merrimack River site listed was Greeley Park, and it
was confirmed. Mr. Quarles thought Dan's proposal of a comprehensive
review of public access sites and needs state-wide was a great plan
and asked the timeframe. Dan thought May and shared the some of
the credit with Office of Energy and Planning because of their inventory
database they shared with us. He reviewed some of the holes in the
data to make it as accurate as possible, but without OEP's assistance
it would be difficult to put all the information together. Rich
Tichko will be following up with the other agencies (DRED, DES,
DOT) and hopefully in the end it will be a useful tool for the Board.
Chairman MacNeil questioned
how many years F&G published the Boat Access Map. Dan Lynch
said F&G is looking to update it and distribute it again. They
plan to make it even more useful.
5. Legislative Update
- Chairman Allen K. MacNeil
Jared Teutsch was asked
if he had any other bills of interest to discuss with the Board.
He noted he had discussed a few of the bills already. The speed
limit bill is still in the Transportation Committee and he believed
they would exec that bill out. Chairman MacNeil asked him to keep
him informed of the status of this bill.
Tom Quarles saw the proposed
bill on changing the boating safety and certification requirement
which would require an on the water test and Jared informed him
the bill passed the committee and should be on the consent calendar
the week of March 6, 2006 in the House. Jared asked Rep. Chaplin
for additional information. Rep. Chaplin stated that HB 1463FN passed
16-0 with the idea of improving items for safety. Tom Quarles was
surprised at this due to the cost that might be involved, but Rep.
Chaplin said the hiring of 5 people was dropped out and amended
so no additional state funds were required.
Jared Teutsch noted that
the NHLA originally opposed the bill because canoes and kayaks would
be required to carry flags. They did agree with safety education
and Jared believes the flags are still part of the bill. Dan Lynch
felt it would have to go to Finance because of the "FN"
notation, however, Rep. Chaplin said there was now no dollar amount
assigned to the bill.
Dan Lynch addressed HB
1426 as requested at the February meeting. It deals specifically
with State land in the City of Concord to square away land owned
by Brochu's Landscaping along Route 93. The owner was trying to
gain access from one area of land to another. It does not deal with
any access to the Merrimack River. There is a state boat access
downstream.
7. Hobo Railroad - Mike
Pillsbury/DOT
Mr. Pillsbury was not
in attendance at the March meeting, however, Johanna Lyons, subcommittee
member, addressed the Board. Johanna informed the Board that the
subcommittee met. She provided Carol Barleon and Mike with short,
targeted management plans so that Mike could start to look at how
to frame a management plan of public access to bring to his Commissioner.
It was suggested to put him on the agenda for the April meeting.
Mr. Quarles noted that
at last month's meeting there was a fundamental question raised
about the purchase of this land for wetlands mitigation plan in
the mid-90s resulting in restrictions on this parcel. He questioned
where that question stood and does it prevent any development in
that area. Ms. Lyons read the minutes and did not understand that
to be the issue. She clarified that it was a letter that went to
Audubon that talked about needing a management plan for this property
-- not an Audubon property but DOT property. They need to do a management
plan for the property that has public access involving other agencies.
There were some restrictions because portions were bought for wetlands
mitigation. Tom asked if Audubon was supposed to participate in
that plan, and Johanna replied, "No." Audubon just asked
for information about the property. Tom Quarles' other issue was
what is the extent of Hobo's lease? Johanna informed him that this
will be all part of the plan, and it will be tied up all as one
piece. Johanna Lyons will let Mike Pillsbury know he is on the April
agenda. Tom asked if public access is going to be part of the plan
because of the issues we have raised and was told it was because
the original plan in 1995 was never completed. Ms. Lyons referred
to page 30 in the brief discussion of the environmental assessment.
Tom asked how big this parcel was. Dan thought it was about 2,800
feet of riverfront. Carol Barleon informed the Board that Mike Pillsbury
does have a copy of the complete environmental assessment.
ADJOURNMENT
Dan Lynch moved to adjourn
the meeting. Seconded by Jacquie Colburn. Unanimously approved.
Meeting adjourned at 11:15 a.m.
<Return to top>
________________________________
PUBLIC WATER ACCESS ADVISORY BOARD MEETING
MINUTES
February 6, 2006
9:00 a.m. - NH Fish and Game Headquarters
Members Present: Allen
K. MacNeil, Chairman, Thomas Quarles, Esq., Vice Chairman, Carol
Barleon, OEP; Paul Blizzard, Roger J. Bellerose, Sr., B. David Bryan,
Rep. Duncan Chaplin; Jacquie Colburn, DES; Shari Colby, DRED; Cheryl
Killam, Gov's Commission on Disability; Michael Pillsbury, DOT;
and Daniel R. Lynch, F&G
Members Absent: David
Barrett, DOS; John Cowan, Maynard Goldman, NHLA; Brian Giles, Patricia
Goodridge, Senator John T. Gallus, Senator Joseph D. Kenney, and
Representative John Klose
Audience Members: Paul
Goodwin and Jared Teutsch, NH Lakes Association
*****************************************************************************
MEETING CONVENED
Chairman Allen McNeil
welcomed the newest member to the Board, Representative Duncan Chaplin,
who formally replaced Representative Howard C. Dickinson per a written
memo from House Speaker W. Douglas Scamman, Jr. dated August 2,
2005.
Vice Chair Quarles recognized
and welcomed new Board member B. David Bryan. This appointment was
the result of new legislation passed last year for the purpose of
creating a position for "coastal estuarine interests."
Mr. Bryant confirmed that he was a member of the Coastal Conservation
Commission and explained its purpose. Mr. Bellerose asked Mr. Bryant
to comment on Hilton Park and stated that everyone was disappointed
that we would not see an "all tides" dock.
Mike Pillsbury from DOT
was reintroduced as the new member to the Board from The Department
of Transportation for anyone who had not yet met him.
Further, Mr. Quarles
introduced guest speaker Paul Goodwin who is here to discuss the
marine contractors' suggested recommendations to Harilla's Landing.
The meeting was called
to order at 9:03 a.m.
AGENDA ITEMS
1. Approval of the January
9, 2006, Meeting Minutes - Allen MacNeil, Chairman, PWAAB
Corrections to the January
9, 2006 meetings were as follows:
Page 2, paragraph 3,
1st sentence; add the words . . . the "New Hampshire"
Division of Historical Resources Assessment was completed and submitted
to (delete "them") the NH Division of Historical Resources
which did find the Laconia compound eligible for designation.
Page 2, paragraph last paragraph - change Sally Holden to "Sally
Holder."
Page 4, 1st paragraph, 3rd line down; - reword . . . "Further,
legislation passed last year which removed those properties purchased
with state and highway funds from the CORD review process, has caused
some confusion."
Page 6, item#7, 5 lines from the bottom; remove the "s"
Mr. Blizzard's name. Next sentence; change Mr. Blizzard to "Mr.
Lynch also informed the Board . . ."
Page 9, 3rd paragraph from the bottom; it was agreed that the minutes
would stand as they were written in that the . . . "sign has
not been there for 6-7 years."
Mr. Bellerose moved to
approve the minutes of January 9, 2006; seconded by Brian Giles.
The Board approved the minutes with one member abstaining (Carol
Barleon).
2. Update on Winnisquam
Access Site - Jacquie Colburn, DES
Jacquie Colburn gave
an update on the working group meeting of January 20, 2006. The
following items were discussed at that meeting: As reflected in
the January 9, 2006 minutes, the Historical Resources Assessment
was completed and submitted to the New Hampshire Division of Historical
Resources and the Laconia compound is determined to be eligible
for designation. Approval was received to remove the Butler building.
With that approval, Fish and Game has been working on a bid package.
There is a meeting scheduled for potential contractors to bid on
later in February. DES and F&G have been corresponding regularly
via e-mail to confirm that all necessary information is shared with
contractors and available to them. DES continues to work with Camp,
Dresser & McKee to finalize what is necessary to complete requirements
for the NH Historical Resources Division. The Fish and Game Department
continues to work on the need for review and assessment.
Prior to the last working
group meeting, Fish and Game mailed the waterfront design done by
Fay Spofford & Thorndike (FST) to the various permitting agencies.
Jacquie left word with Rich Tichko of F&G to coordinate a permitting
agency meeting to make a decision on the waterfront design. Prior
to the removal of the Butler Building, a demolition permit will
be required from the City of Laconia. Sally Holder of the Winnisquam
Lake Association offered her assistance in getting those permits
and working with F&G in getting them recorded with the City
of Laconia. Also, Rich Tichko informed the working group that Fish
and Game will have to attend a City of Laconia Planning Board or
Council meeting because of the passage of RSA 674; Change of Use.
Because of this new law, Fish and Game will need to notify local
community of this "Change of Use" on this property. The
next working group meeting is scheduled for Friday, March 3.
Vice Chair Quarles asked
if going before the Planning Board was an informational process
or an approval process and Ms. Colburn referred his question to
Fish and Game. Mr. Lynch felt that it was more a notification process.
Further, he was not sure we even needed to take any action under
RSA 674. Mr. Lynch noted that an Open House was held within walking
distance of the location to showcase the concept of the project
and to identify the intent of the land acquisition. Dan Lynch said
F&G was looking for clarification from the Attorney General's
Office as to whether this meets the requirements of that statute.
In January, Dan Lynch informed the Board that F&G had received
a memo from FST that laid out waterfront structural options and
the matching dredging area that would be required, which were sent
to federal FEMA, OESP (state-side of FEMA), NH DES, Army Corps of
Engineers, USFWS (Federal Aid Division) and the NH Division of Historical
Resources. The focus was to get pre-comments on a preferred waterfront
option because the waterfront will dictate what will occur on the
rest of the site in terms of grades for the parking area. The preferred
alternative is to have a wharf-type design which is in keeping with
the atmosphere in that section of the City. Across the river is
a wharf-type design for Martel's facility. The design allows for
no significant impact to the floodway capacities in the river channel.
Comments have been received back from FEMA and OSEP. They agreed
that the wharf-type option seems to be the best as it would allow
for maintaining the current amount of floodway capacity. They are
looking at putting in a ramp (which is setback and cut into the
bank) and a double wide floating dock. Upstream to the property
line and on downstream to the property would be the open wharf.
Boats would be able to launch, move their boat, tie off and go park
their vehicle. F&G has received some velocity information from
The Department of Environmental Services/Dam Bureau; however, they
are still looking for more input from the Army Corps of Engineers
and Dept of Environmental Services.
Dan Lynch explained that
no dock borings had been done. Based on boring information, the
original planning was problematic. It was determined that the sheet
piling would not be down far enough.
Mr. Giles asked Mr. Lynch
to explain the wharf configurations and traffic patterns as the
river was not too wide on that part of the river. Mr. Lynch explained
that there are no docks coming out on Martel's side. The impact
in terms of narrowing would not create a traffic situation. In terms
of the volume of activity in that channel, right now Fish and Game
leases the parking area that supplies 42 vehicle and trailer spaces.
F&G will be reducing the parking area by 11 trailer spaces.
Mr. Bellerose stated that most traffic would be downstream. The
ramp is slated to be installed on the north side of the F&G
property.
3. Update on Harilla's
Landing - Vice Chairman Thomas Quarles
Vice Chair Tom Quarles
reviewed the background of the public Open House held last August,
which included DOT Commissioner Carol Murray, F&G Executive
Director Lee Perry as well as residents, boat users, and an area
contractors group to discuss ways to best refurbish this access
site and meet all the users' needs. As a result of that meeting,
we agreed that the contractors group would meet and come up with
a conceptual design plan that would address their needs and have
space for all other user groups; then meet with DOT and F&G
and move forward with renovating this contractor's area as soon
as possible.
Mr. Quarles introduced
Mr. Paul Goodwin of Watermark Marine Construction, representing
the contractors group, to review their working plan. Mr. Goodwin
distributed copies of their proposed plans and gave a brief history
of his personal involvement of this site over the years. Mr. Goodwin
reviewed the scanned DOT map which the group used as a guide in
planning out their proposal. He explained what you would see as
you rode down into the site and that the right side of the dock
appeared to cross the property line between the State and Harilla's
Landing Yacht Club. The dock area near the existing launch ramp
has a retaining wall with good water depth. He explained the "T"
shaped structure which is used by Sandy Island is in rough shape.
Where the contour lines turn the corner the water is very deep.
This would be very good for launching or docking a boat. He further
pointed out to the left of this area the existing launching area.
Two things further (1.) off the point are two electric cables that
supply the island, which he was not sure where they went, and (2.)
there are six rather large boulders that are potential dangers (data
came off a DOT plan). It is estimated they are 3-4' below the surface.
Mr. Goodwin said the
plan would need to separate commercial and residential because you
cannot use federal funds for commercial use. He also talked about
a proposed area for commercial access for loading and unloading
only and a barge ramp. He also pointed to an area that may need
dredging and rock removal. There would be delineation between the
commercial and public side.
The contractors group
concluded that they do not necessarily need docking space. He noted
that the public uses the existing ramp for shopping, etc. Therefore,
on the plan it was marked "proposed public access load and
unload dock," so cars could pull up to the area. On the commercial
side it was geared for a truck to come and go.
On the left hand side
of the plan, Mr. Goodwin referred to the concrete pad. He asked
Mr. Quarles to clarify if this was abutting someone's property.
Mr. Quarles clarified that the abutter to the east complained about
those docks because if you naturally draw their property line into
the water there is an encroachment. As part of a survey, it was
noted that the Yacht Club has a corner of their property in this
area. Mr. Quarles said it has turned out not to be as much of a
problem as anticipated.
Moving forward, wetlands
permits would have to be applied for. You would need DES permission
for rock removal. If Harilla's Yacht Club and the State were both
applicants, the permitting will be easier.
Mr. Goodwin stated that
a lot of erosion has occurred over the last 20 years to the area
and the dock. He was guessing that water erosion from the road has
caused a lot of damage.
Before opening for comments,
Vice Chair Quarles reviewed the goals first established in August
for this project. There was consensus from the beginning that there
were problems, but if the separation from the commercial from the
general public users could be identified and accounted for in the
conceptual plan then we could have the contractors take over on
an "in-kind" basis to do the work on their site. Before
this, you need a conceptual plan and a buy-in from the agencies
involved. This is the direction we hoped to move toward. In terms
of the property line issues, the conceptual agreement from the Yacht
Club is to do the land swap which would take a portion of land near
the shoreline where there are some of the Yacht Club's seasonal
docks. In concept, they have agreed to swap all that land (which
includes the concrete pad on the diagram) with the sliver of land
they are encroaching on. They still need access to the seasonal
docks (condo owners own these docks); therefore, we would need to
keep road access available in the plans while at the same time using
that land for our purposes as public access.
Mr. Quarles was impressed
with Mr. Goodwin's concept and presentation. He did ask about the
electrical substation as shown on the map. Mr. Goodwin believed
there were actually two and showed where he thought they were located.
He believes that in the wetland area near the wharf there is one
old cable that is not connected. He believes it is owned by NH Coop
not Public Service. He offered his services as well as those of
the group to assist in getting the permitting process in place.
In looking at the plan,
Roger Bellerose had a wetlands question dealing with the left of
the launch area where there used to be a retaining wall. The Board
was informed that it was actually filled in. Mr. Goodwin noted that
it is actually paved quite close to the dock.
Board members questioned
what the next steps were for moving forward with this project.
Mr. Quarles clarified
that at the meeting in August it was made clear to attendees that
because of the federal funding requirements that this site be open
24 hours per day to recreational boaters and fishermen and that
the prime parking would be reserved for those intermittent, temporary
users. It could not be used by Yacht Club people, island owners
or others in the area. He did not hear any protests at the meeting,
though this does not mean there will not be problems. At various
times in the summer (referenced DOT photos) parking is a mess and
will need to be policed. The town at this time enforces parking
and will tow a trailer that is not registered. The non-recreational
attendees at the meeting knew if they were going to park for more
than a temporary loading and unloading basis, they would have to
park off the F&G site onto the state area maintained by DOT.
We also talked about the 50' (25' from center line) right-of-way
on the road which would give enough space for head-in parking. It
is a big issue but not insurmountable. The next step would be to
push the two departments (DOT and F&G). In the last year that
we have been working on this site, neither department has taken
the lead. It is now time to get an engineer to sit down and start
to do assessments and concepts. Now that we do have a conceptual
design by a contractor, we will need to hear back from the departments
through Commissioner Murray and Director Perry so that this site
is on F&G's radar along with Sunapee and Winnisquam.
Mr. Bellerose felt it
would be advantageous if we could isolate and remove the boulders.
Mr. Goodwin felt that decision would be up to DOT because they are
the applicant and own the land. He felt that everyone could help
get the work done. Mr. Goodwin told Chairman McNeil he had the equipment
to remove the rocks. Dig-Safe cannot help because they do not chart
electrical cables in the water.
Chairman MacNeil said
we could not proceed without the two departments (DOT & F&G)
on board.
Tom Quarles reminded
the Board that Mike Burlage was the DOT contact before he left for
active military duty. So far there is no replacement from DOT. He
did note that Mark Morrell from DOT's Gilford District had been
very actively involved on the project and that there had been a
couple of meetings with DOT attorneys in the past.
Mr. Pillsbury was not
aware of DOT's involvement but offered to look at the files and
work with Mr. Quarles.
Dan Lynch praised the
contractor group's design. He felt that Fish and Game has no authority
because DOT owns the land. In terms of providing the funding, we
have state boat access funds and access to federal funds. Tom Quarles
has laid out what activities exist for federal money but he was
not sure if the premise of the state wide boat access fund is to
fund commercial activity. F&G could start to initiate an answer
to this question with our representative at the Attorney General's
Office. He did feel there are in-house issues that DOT needs to
work out first to clear up the land issues.
Mr. Lynch clarified for
Mr. Quarles that Fish and Game can supply just funds having done
so in the past for other projects done by other agencies. Mr. Lynch
was familiar with federal eligibility and suggested as we move forward
we could look at improved plans and designs and to get clarification
of the statute on what we can do with the public water access fund
(is any intended for commercial). Identify what that money can be
use for and then what we don't have a funding source for, Paul Goodwin
and his group might be willing to do.
In discussion with Paul
Blizzard, Vice Chair Quarles did not see any insurmountable ownership
issues with the Yacht Club to do the land swap. The state owns the
underlying lake bed and we had DES representatives involved. As
long as you can show this is a public purpose, DES will approve
it. Federal funds do not allow for just commercial use. If it was
mixed commercial and recreational use, they would consider funding.
Mr. Quarles felt that three of the areas proposed by the contractors
(from right to left on the map) would qualify but the fourth would
clearly be a commercial use.
Assuming the funding
did come from the access portion of F&G, Roger Bellerose asked
Dan Lynch if F&G would take over maintenance, and Dan told him
it would depend on who owned the site. This is something DOT needs
to address in terms of property, and he cannot speak for them. Further,
he was not sure if this project needed to go through the CORD process.
Paul Blizzard asked Paul
Goodwin about parking usage and was told about 50% is people from
the Islands. He explained that the Town of Moultonboro will only
tow a car or trailer that is unregistered and that folks have been
known to leave vehicles there all summer.
Mr. Goodwin informed
the Board that for approximately 16 years his construction company
has offered to help with this site, and offered to do it for free.
Mr. Quarles felt there was considerable work to be done that must
be above and beyond what his company would be able to do for free.
Tom Quarles clarified
for Carol Barleon that it was not an option to use the current lot
rented by contractors up the road. We had considered buying it for
satellite parking but that is not going forward.
4. F&G Project Update
- Daniel R. Lynch, F&G
Dan Lynch provided the
Board with the Public Water Access Project Team Meeting January
26, 2006 Minutes as promised at the January 9th meeting. He reviewed
the purpose of the monthly meetings and who generally attends from
Fish and Game.
1. Baker River - After having received public input on a concept
that was presented to the Town of Plymouth, Board of Selectmen,
F&G is moving forward to obtain an amended wetland's permit
to do the work. We have a power construction sequence laid out,
final plans for the site, met with a representative from DES the
first of February and now will be working to apply for an amended
wetland's permit. F&G plans to do the retrofit on the facility
over the next construction season.
2. Pleasant Lake (Deerfield)
- Received the final plans in early January. F&G submitted wetland's
permit 1st of February and expect to hear from DES soon. There is
a mitigation component that F&G needs to comply with because
of the wetland's delineation (part of the land we own will be left
to meet the delineation requirements).
3. Merrymeeting Lake
- 70% completed plan. There is a willing seller but we do not have
a sale and purchase agreement signed for land to be used for the
parking area. They are waiting for additional information on the
proposal for the replacement of a water line to the Powder Mill
Hatchery which is adjacent to the boat access facility. The consultant
should have information in early February. Then we hope to have
purchase and sales agreement, complete the land acquisition and
move forward on submitting a wetland's application.
4. Baxter Lake - Contracted
with the DES/Dam Bureau to do the work. The draw down was unable
to be completed this fall, and we are looking to extend our completion
date into early spring or fall so water can be lowered and the concrete
logs put into place. The road going into the parking area is complete,
ramp usable and base materials in place for concrete logs.
5. Orford - Discussion
with AG's Office set for February 7 to finalize agreement with the
town. The final discussions between town and their attorney have
to do with the term of the lease agreement. The log ramps have a
30 year useful life and there was a question on when that begins
and ends. If F&G made improvements in 20 years, would that restart
the 30 year useful life. F&G has worked out something agreeable
with the town but need to get the AG's approval.
6. Forest Lake (Winchester)
- Historically, an access site to the lake. F&G had stocked
the lake because this location had provided public access. The landowner
wishes to maintain access to their area of back land. There would
be a driveway area to the boat launch facility.
Brian Giles asked for
comments on the work shown on the Mylar of the Hilton Park site.
Mr. Lynch reviewed for Brian that back in the summer it was agreed
between F&G and DOT that F&G's engineering firm would come
up with some plans for repairs to the existing ramp such as quick
set concrete to fix pot holes and class C stone to repair the sides
of the ramps. These are the plans that were concluded and provided
to the Turnpike Bureau. They are moving forward in obtaining the
wetland's permit from Dept. of Environmental Services. Once that
permit is received, F&G would facilitate getting the work completed.
Mr. Pillsbury said it would be difficult to determine when to schedule
the work until the wetland's permit is received which could be 2-3
months.
Chairman MacNeil asked
if these items would be in the Fish and Game's Annual Report. Dan
Lynch will get his report to Chairman MacNeil for inclusion.
5. Legislative Update
- Chairman Allen K. MacNeil
Mr. MacNeil referenced
a recently passed house bill relative to day and night lake speed
on Lake Winnipesaukee and all the great ponds in the State of New
Hampshire and now has been passed onto the Senate. The Chair has
e-mailed the Speaker of the House and Senator Johnson for support.
Mr. MacNeil asked Jared Teusch of the New Hampshire Lakes Association
for comment. Mr. Teusch concurred that the bill did pass 193-139
February 2, 2006, and he encouraged continued support through the
Senate. He stated that the bill is a retained bill from 2005, and
will be heard by Senator Bob Letourneau and the Transportation Committee.
Mr. Teusch referenced
HB 1684 (a NH Lakes Association bill) dealing with the leasing of
state-owned waterfront property which is before Rep. Chandler's
committee on Public Works in the House. A legislative committee
is being created to look at a number of issues such as what are
the roles of the Lakes Advisory Management Committee and Rivers
Advisory Management Committee in the CORD process and what is PWAAB's
role in commenting on the leasing of state-owned lake front property.
RSA 228 allows for $25 per linear foot per year. NHLA feels that
amount is too low, mainly because when that lease is granted that
person's property value is increased 2-3 fold. He discussed the
value of just leaving it alone. He will keep the Board advised of
the status and e-mail the Chairman. The PWAAB secretary will supply
him with e-mail addresses of the Board.
Vice Chair Quarles asked
Jared about the House vote on HB 1684, and he did not know at this
time. Originally, the bill had a moratorium and is no longer part
of the bill. When Legislative Service drafted the final bill, they
changed it from a study committee to a commission. NHLA did not
want another commission looking into this; it only wanted the issue
looked at by the law-makers. Hopefully, the bill will be changed
back to a committee. There was some opposition to the bill from
developers and attorneys.
Tom Quarles asked Jared
the status of HB 1228 relative to the sale or lease of state-owned
real estate, which requires state agencies to charge an administrative
fee for costs incurred by the agency in preparing the sale or lease
of real property, and he was informed that bill passed the Public
Works Committee. It should then go to the Floor and back to Finance.
There is a third bill
being presented by Rep. Gene Chandler (could not recall the HB number)
that looks at the CORD process. HB 1684, HB 1228 and this third
bill are all inter-related, and there is talk of integrating HB
1684 with Gene Chandler's bill. Rep. Chandler's bill is simply looking
at the CORD process.
Vice Chair Quarles reviewed
F&G's legislative list provided at last month's PWAAB meeting
and felt there may be two other bills the Board might wish to review
that might concern public waters. He asked for F&G to research
and report back their findings. They were HB 1364 - establishing
a commission to study the best use and possible transfer of certain
state-owned land in the Town of Brentwood, and HB 1426 - granting
a right-of-way to use parts of state-owned land in Concord within
the I-93 corridor.
Dan Lynch informed him
that HB 1364 dealt with Fish and Game property known as the Brentwood
Game Farm, which up until December 2004 the University of New Hampshire
used as part of their wildlife education classes and opted not to
continue to utilize this facility. We have had discussion at F&G
as to what we would do with the property. F&G has had calls
from the town wishing to have it left as open space, looking to
see if it could be sold to be used as a school, public safety complex
or public works. The bill was submitted to see what could be done
with it. At that time, we were looking to leave it as open space.
Director Perry has testified the town is aware of this and to the
best of his knowledge the bill was ITL; therefore, the bill is gone.
Mr. Quarles asked if there was any public water on this property
and was told no.
Dan Lynch was not familiar
with HB 1426 but informed Mr. Quarles that he would have Fish and
Game look into it.
Mr. Teusch informed the
Board that he would keep the Board abreast of any upcoming legislation
and plans to attend the PWAAB meetings on a regular basis.
6. Hobo Railroad - Mike
Pillsbury/DOT
Mr. Pillsbury reviewed
briefly the discussion that took place at the January 2006 meeting
and distributed a survey map for the Board to review. The map showed
the various right-of-ways, rail crossings and other areas as mentioned
in previous meetings. Mike Pillsbury clarified previous questions
about whether the State owned all the way from Route 175 to the
river and he said it does. Its lot is bisected by the railroad and
has an active rail line crossing which creates a lot of liability.
The access road from Route 175 has an easement to the property used
by the utility company.
In 1997 the Audubon Society
requested an environmental assessment. Mike Pillsbury provided copies
of DOT's April 9, 1997 response to Audubon, in which it referenced
an attached environmental assessment of this parcel of land in Woodstock.
Mr. Pillsbury believes the management plan was never finalized by
the various state agencies.
Mike Pillsbury pointed
out the location of the "Polar Express" on DOT's survey
map for the Board. Chairman MacNeil said anyone traveling to Lincoln
cannot miss it from the road. Mr. Pillsbury believes they have approval
to be there but at the Chair's request offered to look further into
this facility.
Vice Chair Quarles asked
that DOT initiate working again on the 1995 management plan. It
was determined the property was acquired at that time. Mr. Quarles
noted that at the January meeting the Board requested a copy of
the Hobo lease (not what they pay but what is their leasehold).
Within this plan, the Board would like to know if Hobo Railroad
has rights other than the railroad corridor. He further asked Mr.
Pillsbury if DOT knew whether the Hobo Railroad uses the gravel
pit. Chairman MacNeil thought it might be the town, but Mike Pillsbury
said he would look into who used it and who has the rights to it.
Dan Lynch thought the
lease might be null and void if this parcel was acquired for wetlands
mitigation for Pemigewasset River projects if the page 30 of the
environmental assessment document is correct. He was not sure if
a lease to Hobo Railroad complicates the completion of a management
plan. Tom Quarles assumed the railroad was there before DOT acquired
the property. Mr. Pillsbury noted that not all 30 pages of the plan
are attached to the Audubon letter of 1997; only those pages relative
to wetland mitigation. Mr. Quarles felt the Board should have the
full document and Mr. Pillsbury would check DOT archives.
Mr. Bellerose questioned
the access across the property that showed power lines and was told
there was a recorded deed. How does this relate to public use not
Public Service? Mr. Pillsbury clarified that is why we are coming
back to this discussion. It would be the owner and then the easements
to it not a public road. We need to develop a plan to achieve access.
Tom Quarles suggested
a Subcommittee work on this issue. Mike Pillsbury is the Subcommittee
Chair, Johanna Lyons and Carol Barleon also volunteered to serve.
It was opened to anyone else who wished to volunteer.
Annual Report - Chairman
Allen MacNeil
Chairman MacNeil continues
to work toward getting this finalized. We will supply electronic
copies to the Board.
Cheryl Killam, Governor's
Disability Commission, was inadvertently left off the PWAAB list.
Coordinate with Public Affairs to be sure she is on-line.
CORD - State Owned Land,
Surplus Review - Vice Chairman Tom Quarles
SLR 06-001 - Tom Quarles
distributed copies of a new State Owned Land Surplus Review for
the Town of Belmont that the Board will need to review and vote
on at the March 6 meeting. Mr. Quarles said this was a very important
project involving a proposed development on the shores of Lake Winnisquam
near Mosquito Bridge which has been in the news and the Laconia
Citizen. The article will be sent with the minutes for review. He
referenced the map and subdivision plan of undeveloped land that
would need a rail crossing in order to get to the shore for a docking
system. This is similar to the 18 mile development in Meredith on
Winnipesaukee. He felt this needs to be reviewed with great care
because it would be taking undeveloped shoreline and transferring
property ownership to a developer who stands to make large profits.
Tom reviewed the CORD
process that is done through DES and asked Ms. Colburn if DES had
their legal opinion from the AG's Office as to whether the LMAC
or RMAC can veto a proposed state surplus land disposal. Jacquie
Colburn had talked with Mike Walls previously, and she and Mike
Couture hope to expedite a reply from the AG's Office.
Dan Lynch said that at
the last CORD meeting he attended they had abstained from taking
action on a surplus land disposal and actually went out on site.
CORD was waiting for an opinion from the AG's Office on their role
in the process.
Jacquie Colburn mentioned
that Mary Ann Manoogian, Director/Office of Energy and Planning
has resigned. Jack Ruderman is now Acting Director.
Carol Barleon moved to
adjourn the meeting. Seconded by Mike Pillsbury. Unanimously approved.
Meeting adjourned at 11:20 a.m.
________________________________
PUBLIC WATER ACCESS ADVISORY BOARD MEETING
MINUTES
January 9, 2006
9:00 a.m. - NH Fish and Game Headquarters
Members Present: Allen
K. MacNeil, Chairman, Thomas Quarles, Esq., Vice Chairman, Jacquie
Colburn, DES, Paul Blizzard, Roger J. Bellerose, Sr., B. David Bryan,
Brian Giles, Maynard Goldman, NHLA, Cheryl Killam, Gov's Commission
on Disability, Johanna Lyons, DRED, Michael Pillsbury, DOT, and
Daniel R. Lynch, F&G
Members Absent: Carol
Barleon, OEP, David Barrett, DOS, John Cowan, Patricia Goodridge,
Senator John T. Gallus, Representative John Klose, Senator Joseph
D. Kenney, and Representative Howard C. Dickinson
Audience Members: Brian
Lombard, Bureau of Rail & Transit (DOT), Gene Porter, ACBS Nashua,
and Don McGinley
*****************************************************************************
MEETING CONVENED
Chairman Allen McNeil
welcomed everyone and introduced two new Board members of the Board;
B. David Bryan of Coastal Conservation Commission and Michael Pillsbury
from the Department of Transportation. Mr. MacNeil also introduced
two guest speakers; Bryon Lombard, NHDOT Bureau of Rail and Transit,
and Gene Porter of Nashua, Vice President of the Antique and Classic
Boat Society International.
The meeting was called
to order at 9:06 a.m.
AGENDA ITEMS
1. Approval of the December
5, 2005, Meeting Minutes - Allen MacNeil, Chairman, PWAAB
Corrections to the December
5, 2005 meetings were as follows:
Page 5, paragraph 4, first sentence; add the word "access"
following the words "all tides."
Page 5, paragraph 8, first sentence; change . . . "me"
to Director Perry to "meet" . . .
Attendance changes as follows: Brian Giles was in attendance. Johanna
Lyons did not attend.
Vice Chairman Tom Quarles
moved to approve the minutes of December 5, 2006; seconded by Paul
Blizzard. Unanimously approved.
2. Update on Winnisquam
Access Site - Jacquie Colburn, DES
Jacquie Colburn and Dan
Lynch gave an update on the Winnisquam Access Site. It was confirmed
that the F&G MOA had been signed and that Governor and Council
approved Fish and Game's request for the acquisition of the City
of Laconia parcel at the December 21, 2005 G&C meeting. Funds
were conveyed to the City on December 23, 2005, and the deed was
recorded. Fish and Game is now owner of the approximately 1.4 acres
of land. Also, on December 21, 2005, the Governor and Council approved
the MOA between The NH Fish and Game Department and the Department
of Environmental Services for a portion of the Laconia compound
in the area of the Wastewater Treatment Plant. This is part of the
new parcel Fish and Game owns. Items surveyed for Laconia were registered
with the Registry of Deeds. Attached to the MOA between DES and
Fish and Game was a delineated plan of the site showing the area
that would be managed by Fish and Game and the remaining area of
the Wastewater Treatment Facility known as the Wastewater Compound.
Coordination was done with folks at the Laconia compound to try
to best meet their building access needs while still meeting our
needs for a sufficient turning access to the boat access site.
Jacquie Colburn reviewed
the environmental assessment for the Laconia project. Phase I and
II was completed a few months ago. The two technical investigations
have been completed and were favorable. Regarding site investigation,
FST engineers/consultants are still working to put together plans.
Dan Lynch handed Jacquie a packet of permitting information. She
will be working with Fish and Game and FST to put together another
on-site permitting meeting with all the permitting agencies to review
what is proposed and to move forward with a wetlands permit, flood
control permit, Corps of Engineers, and so forth.
Ms. Colburn reported
that the Historical Resources Assessment was completed and submitted
to them. The New Hampshire Division of Historical Resources did
find the Laconia compound eligible for designation. We went through
this process because the structures on site are more than 50 years
old and because of the use of federal funds. Approval has been given
to have the Butler Buildings removed, however, DES met with Historical
Resources in mid-December and DES needs to do some additional paperwork
relative to other structures on site. The Laconia site also has
some piping work that needs to be done, and we need to know what
and when work can be completed. We need to be sure we are in compliance
with Section 106 of the federal law.
Jacquie Colburn asked
Mr. Lynch about the NEPA review and assessment. As a result of the
August Open House, Mr. Lynch noted that comments were compiled and
a lot of the baseline work done. An environmental document needs
to be submitted in order to apply for a federal grant. The final
piece is a set of plans which are 90% completed. We need calculations
done for floodway and floodplain analysis as part of this environmental
document. Fish and Game hopes to meet with the USFWS representative
who signs off on the grants as soon as possible to review the environmental
documentation to ensure it answers their questions and to hopefully
shorten the review time.
The next working group
meeting is scheduled on site for Friday, January 20, 2006.
Dan Lynch informed Chairman
MacNeil that Governor Lynch would like a ribbon cutting April 1,
2006. The consultants FST need 6-8 week to get a set of completed
plans. In terms of federal aid, we need to answer the 12 questions
on the NEPA Checklist. F&G would like to submit this checklist
with the grant to shorten the approval process by 30 days. In that
Fish and Game needs comments back from the US Fish and Wildlife
Service, Dan did not see an April 1 completion date but maybe an
April 1 construction date.
It was noted that there
is no replacement yet for Fred Towle of the Winnisquam Lakes Association,
however, Jacquie Colburn informed the Board that his sister Sally
Holder has stepped in and attended the last three or four meetings
to assist with the site. Chairman MacNeil informed the Board that
the Winnisquam Access site has been named in memory of Fred in thanks
for his tireless efforts on this site. The plaque has already been
purchased.
3. Update on Harilla's
Landing - Vice Chairman Thomas Quarles
Vice Chair Tom Quarles
was able to reach Paul Goodwin, one of a number of interested contractors
in the area, who expressed a desire to make suggestions on Harilla's
Landing. Mr. Goodwin has met with David Farley and one other contractor
(Russell) and they preliminarily came up with an idea of taking
a portion of the left side of the ramp as you are looking at the
lake (the side away from Harilla's Landing). Mr. Quarles asked for
a sketch, however, the contractors have not completed one, however,
they plan to meet to come up with a more finalized plan and report
back to him. If possible, Mr. Quarles asked for a representative
to attend an upcoming PWAAB meeting.
4. Update on Plymouth
Boat Ramp Project - Daniel R. Lynch, F&G
Baker River Site abutting
the Smith Millennium Bridge - This site consist of a set of benches
leading down to the water. The Public was not pleased with the original
concept so with meetings on site and at least one meeting with the
Board of Selectmen to present an alternative, Fish and Game proposed
to change the benches, put in some stairs on each side as well as
removable railings. Our construction crew has met with FST on the
amended wetlands permit. In order to do this, F&G has to provide
DES a construction sequence which has almost been worked out with
FST and F&G. FST is working on final plans to receive these
railings. The railings would be put in place in the latter part
of the spring and taken out in late fall. F&G is looking to
meet with FST to retrofit the site. Dan answered questions on the
new concept of benches and stairs for the committee.
5. Annual Report - Chairman
Allen MacNeil
Chairman MacNeil informed
the Board that the PWAAB Annual Report for 2005 was almost completed.
As soon as all the reports are submitted, he will compiled them
and distribute the finalized report to Board members as well as
to the Governor, the President of the Senate, and the Speaker of
the House.
Mr. Bellerose referenced
his report and reiterated that he felt the Governor should get involved
in the Hilton Park site in terms of the land being transferred from
DOT to DRED. Chairman MacNeil said he could not begin to speak for
the Governor but offered to make reference to this suggestion in
the Annual Report and/or meet with him to discuss it.
Johanna noted that DRED
sites (Rye Harbor, etc.) in that area had been transferred to Ports
and Harbors Authority. They maintain boat launches on the seacoast
and she suggests we contact them.
6. CORD State Surplus
Land Disposal - Vice Chairman Thomas Quarles
Vice Chair Quarles and
Jacquie Colburn in coordination with the Lakes Management Advisory
Committee (LMAC) and Rivers Management Advisory Committee (RMAC)
met to review the State surplus land disposals. In the past, Mr.
Frost from CORD has attended a few meetings to discuss some of these
disposals but not on a regular basis. Our purpose was to get more
involved and coordinate with DES and other related committees such
as the 15 designated local river advisory committees under the RMAC.
Further, legislation passed last year which removed those properties
purchased with state and highway funds from the CORD review process,
has caused some confusion. Both the LMAC and RMAC has the authority
to review these projects and give their recommendations, and it
is ambiguous in the statute if they recommend against such a surplus
land disposal whether such a disposal can go forward despite the
negative recommendation. That issue is before the Attorney General's
Office for a decision. Jacquie has been working with DOT reps with
how this whole process works.
Ms. Colburn felt that
we were getting close to having a process in place as a result of
this statutory change. We realize that unless we hear otherwise
from the AGs Office, the LMAC and RMAC should still proceed with
the understanding that according to their specific program statutes
that the State shall not disposal of state surplus land until these
two committee have had an opportunity to review and make recommendations.
A memo has been drafted following a meeting with Bill Hauser and
Mark Hemmerlein from DOT. They have been working very closely with
DOT on this draft and have a process nearly in place which the LMAC
and RMAC thinks is very workable that will allow us a timeframe
to work with the local advisory committees to review and comment.
Within a few weeks, Ms. Colburn hopes to have a memo from the LMAC
and RMAC to forward to Commissioner Murray that states their recommended
process and hopefully Commissioner Murray will concur. We would
still have some surplus land reviews coming through CORD. Surplus
lands not going through CORD would come from the DOT and go directly
to the LMAC and RMAC. The other thing that we did include in that
memo was an opportunity to pass this information onto the Public
Water Access Advisory Board, which is referenced in that memo. When
Steve Couture from DES returns from Iraq the end of January, he
and Jacquie will do an initial review and forward onto the Chairman.
According to the statutes,
Vice Chair Quarles stated that the PWAAB does not have a voice,
but these agencies agree we should be consulted. As stated by Ms.
Colburn, this memo will be put our Board on par with these two DES
committees where we will get notice the same time as they do. This
will put us on a tight turnaround of 30 days. Since we have only
monthly meetings, we would probably need to leave any immediate
decisions with Jacquie Colburn, Chairman MacNeil and/or Vice Chair
Quarles.
In December, Tom Quarles
received 6-7 lengthy e-mails on this subject from DOT. Only two
of these e-mails impact public waters. Therefore, Mr. Quarles brought
before the Board for action the following two CORD items:
Project SLR 050-018 Harts
Location - Crawford Notch (easement)
In the White Mountain
National Forest, the federal government has a camp site in the area
of Harts Location. However, adjacent to the camp site is a state-owned
rail corridor. The National Forest wants an easement across the
state-owned rail corridor to access the Sawyer River, a tributory
of the Saco River. There is already public access suitable to shore
bank angler fishing. Vice Chair Quarles recommended that the PWAAB
inform CORD that we approve proposed disposal with no further conditions
or recommendations. The motion was made by Tom Quarles and seconded
by Jacquie Colburn and opened for discussion.
Mr. Bellerose questioned
where the Sawyer River was in relation to the Willard Mountain Trail
and Mr. Quarles explained the location of the site on Route 302
beyond Bartlett and that the campsite was well past Attitash off
Sawyer River Road to the left.
Maynard Goldman had no
problem with the CORD request, however, as a matter of procedure,
he felt it would be useful to the Board if these motions could be
typed or written out in a brief one to three sentence explanation
for review before action is taken. Mr. Quarles noted we did have
a deadline on this request but suggested we could work something
out for future requests.
Thomas Quarles moved
that the Public Water Access Advisory Board advise CORD that it
is in agreement with the disposal of state surplus land adjacent
to the Sawyer River, Project# SLR 050-018. Seconded by Jacquie Colburn.
Unanimously approved.
Project# SLR 05-0521
- Lamprey River, Epping
Mr. Quarles reviewed
this project which involved a piece of land along the bank of the
Lamprey River in Epping which is approximately 2 acres. In DOT's
correspondence with the PWAAB, however, it was closer to 4 acres,
and though the parcel is along the Lamprey River, it is not part
of the river that is designated under the RMPP. The RMAC, however,
still has jurisdiction to make a recommendation. This is a parcel
that would be recommended to go from a state public use to a local
public use. Mr. Quarles felt the Board might wish to discuss this
site since it was being transferred from state ownership to town
ownership which could possibly exclude non-residents.
Johanna opened the discussion
by asking whether this request would include the entire parcel that
includes the conservation area or would the parcel be restricted
to just the railroad portion. Mr. Quarles clarified that this land
(owned by the Bureau of Rail Transit) would be transferred from
DOT to the Town of Epping. The Town will maintain it as conservation
land.
Mr. Lombard stated that
he was not actively involved in this particular site but knew it
did not have an active rail line.
Brian Giles clarified
that there is a rail to trail system that is possibly maintained
by DRED or Fish and Game (old rail line) that goes from Portsmouth
into Manchester. There is already a town conservation park on one
side (20-30 acres). This parcel before the Board is just a small
parcel between the rail line and the river. Mr. Giles stated there
is a lot of history and background to this site, but felt it was
a good move to put it in the hands of the town. It can then be part
of the already existing town conservation land which is open to
the public with no restrictions. Mr. Giles informed Chairman MacNeil
that there were no fees charged to access this park. Mr. Lynch was
in favor of having some deed restriction in place to assure that
the parcel was open for general public access for fishing and boating.
Otherwise, the town could take some other kind of action down the
road.
Johanna Lyons and Cheryl
Killam discussed taking the no fee out of the motion and recommended
that there be a $1 or $2 fee. They felt the town should be able
to make improvements to the site without having to go to the local
taxpayers. Ms. Lyons agreed with Ms. Killam in that a small fee
would allow the town to make improvements to accessibility if needed.
Mr. Bellerose asked if the site was useable the way it is now. Mr.
Giles informed him that it was a very narrow strip of land between
the river and railroad with no road access to it so it does not
lend itself for an area for a boat launch. It would be for riverbank
fishing. It was requested that the Board amend the motion to ensure
the area be open for general public recreational use. Daniel seconded
the amended motion. With a show of hands, the amended motion passed.
Thomas Quarles moved
that the PWAAB advise CORD that the Board is generally in support
of this land transfer adjacent to the Lamprey River, Epping, as
long as there is a deed restriction binding on the transferee, Town
of Epping, that the land be open for public recreational use. Johanna
Lyons seconded the motion. Unanimously approved.
7. Hilton Park Update
- Daniel R. Lynch, Fish and Game
Mr. Lynch reported that
Commissioner Murray and Executive Director Perry met relative to
Hilton Park. He noted that the floating dock was removed about 2-3
years ago. It was removed because it needed repairs and was becoming
costly to maintain. Prior to this the dock had some level of commercial
use. A set of specs is being drawn up and the Marine Trades Association
is going to donate the materials and labor to construct it. F&G
will put it into place. This should re-establish this use. In terms
of the existing ramp that is on site, a few months ago PWAAB asked
F&G to meet with DOT to make remedial repairs to the ramp. We
have a final set of stamped Mylar's for these repairs for DOT. F&G
will be lending assistance to DOT to obtain a wetlands permit. Once
the permit is received, F&G can initiate repairs. Tom Quarles
asked if this floating dock would be adjacent to the access ramp
and Dan Lynch explained the location. Mr. Lynch informed Mr. Blizzards
that to his knowledge F&G Commissioner Glenn Normandeau was
the only contact related to the Marine Trades Association. Mr. Lynch
also informed the Board that he believed Ports and Harbors had been
brought into the mix. There was a brief discussion on why it might
make sense for Ports and Harbors to take care of the site. Mr. Bellerose
was informed that there are no plans at this time to address "all
tides" access.
8. Legislative Items
- Daniel R. Lynch, Fish and Game
Mr. Lynch distributed
copies of a 14 page handout compiled and reviewed by Fish and Game
on "2006 Legislative Service Requests" as requested by
PWAAB. The Board took a few minutes to review any items of interest.
Copies will be mailed to any member not in attendance at the January
meeting. The following LSRs were reviewed: 2474R, 2367R, 2812R and
2443R (HB1364). HB 1364 might be the only one the Board needs to
follow but not participate in. Johanna Lyons questioned the next
step, and it was suggested that a subcommittee be formed to track
any bills. Mr. Quarles suggested that since nothing appeared to
need immediately action, Board members could take some time before
the February meeting to review and report back.
9. Fish and Game Matrix
on Pending Access Site Projects - Daniel R. Lynch, F&G
Mr. Lynch had no additional
information to provide the Board at this time. Once a month the
access crew at Fish and Game meet to discuss the status of the various
projects. The group was to meet December 22 and again in January.
He will compile minutes of both those meetings for the Board to
review at the February meeting.
10. Greely Park, Nashua
- Gene Porter, VP, ACBSI
Chairman MacNeil introduced
Mr. Gene Porter, Vice President of the Antique and Classic Boat
Society International, to discuss a potential access site in Nashua.
As a private citizen in Nashua, Mr. Porter explained that he has
long been concerned about the lack of access to the lower portion
of the Merrimack River for public use where there is about 15 miles
of navigable water. Even though it once was an industrial area,
it is quite primitive. He explained that there is a decrepit, dangerous
boat ramp owned by the City of Nashua. He distributed a copy of
pictures of the area for the Board to review and a map from the
Chamber of Commerce of Nashua showing the area. His purpose for
coming before this Board was to find any avenues or take suggestions
on ways to continue to work with the City of Nashua and other interested
parties to improve this access. To date he has been unsuccessful
in sparking interest from local officials in this unused site. It
is owned by the City and is in the lower part of Greeley Park. Greeley
Park is the 2nd largest park in the City which extends east and
west across Concord Street and across the railroad tracks. The boat
ramp has a six foot drop off and is very dangerous to use. He had
heard a few years ago that Fish and Game was working on a site,
however, Mr. Lynch informed him that those plans had fallen through.
Mr. Greely only heard about this Board two weeks ago and came to
find out if this site was on the agenda as a potential site to be
restored, and if not, how he can help get it on an active list.
Chairman MacNeil clarified
that a former Board member had brought up a potential site on the
Merrimack River in Merrimack. Mr. MacNeil informed Mr. Porter that
the Board does have a program to work with communities. Unfortunately,
due to a change in staff in Merrimack and here, it did not happen,
and we do not know the status of the Merrimack site. Mr. Porter
reviewed the various public officials he has tried to contact but
to date has not made much progress. It appeared to Mr. Porter that
the City of Nashua is focusing more on the project on the Nashua
River and not the much larger Merrimack River.
Mr. Lynch's understanding
of the Merrimack site, which is off the end of Greely Street in
Merrimack, is that F&G has a land use agreement worked out with
the Town. The Town has not signed off on it because the neighbors
have expressed concern about the road into the site. You could not
get a boat through easily due to an almost hairpin turn that swings
back onto itself. The road then goes under a railroad trestle and
into an open floodplain area to get out to the parcel. F&G had
a concept plan all done for the town to showcase it to the town
legislative body. Pending any means to address access to the road,
F&G is still committed to performing the work on the riverfront
by providing formal parking and a formalized ramp. Once the road
issue is addressed, Mr. Lynch believes the town will sign off on
the agreement. When leaving the site, you must almost turn on yourself
to continue on the town road. An abutting landowner has concerns
about folks coming onto his parcel to make that turn.
Mr. Lynch informed everyone
that this site is on F&G's list as well as Greely Park (Merrimack
River) in Nashua. In August, F&G's Boating Access Coordinator
met with the City of Nashua to go over a land use agreement. There
have also been meetings with the Lower Merrimack River Council which
have indicated support. There are two issues the City has to work
out before F&G can finalize an agreement; a railroad crossing
to get from Greely Park through where the boat ramp is located,
and a sewer main that goes through the site (a manhole issue). Mr.
Lynch informed Mr. Quarles that the two individuals working on this
for Nashua are the City Engineer and the Director of Parks.
Mr. Quarles asked Mr.
Porter to clarify his earlier statement that the area he was referring
to provided 15 miles of navigable access from Merrimack River just
below the Budweiser Plant to Lowell, and Mr. Porter reaffirmed this
statement.
The proposed Merrimack
site Mr. Lynch discussed is north of Cromwell Falls which is just
below Budweiser. This site is about where the old "toll site"
used to be, therefore, it would not solve Mr. Porter's issue because
it is above Cromwell Falls.
Mr. Quarles was aware
of a car top access called the Depot Street Access site in Merrimack
where you can carry a non-motorized boat (under the railroad). Mr.
Lynch told them this was a different site owned by the town.
Mr. Quarles felt the
site Mr. Porter referenced should be of fairly high priority to
the Board. Mr. Porter noted you could access from Nashua to Lowell.
There is also a commercial marina in Lowell. There are 100,000 people
in the Nashua area who do not have access to this portion of the
river. Mr. Quarles asked Mr. Porter about the parking situation
at Greely Park, and he replied that he did not know what the requirements
would be, however, he felt there was sufficient space for development.
Mr. Lynch clarified that F&G is not the property owner so in
terms of the railroad and sewer main the City needs to address those
items. It was suggested that Mr. Porter continue to push the City
to take action to refurbish this as an access site. It was noted
that Fish and Game can enter into a long term lease (25-30 years
- life of the project) with the City. F&G will develop and maintain
it so it is beneficial to the City. Mr. Lynch did not want any misrepresentation
on how fast this site could be accomplished in that it takes time
and effort to deal with all the appropriate parties. It was suggested
that one area Mr. Porter might begin would be to check on any of
the title work with the City.
Mr. Porter expressed
his dismay that the State of New Hampshire did not apply for any
federal boating infrastructure grants considering the fuel taxes
we pay. It was suggested that Mr. Porter speak to Jacquie Colburn
about this issue. The Board offered their support to Mr. Porter
should he have further questions and concerns.
11. Hobo Railroad, Woodstock
-- Brian Lombard - Bureau of Rail & Transit
Chairman MacNeil began
the discussion by informing members that he will be putting together
a subcommittee to work on this public access issue. This item was
a continuation from December's meeting when Don McGinley addressed
the Board on the Hobo Railroad (access to the Pemigewasset River).
Mr. Lombard of DOT, Bureau
of Rail & Transit, came before the Board to supply information
forwarded to him by Mr. Burlage of DOT about questions raised on
access to this property on Route 175 in Woodstock. Originally the
question was why does DOT post "no trespassing" signs
on this road. He was not sure if at one time the road was open.
It was his understanding that between Rte 175 and the railroad tracks,
the property is owned by DOT (purchased in 1983). He was not sure
about the ownership of the land between the railroad and the river
but would work to resolve this issue. This section is where the
river has left the main channel which is quite a ways away from
the railroad corridor. The main channel of the river has taken about
10' of banking a year. He noted also that NH Coop has moved one
section of their utility poles. The access near Rte 175 is a dirt
road. He also referred to poor sight distance as you come onto Rte
175. As far as he knows, the road is maintained by the railroad.
They used to store some of their materials in the area as did the
power company. There is a crossing there for their use. A far as
creating a public crossing, we try to avoid it due to safety issues.
If the Board wants to pursue it, we will work with them.
Mr. Quarles informed
Mr. Lombard that at last month's meeting Don McGinley (a user of
that river) came before the Board to present his concerns about
the placement of "no trespassing" signs either by the
DOT or the Hobo Railroad. He thought possibly the Hobo Railroad
because this is the site for the Polar Express excursions over the
holidays. Mr. Lombard thought that this was new.
Mr. Quarles felt this
must be a change in use especially with the "no trespassing"
signs. If it is state-owned land, it was his opinion that it should
be open for vehicular access unless there is some safety issue.
If you have an access site that does not get a lot of use, he did
not see why the standard rail crossing signs could not be put up.
He further felt there was a need for an access of this kind in this
area. Mr. Quarles was interested in seeing a subcommittee go forward
and also to find out who has the authority to put up the "no
trespassing" signs and what are the rights of the Hobo Railroad
relative to its lease and the State's right to public access. The
Board does need to work within the rights of the Hobo Railroad but
thought the Board needed to find out where we stood in view of public
access.
Mr. Lombard noted that
there use to be a cable across the road which has since been taken
down. He believes it was posted that way because it was never set
up for public access. The Hobo Railroad never crosses the tracks;
it is only there to get to supplies. The crossing is a private one
for the railroad. The land between the river and the track is not
set up for parking.
He said there are three "no trespassing" signs up and
when the pit was vacated it was posted (signs are pretty old). Mr.
Quarles asked him if everything from the access road to the riverbank
was state-owned land and Mr. Lombardo did not know. He noted that
between the pit and Rte 175 was purchased by DOT in 1992.
Mr. McGinley noted there
has always been a cable, but it has not been up during the summer
months and the "no trespassing" sign has not been there
for 6-7 years. He further referenced second hand information from
an Amherst police officer familiar with the area who said it was
a Hobo Railroad employee who put up the signs, cable and yellow
tape and told him he couldn't be in the area. A new gravel road
had been put in just before the crossing (150 yards to a completed
Polar Express structure). The power pole is 75' back from the river.
He volunteered to work as a citizen on the committee.
Tom Quarles recommended
that we ask the Bureau of Rails to look at their title records,
determine ownership, and to provide us with a copy of the Hobo Railroad
lease. The Bureau of Rails does not own the bulk of the land, only
owns on either side of the corridor. The access road would fall
in that area.
Mike Pillsbury was concerned
about what lands were under DOTs jurisdiction, and if they were
to take the signs down, they could be opening liability issues.
Chairman MacNeil asked Mr. Pillsbury if he would be willing to chair
the subcommittee. Johanna Lyons volunteered to work on the subcommittee.
Tom Quarles moved to
adjourn the meeting. Seconded by Paul Blizzard. Unanimously approved.
Meeting adjourned at 11:15 a.m.
It was noted that July
3rd meeting has been changed to July 10.
--------------------
<Return to top>
<
Return to Main Public Water Access Advisory Board Page>
|